Loading...
HomeMy WebLinkAboutAgenda Report - August 5, 2015 C-16AGENDA ITEM C,,,16 CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Adopt Resolution Approving City Payment of Central Valley Regional Water Quality Control Board Oversight Costs for PCE Cleanup Program and Appropriating Funds ($220,000) MEETING DATE: August 5, 2015 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt resolution approving City payment of Central Valley Regional Water Quality Control Board Oversight Costs for PCE cleanup program and appropriating funds in the amount of $220,000. BACKGROUND INFORMATION: The Central Valley Regional Water Quality Control Board (Board) oversees the progress of the City's effort to clean up and monitor the groundwater conditions in the Central, Southern, Western and Northern plume areas. City activities include operation of the vapor extraction and treatment facilities within the Central plume area, monitoring and reporting work for the Central, Southern and Western plume areas, construction of the Northern plume monitoring well on Garfield Street, and design of new groundwater extraction and treatment facilities on Church Street south of Tokay Street. Board staff and City staff have been continual partners in the planning, execution, and monitoring of the City's cleanup activities. Board staff reviews work plans prior to their implementation, reviews monthly monitoring reports, reviews monthly project operations reports and regularly meets with the City and its consultants. Relations between the Board and the City are excellent based upon a long history of trust and cooperation. Staff recommends approval of the attached resolution and appropriation of funds in the amount of $220,000. These funds are allocated $110,000 to cover the Board's oversight costs and $110,000 to cover staff time for fiscal year 2015/16. FISCAL IMPACT: Not applicable. FUNDING AVAILABLE: Requested Appropriation: PCE/TCE Rates 56599000.77020) $100,000 Central Plume (59099000.77020) $50,000 Northern Plume (59399000.77020) $20,000 Western Plume (59499000.77020) $50,000 FWS/FWS/tb IW Mzffl�l Jordan Ayers Deputy City Manager/Internal ervices Director "AiQ 0".,ft1r - F. Wally ndelin Public Works Director APPROVED: , City Manager K:\WP\PROJECTS\WATER\PCE,TCE\CRegional Board Payment of Oversight Costs.doc 7/27/2015 1 AA# 2 JV# CITY OF LODI APPROPRIATION ADJUSTMENT REQUEST TO: Internal Services Dept. - Budget Division 3. FROM: Rebecca Areida-Yadav 5. DATE: 7/16/2015 4. DEPARTMENT/DIVISION: Public Works 6. REQUEST ADJUSTMENT OF APPROPRIATION AS LISTED BELOW FUND # BUS. UNIT # ACCOUNT # ACCOUNT TITLE AMOUNT .A 565 32205 Fund Balance $ 100,000.00 SOURCE OF 590 32205 Fund Balance $ 50,000.00 FINANCING 593 32205 Fund Balance $ 20,000.00 594 32205 Fund Balance $ 50,000.00 B. 565 56599000 77020 Capital Pro ects $ 100,000.00 USE OF 590 59099000 77020 Capital Projects $ 50,000.00 FINANCING 593 59399000 77020 Capital Projects $ 20,000.00 594 59499000 77020 Capital Projects $ 50,000 00 7. REQUEST IS MADE TO FUND THE FOLLOWING PROJECT NOT INCLUDED IN THE CURRENT BUDGET Please provide a description of the project, the total cost of the project, as well as justification for the requested adjustment. If you need more space, use an additional sheet and attach to this form. State Water Resources Control Board and Staff time for oversight costs for PCE cleanup If Council has authorized the appropriation adjustment, complete the following: 'Meeting Date: Res No. Attach copy of resolution to this form. Department Head Signature:'i1�_ B. APPROVAL SIGNATURES Deputy City Manager/Internal Services Manager Date Submit completed form to the Budget Division with any required documentation. Final approval will be provided in electronic copy format. RESOLUTION NO. 2015-130 A RESOLUTION OF THE LODI CITY COUNCIL APROVING THE CITY'S PAYMENT OF CENTRAL VALLEY REGIONAL WATER QUALITY CONTROL BOARD OVERSIGHT COSTS FOR THE PCE CLEANUP PROGRAM AND FURTHER APPROPRIATING FUNDS WHEREAS, during operation of the Busy Bee Cleaners, tetrachloroethene (PCE) was recovered from dry cleaning process wastewater and recycled; however, some PCE was routinely discharged into the wastewater system during normal operations; and WHEREAS, from 1989 through 2004, extensive site investigation activities were conducted to evaluate the degree and size of PCE impacts to the subsurface at and near the site. In 2008, site cleanup commenced with the startup of two remediation systems operated by E2C Remediation. In 2012, the remediation systems were shut down as it was no longer cost- effective to operate the systems due to reduction of contaminants to very low concentrations; and WHEREAS, in 2013, the Site Decommissioning Workplan was approved by the Regional Water Quality Control Board. The decommissioning work is complete and included the abandonment of one extraction well, 22 groundwater monitoring wells, 38 groundwater air sparge wells, and 29 vapor extraction wells. Piping was abandoned in place, street and parking lot surfaces were restored, and the treatment equipment was removed; and WHEREAS, staff recommends approval of the City's payment of Central Valley Regional Water Quality Control Board Oversight costs for PCE cleanup program and appropriation of $220,000. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve the City's payment of Central Valley Regional Water Quality Control Board Oversight costs for PCE cleanup program; and BE IT FURTHER RESOLVED that funds in the amount of $220,000 be appropriated from the PCE/TCE Rates and Settlement Funds. Dated: August 5, 2015 I hereby certify that Resolution No. 2015-130 was passed and adopted by the City Council of the City of Lodi in a regular meeting held August 5, 2015, by the following vote: AYES: COUNCIL MEMBERS — Chandler, Kuehne, Mounce, and Nakanishi NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS —Mayor Johnson ABSTAIN: COUNCIL MEMBERS — None J �NIFERFERRAIOLO City Clerk 2015-130