Loading...
HomeMy WebLinkAboutAgenda Report - March 1, 2000 E-04AGENDA TITLE: Award Contract for Electric Utility Substructures, Turner Road/McLane Substation ($304,999) MEETING DATE: March 1, 2000 PREPARED BY: Electric Utility Director RECOMMENDED ACTION: That the City Council award the contract for installation of electric utility substructures (conduit and vaults) in Turner Road from McLane Substation easterly past Mills Avenue and westerly to Lower Sacramento Road/Woodhaven Lane to the low bidder, Golden State Utility Company, in the amount of $304,999.00. BACKGROUND INFORMATION: On February 9, 2000, eight bids were received and opened for this project. The bid results are shown below: Bidder Amount Golden State Utility, Sacramento CA $304,999.00 Crutchfield Construction, Stockton CA 328,746.65 Pacific Excavation, Elk Grove CA 337,145.00 QBC Inc., Dixon CA 381,775.00 Royal Electric, Sacramento CA 395,022.00 Underground Construction, Benicia CA 408,603.75 Norwood Construction, Pleasanton CA 417,918.00 Warren E. Gomes, Rio Vista CA 543,698.00 This project will install substructures (electric conduits and vaults) in Turner Road from McLane Substation easterly past Mills Avenue and westerly to Lower Sacramento Road/Woodhaven Lane. The substructures will allow the Department to install new high voltage cable systems for replacement of existing cable and conduit systems originating at McLane Substation. The existing facilities, installed in the late 1960's, are deteriorated and are no longer considered reliable components of the distribution system. The existing non -PVC plastic conduit system cannot accommodate today's cables in addition to having collapsed in several sections. This project will also provide necessary additional underground supply lines (feeders) from the substation to the existing and developing areas on the west side of the City. Plans and Specifications for this project were approved by the City Council at the meeting of January 6, 2000. APPROVED: . Dixon Flynn -- City Wanager FUNDING: Included in the Department's 1999-2000 Financial Plan and Budget, Distribution System Improvement (page E-26) Funding Approval: PREPARED BY: ANV/AMS/kf C: City Attorney Vicky McAthie! Finance Director /.,- Alan N. Vallow Electric Utility Director Al Smatsky, Senior Electrical Estimator APPROVED: H. Dixon Flynn -- City Manager RESOLUTION NO. 2000-28 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT FOR ELECTRIC UTILITY SUBSTRUCTURES, TURNER ROAD/MCLANE SUBSTATION WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on February 9, 2000 at 11:00 a.m. for Electric Utility Substructures, Turner Road/McLane Substation, described in the specifications, therefore approved by the City Council on January 6, 2000; and WHEREAS, said bids have been compared, checked, and tabulated and a report thereof filed with the City Manager as follows: Bidder Amount Golden State Utility, Sacramento $304,999.00 Crutchfield Construction, Stockton CA 328,746.65 Pacific Excavation, Elk Grove CA 337,145.00 QBC Inc., Dixon CA 381,775.00 Royal Electric, Sacramento CA 395,022.00 Underground Construction, Benicia 408,603.75 Norwood Construction, Pleasanton 417,918.00 Warren E. Gomes, Rio Vista CA 543,698.00 WHEREAS, the City Manager recommends award of the contract for Electric Utility Substructures, Turner Road/McLane Substation to the low bidder, Golden State Utility Company of Sacramento, CA. NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of the bid for Electric Utility Substructures, Turner Road/McLane Substation, be and the same is hereby awarded to Golden State Utility Company of Sacramento, CA, the low bidder, in the amount of $304,999.00. Dated: March 1, 2000 -------------------------------------------------------------------- -------------------------------------------------------------------- I hereby certify that Resolution No. 2000-28 was passed and adopted by the City Council of the City of Lodi in a regular meeting held March 1, 2000, by the following vote: AYES: COUNCIL MEMBERS — Hitchcock, Land, Nakanishi and Mann (Mayor) NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — Pennino C' M. EAI IMCHE ALLLICE City Clerk 2000-28