HomeMy WebLinkAboutAgenda Report - September 2, 2015 C-07AGENDA ITEM Cw 7 CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Adopt Resolution Awarding Contract for Ham Lane Signal Modification Improvements 2015, to Tim Paxin's Pacific Excavation, Inc., of Elk Grove, ($331,934) MEETING DATE: September 2, 2015 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt resolution awarding contract for Ham Lane Signal Modification Improvements 2015, to Tim Paxin's Pacific Excavation, Inc., of Elk Grove, in the amount of $331,934. BACKGROUND INFORMATION: This project consists of modifying traffic signals to include protected left turn movements on Ham Lane at Vine Street Tokay Street, and Lockeford Street. The work includes installing four new signal poles (two each at Vine Street and Tokay Street), new service pedestals, cabinet controller equipment, and LED countdown pedestrian signals at each of these locations. Plans and specifications for this project were approved on July 15, 2015. The City received the following two bids on August 6, 2015. Tim Paxin's Pacific Excavation, Inc. has signed the required Local Hire forms and will conform to the requirements. Bidder Engineer's Estimate Tim Paxin's Pacific Excavation, Inc. St Francis Electric LLC Location Elk Grove San Leandro Bid $ 290,200.00 $ 331, 934.00 $ 377,770.00 The total project cost including the contract, staff time and contingencies is estimated at $450,000. The difference between the amount budgeted and the total project cost is due to a higher than anticipated low bid and minor project scope changes such as installing a new service cabinet and concrete pad; and replacing the existing pedestrian signal head, and traffic loop detection. FISCAL IMPACT: There will be a slight increase in signal maintenance costs at these intersections. FUNDING AVAILABLE: Gas Tax (30299000.77020) $450,000 Jordan Ayers Deputy City Manager/Internal Services Director APPROVED: ep en Sc w ba , City Manager KAWP\PROJECTS\SIGNALS\Ham Lane Signal Modifications 2015\CAward Ham Lane Signal Mod.doc 8/25/2015 Adopt Resolution Awarding Contract for Ham Lane Signal Modification Improvements 2015, to Tim Paxin's Pacific Excavation, Inc., of Elk Grove, ($331,934) September 2, 2015 Page 2 F. Wally 61anaelin Public Works Director Prepared by Dorothy Kam, Assistant Engineer FNS/DK/tb Attachment cc: City Engineer/Deputy Public Works Director K:\WP\PROJECTS\SIGNALS\Ham Lane Signal Modifications 2015\CAward Ham Lane Signal Mod.doc 8/25/2015 HAM LANE SIGNAL MODIFICATION IMPROVEMENTS 2015 CONTRACT Vine, Tokay and Lockeford Street CITY OF LODI, CALIFORNIA THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred to as the "City," and TIM PAXIN'S PACIFIC EXCAVATION, INC., herein referred to as the "Contractor." WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and agree with each other, as follows: The complete Contract consists of the following documents which are incorporated herein by this reference, to -wit: Notice Inviting Bids Information to Bidders General Provisions Special Provisions Bid Proposal Contract Contract Bonds Plans The July 1992 Edition, Standard Specifications, State of California, Business and Transportation Agency, Department of Transportation All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are intended to cooperate so that any work called for in one and not mentioned in the other is to be executed the same as if mentioned in all said documents. ARTICLE I - That for and in consideration of the payments and agreements hereinafter mentioned, to be made and performed by the City and under the condition expressed in the two bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with the City, at Contractor's cost and expense, to do all the work and furnish all the materials except such as are mentioned in the specifications to be furnished by the City, necessary to construct and complete in a good workmanlike and substantial manner and to the satisfaction of the City the proposed improvements as shown and described in the Contract Documents which are hereby made a part of the Contract. ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does hereby employ, the Contractor to provide all materials and services not supplied by the City and to do the work according to the terms and conditions for the price herein, and hereby contracts to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the General Provisions, in the manner and upon the conditions above set forth; and the said parties for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree to the full performance of the covenants herein contained. ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2 of the Labor Code. The Contractor and any Subcontractor will pay the Contract.doc 4.1 08/12/15 general prevailing wage rate and other employer payments for health and welfare, pension, vacation, travel time, and subsistence pay, apprenticeship or other training programs. The responsibility for compliance with these Labor Code requirements is on the prime contractor. ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full compensation for furnishing all materials and for doing all the work contemplated and embraced in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or from the action of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its acceptance by the City, and for all risks of every description connected with the work; also for all expenses incurred by or in consequence of the suspension or discontinuance of work and for well and faithfully completing the work, and the whole thereof, in the manner and according to the Plans and Contract Documents and the requirements of the Engineer under them, to -wit: Perform the work necessary to install new signal poles and foundation, concrete pad for service and controller cabinets, service pedestals and controller cabinet, LED countdown pedestrian signals with unimount mounting hardware, push buttons and signs; modify traffic signals to accommodate protected left turn phases on Ham Lane at Vine Street and Tokay Street, and on Lockeford Street at Ham Lane; install survey monument at the southwest corner of Ham Lane and Vine Street, and other incidental and related work all as shown on the plans and specifications for "Ham Lane Signal Modification Improvements 2015". CONTRACT ITEMS ITEM EST'D. NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL PRICE Traffic Signal Modification for Ham and Vine 1 LS $135,726.00 $135,726.00 2. Traffic Signal Modification for Ham and Tokay 1 LS $132,518.00 $132518.00 3. Traffic Signal Modification for Ham and Lockeford 1 LS $63,690.00 $63,690.00 ARTICLE V - By my signature hereunder, as Contractor, provisions of Section 3700 of the Labor Code, which insured against liability for workers' compensation or TOTAL $331,934.00 I certify that I am aware of the requires every employer to be to undertake self-insurance in Contract doc 4.2 08/12/15 accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract. ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there be any conflict between the terms of this instrument and the Bid Proposal of the Contractor, then this instrument shall control and nothing herein shall be considered as an acceptance of the said terms of said proposal conflicting herewith. ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to establish lines and grades for the work as specified under the Special Provisions. All labor or materials not mentioned specifically as being done by the City will be supplied by the Contractor to accomplish the work as outlined in the specifications. ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15 calendar days after the City Manager has executed the contract and to diligently prosecute to completion within 40 WORKING DAYS. ARTICLE IX - State of California Senate Bill 854 requires the following: No contractor or subcontractor may be listed on a bid proposal for a public works project (submitted on or after March 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)]. No contractor or subcontractor may be awarded a contract for public work on a public works project (awarded on or after April 1, 2015) unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. Contract.doc 4.3 08/12/15 WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT. IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year and date written below. CONTRACTOR: M Title (CORPORATE SEAL) CITY OF LODI, a municipal corporation M STEPHEN SCHWABAUER City Manager Date: Attest: JENNIFER M. FERRAIOLO City Clerk Approved As To Form: JANICE D. MAGDICH City Attorney CK Contract doc 4.4 08/12/15 RESOLUTION NO. 2015-151 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT FOR THE HAM LANE SIGNAL MODIFICATION IMPROVEMENTS 2015 PROJECT TO TIM PAXIN'S PACIFIC EXCAVATION, INC., OF ELK GROVE WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on August 6, 2015, at 11:00 a.m., for the Ham Lane Signal Modification Improvements 2015 Project, described in the plans and specifications therefore approved by the City Council on July 15, 2015; and WHEREAS, said bid has been checked and tabulated and a report thereof filed with the City Manager as follows: Bidder Bid Tim Paxin's Pacific Excavation, Inc. $331,934 St. Francis Electric, LLC $377,770 WHEREAS, staff recommends awarding the contract for the Ham Lane Signal Modification Improvements 2015 Project to the low bidder, Tim Paxin's Pacific Excavation, of Elk Grove. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the contract for the Ham Lane Signal Modification Improvements 2015 Project to the low bidder, Tim Paxin's Pacific Excavation, of Elk Grove, California, in the amount of $331,934; and BE IT FURTHER RESOLVED that the City Manager is authorized to execute the contract on behalf of the City. Dated: September 2, 2015 I hereby certify that Resolution No. 2015-151 was passed and adopted by the City Council of the City of Lodi in a regular meeting held September 2, 2015, by the following vote: AYES: COUNCIL MEMBERS — Chandler, Kuehne, Mounce, Nakanishi, and Mayor Johnson NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None NIFE . FERRAIOLO City Clerk 2015-151