HomeMy WebLinkAboutAgenda Report - May 3, 2017 C-12CITY OF LODI COUNCIL COMMUNICATION AGENDA ITEM TM AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Task Order No. 42 with West Yost Associates, of Davis, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements ($64,680) MEETING DATE: May 3, 2017 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute Task Order No. 42 with West Yost Associates, of Davis, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements, in the amount of $64,680. BACKGROUND INFORMATION: During the irrigation season (generally April through September), most of the City's treated municipal and industrial wastewater is used to irrigate agricultural crops on 790 acres of City -owned property around White Slough Water Pollution Control Facility (WSWPCF). In response to violations associated with irrigation water inadvertently leaving WSWPCF, West Yost Associates was tasked with evaluating the land application area irrigation system as part of Task Order No. 38, approved by Council on July 20, 2016. The system evaluation included a condition and capacity assessment, alternates for system improvements, and a phasing plan based on the consequences and likelihood of failure of major components of the irrigation system. The evaluation concluded that replacing a concrete lined irrigation channel along the west side of the existing storage ponds and relocating pipeline that underlies a portion of an existing power plant must receive priority when addressing the improvements needed. Task Order No. 42 includes pre -design field work, design drawings, front-end and technical specifications, engineering services during bidding and construction, and project management and quality assurance/quality control for constructing the proposed irrigation improvements. This work will be conducted on a time and materials basis, not to exceed $64,681. Design work for the proposed project is anticipated to be completed by fall of 2017. Construction is scheduled to begin in early 2018. Staff recommends authorizing the City Manager to execute Task Order No. 42 with West Yost Associates, of Davis, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements, in the amount not to exceed $64,680. FISCAL IMPACT: Improving the irrigation system at WSWPCF will increase efficiency and avoid costly repairs and system failures that could result in fines and penalties. There is no impact to the City's General Fund from the recommended action. APPROVED: n Schwab r, City Manager K:\WP\COUNCIL\2017\CC WYA TO 42.doc 4/21/17 Adopt Resolution Authorizing City Manager to Execute Task Order No 42 with West Yost Associates, of Davis, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements ($64,680) May 3, 2017 Page 2 FUNDING AVAILABLE: Funding for Task Order No. 42 is budgeted in Fiscal Year 2016/17 Wastewater Capital (53199000.77020). Funds originally budgeted for the Electrical Upgrades/Coarse Screen/SCADA construction will not be spent in Fiscal Year 2016/17 and can be diverted. Andrew Keys Deputy City Manager/Internal Services Director Charles E. Swimley, Jr. Public Works Director Prepared by Charles E. Swimley, Jr., Public Works Director CES/CES/tdb Attachment K:\WP\COUNCIL\2017\CC WYA TO 42 doc 4/21/17 Task Order No. 42 City of Lodi White Slough Water Pollution Control Facility 2017 Irrigation System Improvements West Yost Job Number 213-18-17-38 In accordance with the Task Order Agreement between City of Lodi (Client) and West Yost Associates, Inc. (Consultant), dated January 13, 1999, Consultant is authorized to complete the work scope defined in this Task Order according to the schedule and budget defined herein. WORK SCOPE Consultant shall design pipelines and structures to replace a channel and pipeline that deliver reclaimed water used to irrigation of crops on the southern 400 acres of City -owned property at the WPCF. The scope of work is described in greater detail in Attachment A to this Task Order. BUDGET The costs for Consultant's services as defined herein shall not exceed $64,680. COMPENSATION Compensation shall be in accordance with the provisions of the Task Order Agreement between Client and Consultant and the billing rate schedule as shown in Attachment B. The compensation limit for services performed under this task order shall not exceed $64,680. If additional funds are required to complete the services defined herein beyond this limit, Consultant shall notify Client in writing prior to reaching the authorized limit, and will not proceed with work in excess of the limit without the prior written approval of Client. SCHEDULE We anticipate that services will be performed in accordance with the following schedule. April 4, 2017 1 n\a\c\K-O\Lodi\2017\TO42 West Yost Task Order Table 1. Anticipated Schedule Task or Activity Anticipated Completion Pre -Design Field Work Mid -May 2017 65% Complete Design Submittal Mid -June 2017 100% Complete Design Submittal Mid -July 2017 Bidding and Award Early October 2017 Construction End of February 2018 WEST YOST ASSO IATE. itiekS Signature W. Franklin Helmick Printed Name Vice President CITY OF LODI Signature Printed Name Title Title 04/05/2017 Date Date Approved as to Corm City Attorney April 4, 2017 2 n\a\c\K-O\Lodi\2017\TO42 West Yost Task Order WEST YOST ASSOCIATES Cons ul;reg knsmecrs Attachment A March 24, 2017 SENT VIA: EMAIL Mr. Charlie Swimley Director of Public Works City of Lodi 221 West Pine Street Lodi CA 94559 SUBJECT: Proposal to Complete Task Order 42—Perform Engineering Design Service for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements Dear Charlie: This is a proposal in response to the City of Lodi's (City) request to perform engineering design services associated with the replacement of certain high-risk components of the reclaimed wastewater irrigation system at the White Slough Water Pollution Control Facility (WPCF). BACKGROUND During the irrigation season (generally April through September), most of the City's treated municipal and industrial wastewater is used to irrigate crops on 790 acres of City -owned property around the WPCF. Recently, West Yost Associates (West Yost) evaluated the consequence and likelihood of failure for major components of the irrigation system, and identified replacing a channel and pipeline that deliver reclaimed wastewater to the southern 400 acres of the City's property as critical improvements. Construction of these improvements cannot proceed until after the irrigation season (in October 2017), and should be completed in early 2018 to avoid potential conflicts with the planned Storage Expansion Improvements Project. This is a proposal to prepare design documents in a manner that will satisfy these scheduling constraints. SCOPE OF WORK The following scope of work assumes that West Yost will provide the engineering services described below, and that construction inspection services will be performed by City staff and specialty inspection personnel retained by the City. Task 1. Pre -Design Field Work The following field work must be completed prior to beginning the detailed design of project improvements: 2020 Research Park Drive, Suite 100 Davis, CA 95618 Phone 530 756-5905 Fax 530 756-5991 westyost corn Mr. Charlie Swimley March 24, 2017 Page 2 • Locating and potholing of a 36 -inch diameter pipeline to which this project will connect. • Topographic survey of about one acre of land along the planned pipeline alignment. Task 1 Deliverable: Pipeline location/depth and topographic sumey information. Task 2. Prepare Design Drawings West Yost will prepare design drawings for review at the 65% and 100% stages of completion. We anticipate that the following design drawings will be required. DWG NO. SHEET NAME G001 TITLE SHEET, LOCATION MAP AND VICINITY MAP G002 INDEX OF DRAWINGS, GENERAL LEGEND, NOTES & ABBREVIATIONS C001 SITE PLAN, CONTROL POINTS, STAGING AREA C002 PIPING PLAN & PROFILE 1 C003 PIPING PLAN & PROFILE 2 C004 PRE -CAST STRUCTURES 1 C005 PRE -CAST STRUCTURES 2 C006 CIVIL DETAILS 1 C007 CIVIL DETAILS 2 E001 ELECTRICAL LEGEND AND ABBREVIATIONS E002 ELECTRICAL INSTALLATION DETAILS E003 ELECTRICAL SITE PLAN AND FLOW MONITORING VAULT PLAN To expedite both the design and the construction of this project, pre -cast concrete structures will be used to contain flow monitoring equipment and as flow control structures. Task 2 Deliverables: 65% and 100% Complete Design Drawings. Task 3. Edit City "Front -End" Document and Prepare Technical Specifications West Yost will edit the City's standard "Front -End" contract documents and prepare technical specifications for this project. Draft "Front -End" contract documents will be submitted to the City for review at the 65% stage of completion, and complete contract and technical specifications will be submitted at the 100% stage of completion. Task 3 Deliverables ri ree'ha?rd copies of the edited 'front-end" specifications at the 65 percent submittal stage. Five hard copies and one electrcnic (PDGF) copy of the final specifications. Task 4. Engineering Services During Bidding and Construction Subtask 4.1: Engneerinq Service During Bkiding West Yost will perform the following bidding phase services: • Attend Pre -Bid Meeting: West Yost will attend an on-site pre-bid conference. It is assumed that the City will organize and lead the pre-bid meeting. WEST YOST ASSOCIATES n\m\LP\Lodi\2017_Lodi_Irrigation System Improv\LP Mr. Charlie Swimley March 24, 2017 Page 3 • Respond to Bidder Inquiries_ West Yost will provide written responses to design -related questions received during the bidding period. It is assumed that the City will be responsible for receiving questions, and will forward any design -related questions to West Yost. It is also assumed that City will be responsible for distributing responses prepared by West Yost to prospective bidders. • Prepare Addenda: West Yost will prepare two addenda to the contract documents. Subtask 4.2: Construction Phase Services West Yost will perform the following construction phase services: • Submittal Review: West Yost will review Contractor submittals for compliance with the design concepts and specifications. West Yost will not review incomplete submissions by the contractor. • Interpretation and Clarification of Contract Documents: West Yost will prepare written interpretation and clarifications of the Contract Documents in response to written requests from the Contractor. • Construction Phase Meetings: At the City's request a member of the design team will attend up to four meetings during the construction period. It is assumed that the construction management team would lead these meetings and be responsible for preparing agenda and meeting minutes. Task 5. Project Management and Quality Control West Yost will manage this project to keep the project on schedule and within budget, and conduct quality assurance reviews of all work products to insure they are of a high quality. SCHEDULE We understand that these improvements should be in service by the end of February 2018, and have structured our proposed scope of services to meet the following schedule. This schedule assumes that West Yost is authorized to begin design services no later than mid-May 2017. Table 1. Anticipated Schedule Task or Activity _ Anticipated Completion Pre -Design Field Work Mid -May 2017 65% Complete Design Submittal Mid -June 2017 100% Complete Design Submittal Mid -July 2017 Bidding and Award Early October 2017 Construction End of February 2018 WEST YOST ASSOCIATES n\m\LP\Lodi\ 2017_Lodi_Irrigation System Improv\LP Mr. Charlie Swimley March 24, 2017 Page 4 BUDGET As indicated above, to comply with scheduling constraints the pre -design field work should be completed by mid-May 2017, however West Yost may not be authorized to begin design services until mid-May 2017. Therefore, we propose use a portion of the remaining budget in Task Order 38, Task 9: Land Application Facilities Irrigation System Evaluation to complete the pre -design field work. This budget is remaining because the irrigation system evaluation cannot be completed until after certain irrigation system pipelines have been inspected by closed-circuit TV, and this inspection has been delayed because of the levee breach. As indicated in Table 2, we propose to complete the Land Application Facilities Irrigation System Evaluation under this Task Order (42). The estimated cost to complete the scope of work described above is summarized in the table below. We will perform all work on an hourly basis at standard company charge rates, and will not exceed the estimated cost summarized herein without written authorization. If additional budget is required to complete services, West Yost will notify the City, prior to exceeding 90 percent of the estimated cost, that budget augmentation will be required to complete the work. Table 2. Proposed Task Order 42 Budget Task or Activity Budget. dollars Task 1 — Pre -Design Field Work (Complete Under TO 38) Task 2 —Design Drawings 35,660 Task 3 — Front -End and Technical Specifications 8,100 Task 4 — Engineering Services During Bidding & Construction 10,460 Task 5 — Project Management and QA/QC 2,100 Complete Land Application Facilities Irrigation System Evaluation 8,360 Total $64,680 Sincerely, WEST YOST ASSOCIATES z 4L, Dave Anderson, PE Engineering Manager RCE #C27659 DA:lh WEST YOST ASSOCIATES n\m\LP\Lodi\2017_Lodi_Irrigation System Improv\LP WEST YOST -4111111 ASSOCIATES 2017 Billing Rate Schedule (Effective January 1, 2017 through December 31, 2017)* Attachment B POSITIONS ENGINEERING LABOR CHARGES (DOLLARS PER HR) PrincipalNice President Engineering/Scientist/Geologist Manager I / II Principal Engineer/Scientist/Geologist I / II Senior Engineer/Scientist/Geologist I / II Associate Engineer/Scientist/Geologist I / II Engineer/Scientist/Geologist I / II Engineering Aide $258 $237 / $248 $216/$229 $193 / $203 $172/$184 $139 / $161 $78 Administrative I / II / III / IV $71 I$891$1081$118 ENGINEERING TECHNOLOGY Engineering Tech Manager I / II $244 / $254 Principal Tech Specialist I / II Senior Tech Specialist I / II Senior GIS Analyst GIS Analyst Technical Specialist I / II / III / IV CAD Manager CAD Designer I / II $225 / $235 $207 / $216 $189 $178 $139/$150/$169/$188 $150 $116 / $130 CONSTRUCTION MANAGEMENT Senior Construction Manager Construction Manager I / II / III / IV Resident Inspector (Prevailing Wage Groups 4 / 3 / 2 / 1) Apprentice Inspector CM Administrative I / II $246 $150/$161/$171 /$214 $130/$145/$161 /$167 $118 $64 / $86 • Technology and Communication charges including general and CAD computer, software, telephone, routine in-house copies/prints, postage, miscellaneous supplies, and other incidental project expenses will be billed at 6% of West Yost labor. • Outside Services such as vendor reproductions, prints, shipping, and major West Yost reproduction efforts, as well as Engineering Supplies, etc. will be billed at actual cost plus 15%. • Mileage will be billed at the current Federal Rate and Travel will be billed at cost. • Subconsultants will be billed at actual cost plus 10%. • Expert witness, research, technical review, analysis, preparation and meetings billed at 150% of standard hourly rates. Expert witness testimony and depositions billed at 200% of standard hourly rates. • A Finance Charge of 1.5% per month (an Annual Rate of 18%) on the unpaid balance will be added to invoice amounts if not paid within 45 days from the date of the invoice. This schedule is updated Rates -1 WEST YOST +� ASSOCIATES 2017 Billing Rate Schedule (continued) (Effective January 1, 2017 through December 31, 2017)* Equipment Charges EQUIPMENT BILLING RATES Gas Detector Hydrant Pressure Gage Hydrant Pressure Recorder, Standard Hydrant Pressure Recorder, Impulse (Transient) $80/day $10/day $40/day $55/day Trimble GPS — Geo 7x $220/day Vehicle Water Flow Probe Meter Water Quality Multimeter Well Sounder * This schedule is updated $10/hour $20/day $185/day $30/day Rates -2 RESOLUTION NO. 2017-84 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE CITY MANAGER TO EXECUTE TASK ORDER NO. 42 WITH WEST YOST ASSOCIATES, OF DAVIS, FOR WHITE SLOUGH WATER POLLUTION CONTROL FACILITY 2017 IRRIGATION SYSTEM IMPROVEMENTS WHEREAS, in accordance with the Task Order Agreement between City of Lodi and West Yost Associates, dated January 13, 1999, West Yost Associates is authorized to complete the scope of work as defined in Task Order No. 42; and WHEREAS, Task Order No. 42 includes pre -design field work, design drawings, front-end and technical specifications, engineering services during bidding and construction, and project management and quality assurance/quality control for constructing the proposed irrigation improvements; and WHEREAS, staff recommends authorizing the City Manager to execute Task Order No. 42 with West Yost Associates, of Davis, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements, in the amount of $64,680. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize the City Manager to execute Task Order No. 42 with West Yost Associates, of Davis, California, for White Slough Water Pollution Control Facility 2017 Irrigation System Improvements, in the amount of $64,680. Dated: May 3, 2017 I hereby certify that Resolution No. 2017-84 was passed and adopted by the City Council of the City of Lodi in a regular meeting held May 3, 2017, by the following vote: AYES: COUNCIL MEMBERS — Chandler, Johnson, Nakanishi, and Mayor Kuehne NOES: COUNCIL MEMBERS — Mounce ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None m ��ua.c;A J NIFER M ) FERRAIOLO City Clerk 2017-84