CITY OF LODI
COUNCIL COMMUNICATION
AGENDA ITEM
C-,1
AGENDA TITLE: Accept Improvements Under Contract for Water Meter Program Phase 5, and
Adopt Resolution Appropriating Funds ($213,548)
MEETING DATE: May 4, 2016
PREPARED BY: Public Works Director
RECOMMENDED ACTION:
Accept improvements under contract for Water Meter Program
Phase 5, and adopt resolution appropriating funds, in the amount of
$213,548.
BACKGROUND INFORMATION: The Water Meter Program Phase 5 contract, awarded to Knife
River Construction, of Stockton, in the amount of $2,778,225, on
March 4, 2015, has been completed in substantial conformance
with the plans and specifications approved by City Council.
At the October 20, 2010 City Council meeting, a seven-year construction phasing was approved and the
property owner meter payment was capped at $300 per parcel. The project area for Phase 5 is
presented in Exhibit A and included the installation of 1,595 meters and the replacement of 17,000 feet
(3.2 miles) of water main.
The original contract completion was 210 days. Another 120 days (330 days total) were added due to
Change Order No. 3 that included alley and additional meter installation work. The final contract price
was $3,844,188.59. The difference between the contract amount and the final contract price is due to
change orders totaling $1,066,858.59, or 38 percent of the original contract amount.
Change Order No. 1 included various time and material changes as directed by City staff due to
unknown conditions or City requested changes in the field as described in Exhibit B ($244,505.16).
Change Order No. 2 included various time and material changes as directed by City staff due to
unknown conditions or City requested changes in the field as described in Exhibit C ($371,424.38).
Change Order No. 3 included work performed on a time and materials basis as directed by City staff due
to unknown conditions or City requested changes in the field as described in Exhibit D. Seven hundred
meter installations were added and two alleys were reconstructed due to existing sewer conditions that
required immediate attention. Sewer work is paid for from wastewater funds ($450,034.05).
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of
Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors
that the project is complete and begins their 30 -day period to file a stop notice requiring the City to
withhold payments from the prime contractor in the event of a payment dispute.
APPROVED:
_.&..___
-Stephen Sch b er, City Manager
K:\WP\PROJECTS\WATER'Meters\Water Meter Program Phase 5\CAccept WMPP5.docx 4/25/16
Accept Improvements Under Contract for Water Meter Program Phase 5
May 4, 2016
Page 2
FISCAL IMPACT:
Water main leak and service repairs will be reduced. No additional costs
will be incurred for reading of the meters as they are automatically read
concurrent with the reading of the electric meters.
FUNDING AVAILABLE: Appropriation requested:
Water Capital Fund (56199000.77020) - $213,548
Jordan Ayers f'
Deputy City Manager/Internal Services Director
Charles E. Swimley, Jr.
Public Works Director
CES/GW/tdb
Attachments
cc: RMC Water and Environment
Terracon
Knife River Construction
Henderson Brothers Company
K:\WP\PROJECTS\WATER Meters\Water Meter Program Phase 5\CAccept WMPP5.docx 4/20/16
LAKE
AYERS
RE MAN
LOCUST
0
LT_
o.
w
z
0
7
OAK
WALNUT
�•
W
0)
z
J
m
City of Lodi WMP
Phase 5 Construction Area
ho,
u�L�,y•CANEL'
•
CO
AL/s•eilea
KEFORD
MARIPOSA CARLO
LOCU ST
z w PINE
0
c Q
LL
WAL UT
LI II
OAK
CRESCENT
1
El
x
HUTCHINS
OLIVE
sr
PLEASANT'
4L !
U
:FORREST�
rr-11-
,o
- DAISY w
-1Ji I
1� ��_
DE FORCE
-r -�
I I
z
LOCUST
a
LAWRENCE
O 4
ELM 0 n
X
0 co o
U
o 0
Z v]
1
U
w
w
-J
w
a
WALN UT
CH ESTNUY
OAK
WALNUT
0
625
1,250
2,500
Feet
Phase 5 Replacement Mains
Phase 5 Construction Area
J
118
1D
14 718.5
•
eq AM
712 N
20 N
701
18
715 C 71
24 124 57 70.87
729
26 725 St 720.4 B C D E F_
N 739
35 736 5I�
7411- - - 741
742n �' S y '747
Aev
e K tl~,� '123_57
728 i 72
728
3!
441w.5 y]
744
'140 a71177--
I s!iv 741
m in
8�0
B18
820
'h �iFA1'
824
.`� � .. .
30
8383
684,
840 b. 1
11. rti
1648 n N
921
82
820
829
ti
„ pi .1
PROJECT 1
•-• hop.
n i=tri ' i1
901
903
— .�
945
m I rs I 829
- 1 -: 936
TU v4 941
2
844
969
906
912
918
922
926
930
.934
938
946 §
190a
1006
1010
1014
I N
900
910 909
91 ) 919 13
9
f 91 x922
9211 924
926` 925
92 m 928 79_939
93 932
93 9401 Ro
It,
c
N
1050
2 52' d T
9f111 N in
110
110
1036
1940 .
1050 r co) ...UP) o1 is
v 4 1
103
103+
1041
104
654r. e:.r
Change Order #3 Meter Area
822
825 -1
934
-834
836
840
807
515
921
490
825
825.
- i
-7-T
906
910
918
917
924 923
PROJECT 2
950
1005
1038
929
1011
1045
822
825 -1
934
-834
836
840
807
515
921
490
825
825.
- i
-7-T
906
910
918
917
924 923
PROJECT 2
950
1005
1038
929
1011
1045
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Water Meter Program Phase 5
Meter Installation and Main Replacement
CONTRACTOR: Knife River Construction
ENGINEER RMC
GO. NO: 1
PCO NO: 1
RFI NO:
g.RC PCU NO: 2, 3,.+t, 56, 7, 8, 9:10,1.1,12 and 13
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
Miscellaneous T&M work tracked and documented by project inspectors, slip lining of sewer on Ham Lane as
requested by City staff, tree removal over a rich box on S. Sunset Drive, Civic Center complex meters and services
work originally to be part of the nonresidential meter project and sidewalk/driveway/ADA ramp replacements
associated with the meter program work. Supporting documentation is attached The total of KRC PCOs 2-13 is
$244,505.16
Request, Proposal, Recommendation And Approval.
Requesting Official: Wally Sandelin Date of Request: 4/14/15-7/14/15 Schedule ImpactO_Days
Contractor Proposal Date: 7/28/15 Add Amount $244,505.16
Reason For Change: Owner Requested/Unknown Condition Account
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLE71. THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR IOBSTTE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL 13I3 STARTED UNTIL THIS PROPOSAL IS ACCEPT'i?D.
rcri......4. 9 i f(
—
ORIGINAL CONTRACT $2,778,225.00
Contractor Date
62/r40r
PREVIOUS ADDS 10
PREVIOUS DEDUCTS ID
tructk n Data
/3/ts
THIS CHANGE $244,505.16
CONTRACT TO DATE $3,022,730.16
Public Warks '• Date
L"
L , ,.i .. _.. -..
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: 210 Calendar Days
City ManagOr Date
ADJUSTED CONTRACT
COMPLETION DATE: 210 Calendar Days
WMPP5 PCO 1
Water Meter Program Phase 5
Change Order #1 Tally
KRC PCO #
Amount
Description
2
$47,734.65
T&M Work Through May 2, 2015
3
$10,350.00
Slip -line 4" sewer lateral as requested by City Staff
4
$3,000.00
Tree Removal over Water Line at 19 N. Sunset Drive
5
$24,346.00
T&M work for meter crews
6
$39,581.06
Additional water main tie-ins, "T"s and valves
7
$10,433.50
Additional Pot hling and service work requested by City Staff
8
$26,275.95
Install an additional 145 LF of 6" main on Pine St and replace valve at City Hall
9
$13,286.00
T&M Work for meter installations
10
$8,345.50
T&M work for water mains
11
$21,084.00
Removal and replacement of 1,757 SF of sidewalk, driveway and ADA corner ramp
12
$29,808.50
Various T&M Work from July 27 to August 10
13
$10,260.00
Removal and replacement of 8555F of sidewalk and driveway
Total $244,505.16
CITY OF LODI
PROPOSED CHANGE ORDER AND REQUEST FOR PROPOSAL
PROJECT: Water Meter Program Phase 5
Meter Installation and Main Replacement
CONTRACTOR: Knife River Construction
ENGINEER: RMC
C.O. NO: 2
PCO NO: 2
RFI NO:
KRC PCO NO: 14, 15, 16, 17, 18, 19, 21, 22, 23, 24, 25, 26,
27, 29, 30, 31 and 32
Submit Proposal Within 15 Days Upon Receipt of This Request
Brief Description Of Work
Miscellaneous T&M work tracked and documented by project inspectors, new street light conduit and wiring on Rose
and California Streets between Oak and Pine Streets, replace 600 meter box lids for east side meters not included in
Phase 5 contract as requested by City staff, etc. Supporting documentation is attached. The total of KRC PCOs 14, 15,
16, 17, 18, 19, 21, 22, 23, 24, 25, 26, 27, 29, 30, 31 and 32 is $371,424.38
Request, Proposal, Recommendation And Approval
Requesting Official: Wally Sandelin Date of Request:
Contractor Proposal Date: 9/8/15 Add Amount: $371,424.38
Reason For Change: Owner Requested/Unknown Condition
7/14/15 to 11/18/15 Schedule Impact _0_Days
Accountt."L� I4,00 V7- Ca� �_
r [/
Requested By: Gary Wiman
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED.
S-- A r/ep
ORIGINAL CONTRACT $2,778,225.00
Date
Contractor Date
--
/ fU 7/`
PREVIOUS ADDS $5e65.05, l
PREVIOUS DEDUCTS 8444;60646,4b 11
• nstruction yam. Date
CU 41, 1p 1. j ( , • ` LAP
THIS CHANGE $371,424.38
CONTRACT TO DATE $3,394,154.54
Public Works Date
. . ,i 'y
CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: 210 Calendar Days
Cl -M , ; �_ ~r D tl��
t3'
ADJUSTED CONTRACT
COMPLETION DATE: 210 Calendar Days
WMPP5 PCO 2
1/6/2016
Water Meter Program Phase 5
Change Order #2 Tally
KRC PCO #
Amount
Description
14
$20,058.50
Various T&M Work from July to September from Tommy's Crew
15
$20,511.00
Various T&M Work from September from Tony's Crew
16
$25,993.50
Various T&M Work from 7/28/15 to 8/18/15
17
$39,480.00
Various T&M Work from 8/20/15 to 9/2/15
18
$14,100.00
Replace Street Light conduit and wiring on California & Rose between Oak & Pine
19
$4,638.00
Concrete replacement at various Fire hydrants 9/14/15
21
$42,802.90
Various T&M Work from 9/11/15 to 9/18/15
22
$19,468.50
Various T&M Work from 9/21/15 to 9/25/15
23
$22,671.00
Various T&M Work from 9/28/15 to 10/2/15
24
$44,002.50
Various T&M Work from 10/5/15 to 10/15/15
25
$25,800.00
Replace 600 exisitng meter lids with Fiberliyte lids per City Request
26
$1,725.00
Repair of gas line at 309 W. Walnut
27
$3,800.00
water clean-up at 9 S. California
29
$30,741.78
Various T&M Work from 10/16/15 to 10/22/15
30
$10,577.50
Various T&M Work from 10/23/15 to 10/29/15
31
$21,258.20
Various T&M Work from 10/30/15 to 11/10/15
32
$23,796.00
Various T&M Work from 11/11/15 to 11/18/15
Total $371,424.38
CITY OF LODI . . .
PROPOSED_CHA.NOR.ORDER Ale). REQUESIECIR_PROP_OSAL
PROJECT: Water Meter Program Phase 5
Meter Installation and Main Replacement
CONTRACTOR: Knife River Construction
ENGINEER: RMC
C.O. NO: 3
PCO NO: 3
RFI NO: 2001
Fl NO: _ . . • • ._•• ..
woiti 15 Days Upon Receipt of This Request
1-4mis ,„.41
,M111 wv-Av.m1.,
,
1(,e...72AKtymmta
This Change Order includes:
41. KRC PCO 1 to install approximately 700 additional type "A" meters as requested by the Public Works
Director. $66,500.00
12. KRC PCO 20 replaced the existing sewer main and manhole and reconstructed the alley between Elm and
Locust Street west of Hutchins Street. This work is charged to the Wastewater fund. $182,970,00
13. KRC PCO 28 replaced the existing sewer main, added storm drain line and reconstructed the alley off of Rose
Street between Pine and Elm Streets. This work is charged to the Wastewater fund. $53,517.00
14. KRC PCO 33 is for various Time and Materials work performed between November 2015 and December 10,
2015. All work was witnessed and authorized by City representatives, $11,368.00
q5. KRC PCO 34 is for various Time and Materials work performed between January 14, 2016 and February 18,
2016. All work was witnessed and authorized by City representatives. $10,749.00
6. KRC PCO 35 is for additional miscellaneous concrete repairs performed on a Time and Materials basis. All
work was witnessed and authorized by City representatives. $19,245,00
7. KRC PCO 36 is for additional miscellaneous asphalt repairs performed on a Time and Materials basis. All
work was witnessed and authorized by City representatives. $105,685.05
ie tnt1 nftlie seven (7' items above is 5
..___ _ _._ ......
NewI6064414 - P.- -A-A . it Isii,.-1..7,, ,; ., Woilibt).W1154,4„.01,AV4%., •-• -.,:a,Wyni,P-t..1g4, . ', ,-6:,. ., - •,-::11.
- „ - ig:_,,,,-,r."!--. .v.....m, ,---, 4, - :x.01= ,,,,,,,,,,z.v),N,...,_,_, .-,mr*".%Ak. _,r ,sa4•sy_t k..7.;1_ -N -A'' t
Requesting Official: Lyman Chang Date of Request: 4/10/15 Schedule Impact=1.20_D4rs
Contractor Proposal Date: 3/7/16 Add Amount: $450,034.05
Reason For Change; Owner Requested/unknown conditions Water Account: PWWA-0047,constr.extlabor $213,547,05
Itoluiisted Eiy?„GarY. W . - imanWastewaterAccount: PWWA-0047.Con.st.ExtLabor.WW $2$6,481.00
CONTRACTOR AGREES TO Fi,n32'MAI.L.L:ABOR AD MATERIALS AND PERKIRM ALL W041( rtaN1rtg1) TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS PORSIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS intoropig, 1p_ ACcEPTED. ... ... „
1,
I . c/16-/
4P'
ORIGINAL CONTRACT $2,778,225.00
Contractor Da -
----
PREVIOUS ADDS .$615,929.54
PREVIOUS DEDUCTS $0
C,6 tar. alon ivI4na7Z------ Date
Lt • ( 9 - i Li,
THIS CHANGE $450,034.05 -.
,
cONTRAC'r TO DATE $3,844,188.59
_. .
_c)
Public Works Date '
......ta
111. 11116. e._
'1
CONTRACT TIME ADJUSTMENT 120 DAYS
ORIGINAL CONTRACT
COMPLETION DATE: 210 Calendar Days
1 wimp, 1 1 -iii-,
City :k % ger D e
ADJUSTED CONTRACT . .
COMPLETION DATE: 330 Calendar Days
WMPP5 PCO 3,docx
4/12/2016
Water Meter Program Phase 5
Change Order #3 Tally
KRC PCO
Amount
Description
1
$ 66,500.00
Install 700 Additional Type "A" Meters as Requested by PW Director
20*
$ 182,970.00
Reconstruct Alley Between Elm & Locust due to sewer & drainage issue!
28*
$ 53,517.00
Reconstruct Alley off Rose between Pine and Elm due to sewer issues
33
$ 11,368.00
Various T&M Work from 11/1915 to 12/10/15
34
$ 10,749.00
Various T&M Work From 1/14/16 to 2/18/16
35
$ 19,245.00
Additional concrete repair work at various locations
36
$ 105,685.05
Additional Trench patch paving performed T&M
TOTAL $450,034.05
PCO 20 an d28 were performed due to conditions related to existing
$ 236,487.00 sewer issues and shouold be charged to the wastewater fund.
$ 213,547.05 Water Fund
1. AA#
2. JV#
CITY OF LODI
APPROPRIATION ADJUSTMENT REQUEST
TO:
Internal Services Dept. - Budget Division
3. FROM: Rebecca Areida-Yadav
4. DEPARTMENT/DIVISION: Public Works
T5. DATE:
4/20/2016
6. REQUEST ADJUSTMENT OF APPROPRIATION AS LISTED BELOW
FUND #
BUS. UNIT #
ACCOUNT #
ACCOUNT TITLE
AMOUNT
A.
SOURCE OF
FINANCING
561
32205
Fund Balance
$ 213,548.00
B.
USE OF
FINANCING
561
56199000
77020
Capital Projects
$ 213,548.00
7. REQUEST IS MADE TO FUND THE FOLLOWING PROJECT NOT INCLUDED IN THE CURRENT BUDGET
Please provide a description of the project, the total cost of the project, as well as justification for the
requested adjustment. If you need more space, use an additional sheet and attach to this form.
Change Order 3 with Knife River for the Water Meter Program Phase 5 project
If Council has authorized the appropriation adjustment, complete the following:
Meeting Date:
Department Head Signature:
Res No:
Attach copy of resolution to this form.
8. APPROVAL SIGNATURES
Deputy City Manager/Internal Services Manager
Date
Submit completed form to the Budget Division with any required documentation.
Final approval will be provided in electronic copy format.
RESOLUTION NO. 2016-57
A RESOLUTION OF THE LODI CITY COUNCIL APPROPRIATING
FUNDS FOR WATER METER PROGRAM PHASE 5
WHEREAS, the City Council awarded the contract for the Water Meter Program Phase 5
to Knife River Construction, of Stockton, in the amount of $2,778,225, on March 4, 2015; and
WHEREAS, the Water Meter Program Phase 5 included the installation of 1,595 meters
and the replacement of 17,000 feet (3.2 miles) of water main; and
WHEREAS, 700 meter installations were added and two alleys were reconstructed due
to existing sewer conditions that required immediate attention; and
WHEREAS, the final contract price was $3,844,188.59. The difference between the
contract amount and the final contract price is due to change orders totaling $1,066,858.59 or
38 percent of the original contract amount; and
WHEREAS, staff recommends appropriating funds in the amount of $213,548 for the
Water Meter Program Phase 5 project.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
appropriate funds in the amount of $213,548 for the Water Meter Program Phase 5 project.
Dated: May 4, 2016
I hereby certify that Resolution No. 2016-57 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held May 4, 2016 by the following vote:
AYES: COUNCIL MEMBERS — Johnson, Kuehne, Mounce, Nakanishi, and
Mayor Chandler
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
Sty Clerk
NIFER FERAIOLO
2016-57