AGENDA TITLE: Adopt Resolution Accepting Rose Gate Subdivision Unit No. 1 (Tract No. 3785)
and Unit No. 2 (Tract No. 3813) Public Improvements
MEETING DATE: November 18, 2015
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution accepting Rose Gate Subdivision Unit No. 1
(Tract No. 3785) and Unit No. 2 (Tract No. 3813) public
improvements.
BACKGROUND INFORMATION: Public improvements at Rose Gate Subdivision Unit No. 1
(Tract No. 3785) and Unit No. 2 (Tract No. 3813), as shown on
Exhibit A, have been completed in substantial conformance with
the requirements of the improvement agreement between the City and Frontier Land Companies
approved by City Council on June 18, 2014.
The public improvements include installation of all interior subdivision improvements, along with street
frontage improvements, along the north side of Lodi Avenue from Lower Sacramento Road to the
westerly project limits. The improvements along Lodi Avenue consist of undergrounding the existing
overhead power poles, installation of a round -about, masonry wall, curb, gutter and sidewalk (north
side only west of the round -about), landscape and irrigation, street lights, signal improvements, and
full -width paving.
The streets to be accepted are as follows:
Streets Length in Miles
Lodi Avenue* 0.32
Interior Streets 1.86
Total New Miles of City Streets 2.18
* Lodi Avenue from Lower Sacramento Road to the west boundary of Raley's
Center (0.18 miles) consists of landscape and irrigation improvements in an
existing street right-of-way and did not add additional miles to the City's street
system.
Temporary off-site storm drain and wastewater improvements (also reflected in Exhibit A) have been
constructed as a condition of securing the right to develop the Rose Gate Project. The temporary
infrastructure will be privately owned and maintained by the developer in accordance with the terms
and conditions of the Temporary Maintenance Agreement, also approved by Council on June 18, 2014.
APPROVED:
S e n Schw- • - - - r, City Manager
K:\WP\DEV_SERV\Developments\Lodi Westside\Rosegate Subdivision\improvement agreement\CAccept public approvements_cs.doc 10/28/15
Adopt Resolution Accepting Rose Gate Subdivision Unit No. 1 (Tract No. 3785) and Unit No. 2 (Tract No 3813) Public Improvements
November 18, 2015
Page 2
FISCAL IMPACT:
There will be an increase in long-term maintenance costs for public
infrastructure and City services, such as police, fire, and parks. This
cost will be funded by proceeds from the Community Facilities District
No. 2007-1.
FUNDING AVAILABLE: Not applicable.
_Fur F. Wally Sandelin
Public Works Director
Prepared by Charles E. Swimley, Jr., City Engineer/Deputy Public Works Director
FWS/CES/tb
Attachment
cc: City Attorney Magdich
City Engineer / Deputy Public Works Director Swimley
Senior Civil Engineer Chang
Associate Civil Engineer Nathan
Senior Engineering Technician Wiman
FCB Homes
MCR Engineering
K:\WP\DEV SERV\Developments\Lodi Westside\Rosegate Subdivision\improvement agreement\CAccept public improvements_cs.doc 11/3/2015
Rose Gate Offsite Exhibit
(
Legend
Sewer & SD Easement
L=11 MI
City Limits
r
Rose Gate Subdivision
i
i
1
1
1
1
mporary
sin
Ij
j
I!
I
I
I'
I'
0
I'
0
I'
0
I�
I!
iliiT,T "
Allor
•
A/1 ill
Master Plan Sewer
& Storm Drain Line
Temporary Sewer
Pump Station
Temporary Sewer
Force Main
Temporary Sewer Force
Main Discharge Point
S
1 inch = 500 feet
When Recorded, Return to:
City of Lodi City Clerk's Office
P.O. Box 3006
Lodi, CA 95241-1910
RESOLUTION NO. 2015-203
Doc t1: 2015-138952
11/23/2015 11,23:09 Ali
Page: 1 of 1 Fee: $0
Steve J. Bestoiarides
San Joaquin County Recorders
Paid By: SHOWN ON DOCUMENT
111 t'{fl'iiti
A RESOLUTION OF THE LODI CITY COUNCIL ACCEPTING ROSE
GATE SUBDIVISION UNIT NO. 1 (TRACT NO. 3785) AND UNIT NO. 2
(TRACT NO. 3813) PUBLIC IMPROVEMENTS
WHEREAS, public improvements at Rose Gate Subdivision Unit No. 1 (Tract No. 3785)
and Unit No. 2 (Tract No. 3813) have been completed in substantial conformance with the
requirements of the Improvement Agreement between the City and Frontier Land Companies
approved by City Council on June 18, 2014; and
WHEREAS, the public improvements include installation of all interior subdivision
improvements, along with street frontage improvements on the north side of Lodi Avenue from
Lower Sacramento Road to the westerly project limits; and
WHEREAS, the improvements along Lodi Avenue consist of undergrounding the existing
overhead power poles; installation of a roundabout, masonry wall, curb, gutter and sidewalk
(north side only west of the roundabout), landscape and irrigation, street lights, and signal
improvements; and full -width paving.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby accept
Rose Gate Subdivision Unit No. 1 (Tract No. 3785) and Unit No. 2 (Tract No. 3813) public
improvements; and
BE IT FURTHER RESOLVED that the streets to be accepted are as follows:
Streets Length in Miles
Lodi Avenue* 0.32
Interior Streets 1.86
Total New Miles of City Streets 2.18
*Lodi Avenue from Lower Sacramento Road to the west boundary of Raley's Center (0.18 miles) consists of
landscape and irrigation improvements in an existing street right-of-way and did not add additional miles to
the City's street system.
Dated: November 18, 2015
I hereby certify that Resolution No. 2015-203 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held November 18, 2015, by the following vote:
AYES: COUNCIL MEMBERS — Chandler, Kuehne, Mounce, Nakanishi, and
Mayor Johnson
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
NIFER FERRAIOLO
City Clerk
2015-203