HomeMy WebLinkAboutAgenda Report - May 2, 2018 C-04TM
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA ITEM
C-4
AGENDA TITLE: Approve Plans and Specifications and Authorize Advertisement for Bids for Blakely
Park — North Pool Improvements
MEETING DATE: May 2, 2018
PREPARED BY:
Public Works Director
RECOMMENDED ACTION:
BACKGROUND INFORMATION:
Approve plans specifications and authorize advertisement for bids
for Blakely Park — North Pool Improvements.
This project consists of removing the existing concrete deck and
plaster/fiberglass pool finish and installing a new white plaster finish
and concrete decking, along with other miscellaneous
improvements.
The north pool was originally constructed in 1987. The existing plaster/fiberglass pool finish was installed
in 2001 with an expected 10 to 12 year life span. The plaster is currently blistering and breaking away
from the pool shell.
The pool decking received a polymer concrete overlay in 2006 or 2007. The polymer has been failing
over the past few years and the old deck cracks are coming through the polymer surface. In some cases
portions of the polymer surface have broken off causing immediate safety concerns.
This project also includes the replacement of the existing starting block platforms along with new
backstroke stations, pool deck tile markers, and two new main drains to meet the current public
swimming pool code requirements.
The plans and specifications are on file in the Public Works Department. The planned bid opening date
is May 23, 2018. The project estimate is $150,000.
FISCAL IMPACT: The project will have a minimal impact on annual maintenance costs, and
will reduce the City's exposure to claims related to the condition of pool
decking. This project will not impact the General Fund.
FUNDING AVAILABLE: The City will be using Community Development Block Grant funds. Specific
account information will be identified at project award.
Charles E. Swimley, Jr.
Public Works Director
Prepared by Sean Nathan, Senior Civil Engineer
CES/SN/tdb
Attachment
cc: CDBG Program Specialist
Parks Director
APPROVED:
Stephen abauer, City Manager
K:\WP\PROJECTS\PARKS\Blakely Park\2018 Pool Resurfacing\CPSA.doc 4/11/2018
Exhibit A
.40
1