Accept Improvements Under Contract for Well 10C Rehabilitation Project
February 1, 2017
Public Works Director
RECOMMENDED ACTION: Accept improvements under contract for Well 10C Rehabilitation
Project.
BACKGROUND INFORMATION: Well 10C is located at 790 North Guild Avenue. Preliminary
video inspection performed in 2013 indicated severe
encrustation on the well casing and well screens. The video also
revealed more than 40 feet of silty type material at the bottom of the well.
This project consisted of performing video inspection of the water well, cleaning the well casing,
inspecting and replacing the deep well turbine pump equipment, and other incidental and related work
as shown on the plans and specifications for the project, as shown in Exhibit A. The water well is
needed to supplement peak hour demand and fire flows in the industrial area east of Highway 99.
The contract was awarded to Zim Industries, Inc., of Fresno, in the amount of $110,385, on December
16, 2015. The contract has been completed in substantial conformance with the plans and
specifications approved by City Council on August 19, 2015.
The final contract price was $117,835.00. The difference between the contract amount and the final
contract price is due to two change orders. Change Order No. 1 included well screen repair work
which was revealed during the video inspection ($5,600.00). Change Order No. 2 included rebuilding
the existing well motor bearings ($2,300.00). The contractor provided a two-year warranty bond for
the pump equipment as specified for the project.
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of
Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors
that the project is complete and begins their 30 -day period to file a stop notice requiring the City to
withhold payments from the prime contractor in the event of a payment dispute.
FISCAL IMPACT: The project will decrease maintenance and operating costs of the water
well due to new pumps and clean well screen.
FUNDING AVAILABLE: This project was funded by Water Capital Fund
Charis E. Swimley, Jr.
Public Works Director
Prepared by Lyman Chang, City Engineer/Deputy Public Works Director
CES/LC/tdb
Attachment
cc: City Engineer
Utilities Manager
Public Works Management Analyst
Zim Industries, Inc.
APPROVED: 1'114
p en Schwab aw ity Manager
K:\WP\PROJECTS\WATER\We1110C\Rehabilitation Project\CAccept.doc
1/23/17
Well Screen Before Well Rehabilitation
Well Screen After Well Rehabilitation