HomeMy WebLinkAboutAgenda Report - September 6, 2017 C-05TM
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA ITEM
C -5
AGENDA TITLE: Approve Plans and Specifications and Authorize Advertisement for Bids for Lodi
Station Parking Garage Maintenance and Repair Project
MEETING DATE: September 6, 2017
PREPARED BY: Public Works Director
RECOMMENDED ACTION:
Approve plans and specifications and authorize advertisement for
bids for Lodi Station Parking Garage Maintenance and Repair
Project.
BACKGROUND INFORMATION: The Lodi Station Parking Garage, located at 50 North Sacramento
Street, was constructed in 2002, using post -tensioned concrete.
Due to the age of the facility and observations of cracks in the
concrete and masonry, staff hired Siegfried Engineering, Inc. of Stockton, in October 2016, to conduct a
structural assessment of the structure. The assessment report (Exhibit A) identified several issues that
need to be addressed in order to maintain the parking structure's long-term structural integrity. It must be
emphasized that none of the identified deficiencies pose a risk to the public at this time.
This project will perform various minor structural repairs recommended by Siegfried Engineering, Inc. to
repair cracks in the concrete columns, beams, and concrete decks. The project will also replace some
exterior veneer panels that were damaged by vehicles; and address other miscellaneous improvements
needed to extend the life of the parking structure.
The plans and specifications are on file in the Public Works Department. The planned bid opening date
is October 12, 2017. The project estimate is $300,000.
FISCAL IMPACT: The repair will extend the useful life of the parking structures.
FUNDING AVAILABLE: Transportation Development Act (TDA) Fund
Charles E. Swimley, Jr.
Public Works Director
Prepared by Lyman Chang, City Engineer/Deputy Public Works Director
CES/LC/tdb
Attachment
cc: Transportation Manager/Senior Traffic Engineer
Public Works Management Analyst
City Engineer/Deputy Public Works Director
Siegfried Engineering, Inc.
APPROVED:
rl• Sc w!er, City Manager
K:\WP\PROJECTS\TRANSIT\Lodi Station Parking Structure\2017 Structural Repair\CPSA.doc 8/22/2017
SIEGFRIED
June 7, 2017
Lyman Chang
City of Lodi
Public Works Department
221 W. Pine Street
Lodi, CA 95240
Dear Mr. Chang:
Subject: Lodi Station Parking Garage
Structural Investigation
Enclosed you will find a set of construction documents for the Lodi Station Parking Garage repair project.
This includes;
1. A plan set that includes the locations of all repairs. We conducted detailed field reviews of all
potential repair features and have identified them on the plans. We also list two tables, one
identifying required repairs and repair priority and a second table indicating ongoing maintenance
activities recommended for this building.
2. A copy of the Geotechnical Engineering Report performed by Terracon Consultants, Inc., dated
March 21, 2017.
As a follow up to our April 29th, 2016 Structural Investigation Report and our "Draft" report dated February
17, 2017, the following is a brief summary of our additional findings and recommended actions for each
item identified.
1. Column To Beam Cracks
Our report referred to numerous cases where the columns have diagonal cracks at their intersection
with the deck beams. These cracks are in areas of very high shear stresses and were of immediate
concern.
We have conducted additional measurements and found most of the cracks to be less than 0.020
inches in width. The fissures in the paint and the accumulation of efflorescence due to moisture
weeping through the cracks makes most of them appear worse than they actually are. In general,
these cracks do not represent a structural hazard for current service loads. We recommend sealing
the cracks and painting the columns to prevent the intrusion of moisture and additional
deterioration. We also recommend regular period inspection of this condition.
We did find one column at the intersection of grids B & 14 with cracks up to 0.035 inches in width.
This crack width is an indication of potential structural disrepair. Therefore, we recommend more
significant structural repairs for this condition as indicated on the attached plans.
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.0121
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Page 1 of 3
l■
MT SIEGFRIED
In addition to our visual observations and measurements, we conducted a structural analysis of the
beam to column joints based on the 1997 Uniform Building Code which was in effect at the time of
design and construction.
Initially, we had reported a potential overstressed condition due to the seismic load effects
considered in our preliminary analysis. However, a more thorough analysis and review of
construction documents seems to indicate the original designer did not consider these frames in
the resistance of seismic loads. Using a rigid diaphragm analysis, the majority, if not all, of the
seismic load is considered to be resisted by the shearwalls at the north and south ends of the
building. Based on this analysis and Building Code prescriptions at that time, the beam to column
joints appear to be designed in accordance with the Building Code. We determined the building
columns to have an ultimate shear capacity 140 kips. The maximum calculated ultimate load in our
analysis was 140 kips. Therefore, the columns are reinforced at 100% capacity, satisfying the
building code criteria.
The attached geotechnical report indicates the possibility of foundation settlement. This settlement,
if it has occurred, would increase column shear stresses by another 5 to 10%. Though not desirable,
this slight overstress is not significant enough to make this structure unsafe.
Please note, the analysis performed only addressed the observed diagonal shear cracks. We did
not analyze other beam, column and slab elements.
2. Other Column Cracks
In addition to the diagonal column cracking in item 1 we observed horizontal cracking in many
columns. Generally, we found these cracks to be non-structural and not affecting the structural
integrity of the building. We recommend sealing and painting the structure to minimize moisture
intrusion into these cracks. Over time, the cracks will likely reappear and require ongoing
maintenance as indicated on the plans.
3. Slab Cracks
As previously reported, these cracks do not currently compromise the structural integrity of the
slabs but should be sealed to prevent further deterioration. The plans have denoted their location
and approximate total lengths.
In regards to the spalled slab areas, this will require a more substantial structural repair.
Details of the crack and spall repairs are presented on the attached construction documents.
4. Beam Cracks
As previously indicated, we found several isolated conditions where beams have experienced
diagonal cracking as shown in photo 5 of the initial report. At this time, the cracking is relatively
minor and does not represent a structural hazard. We recommend the cracks be sealed to prevent
further structural deterioration.
5. Masonry Walls
As previously identified, most instances of vertical and diagonal wall cracks were caused by the
lack of control joints. In addition, settlement as identified in the Geotechnical Investigation has likely
contributed to some of the cracking observed.
Overall, these cracks do not affect the structural integrity of the walls. However, they will continue
to be a cosmetic nuisance as they will open and close with seasonal changes in temperatures.
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.0121
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Page 2 of 3
d ■
WI SIEGFRIED
We recommend repairing these cracks as depicted on the attached plans including;
a. Sealing the cracks, and
b. Sawcutting the wall in select locations to create control joints and minimize future cracking and
maintenance.
6. Elevator Towers
The Geotechnical Investigation included one boring at each elevator tower. Their findings indicate
some differential settlement of the towers, causing the slight outward lean. Through subsequent
vibration monitoring, Terracon has determined that settlement has likely ceased.
At this time, the settlement has not affected the structural integrity of towers. However, a portion of
the north tower wall above the 3rd level will require repair.Currently this does not represent a
hazard.
7. Museum Area
We investigated the rusted roof framing and beam to beam connections and found the structure
and it's connections to be in good condition. The moisture intrusion problem should be remedied
immediately to prevent any further deterioration. The plans detail the sealing of the parking garage
roof deck above to help minimize moisture intrusion into this location.
8. Miscellaneous
Refer to the plans for various cosmetic repair locations
We trust this information will be of assistance in the continued repair and maintenance of this building.
Please review and provide comments on this report and the attached documents. If you should have any
questions or need additional information, please do not hesitate to give us a call.
Sincerely,
SIEGFRIED
N9
Q'
LIJ NO. S-4550
cc
Exp. 12/31//7
Ls)
s�CT,
of CAoj
G-7 /7
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.0121
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Page 3 of 3
CITY COUNCIL
DOUG KUEHNE, Mayor
ALAN NAKANISHI,
Mayor Pro Tempore
MARK CHANDLER
BOB JOHNSON
JOANNE MOUNCE
CITY OF LODI
CITY HALL, 221 WEST PINE STREET
P 0. BOX 3006
LODI, CALIFORNIA 95241-1 91 0
(209) 333-6706 / FAX (209) 333-6710
EMAIL: pwdept@lodi.gov
www lodi.gov
August 31, 2017
Siegfried Engineering, Inc.
3244 Brookside Road, Suite 100
Stockton, CA 95219
Attn; Anthony L. Lopes, P.E., S.E.
STEPHEN SCHWABAUER
City Manager
JENNIFER M. FERRAIOLO
City Clerk
JANICE D. MAGDICH
City Attorney
CHARLES E. SWIMLEY, JR.
Public Works Director
SUBJECT: Approve Plans and Specifications and Authorize Advertisement for Bids
for Lodi Station Parking Garage Maintenance and Repair Project
Enclosed is a copy of background information on an item on the City Council agenda of
Wednesday, September 6, 2017. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunity to address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand -deliver the letter to City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Jennifer M. Ferraiolo, City Clerk, at (209) 333-6702.
If you have any questions about the item itself, please call Lyman Chang at (209) 333-
6706.
Charles E. Swimley, Jr.
Public Works Director
CES/td b
Enclosure
cc: City Clerk