HomeMy WebLinkAboutAgenda Report - April 15, 2015 C-04AGENDA ITEM C 4WE4 CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Change Order No. 3 to the Professional Services Agreement with WMB Architects, of Stockton, for Construction Administration Services for City Hall Annex First Floor Phase 2 Interior Remodel Project ($71,405) MEETING DATE: April 15, 2015 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute Change Order No. 3 to the professional services agreement with WMB Architects, of Stockton, for construction administration services for City Hall Annex First Floor Phase 2 Interior remodel project, in the amount of $71,405. BACKGROUND INFORMATION: City Council awarded the professional services agreement for design services for the City Hall Annex first floor remodel to WMB Architects on August 15, 2012. The project construction contract was awarded to Diede Construction ($2,492,000) on February 18, 2015. The requested change order (Exhibit A) is for construction administration services during the construction project. WMB will assist City staff reviewing product data, drawing submittals and resolving issues related to the daily construction activities as they arise. The project will replace the Civic Center chiller unit and add the City Hall Annex Facility to the chiller system; relocate the computer server and phone rooms from the basement to the first floor; relocate the main electrical service to the first floor; replace and relocate the emergency generator outdoors; and remodel the first floor area for use by the Parks, Recreation and Fire Administration Divisions. The planned project completion is October 2015. FISCAL IMPACT: The project will permit the Parks, Recreation and Fire Administration Divisions to return to the Civic Center complex. Funding is split among funds similar to the construction contract (27 percent General Fund, 73 percent Enterprise Funds). FUNDING AVAILABLE: General Fund (43199000.77020): $19,279 EUD (50465100.72920): $17,375 Water (56199000.77020): $17,375 Wastewater (53199000.77020): $17,375 Jordan Ayers r Deputy City Manager/Internal Services Director , "hl F. Wally S delin Public Works Director Prepared by Gary Wiman, Construction Project Manager FWS/GW/eb Attachment cc: Fire Chief Parks, Recreation and Cultural Services Director APPROVED: ` '3 I Step en Schwabau -,_ ' Manager K:\WP\PROJECTS\MISC\City Hall Annex 1st Floor Remodel 2013\CHARP Phase 2 Project\C WMB City Hall Annex Phase 2 CO3.doc 4/2/2015 Exhibit A r1r, WMB ARCHITECTS 5757 Pacific Avenue 2000 L Street Suite 226 Suite 125 Stockton CA 95207 Sacramento CA 95811 209.944.9110 916.254.5546 PROPOSAL OF SERVICES CITY HALL ANNEX —1ST FLOOR PHASE II INTERIOR REMODEL 12-62 March 17, 2015 DESCRIPTION OF THE PROJECT Construction Administration Services SUMMARY SCOPE OF SERVICES The scope of services includes: • Construction administration The proposal includes services of the following disciplines: • Architecture • Mechanical engineering (plumbing and HVAC) • Electrical engineering The proposed fee is based upon tasking the time anticipated for this phase of the work. Our proposal for architectural / engineering services is as follows: SCOPE OF SERVICES Construction Administration • 24 construction site meetings with architect — assume 6 months construction timeframe- 24 meetings provided in proposal. • Site visits for mechanical and electrical engineers. • Process and document as required General Contractor's Requests for Information (RFI's). • Process product submittals and shop drawings. • Review and evaluate substitutions to products and equipment submitted by the General Contractor. • For RFI, submittal and substitution review and processing, this proposal assumes 11 hours per week of Project Manager time and 2 hours per month Principal time. (in addition to construction meetings and punch list services) Administration services required for this work that exceed 20% of the aggregate hours provided in this proposal will be invoiced as additional services. • Monthly General Contractor payment request and progressive lien waiver review. Sub- contractor lien waiver documentation and verification responsibility of the General Contractor. www.wmbarchitects.com March 19, 2015 • Punch -list site and building evaluation at substantial completion. Develop punch list of items for correction. Follow-up site and building evaluation of punch list items at final completion. Review of General Contractor's Operations and Maintenance Manual and warranties. Assistance in facilitation of training City staff by vendors regarding building start-up requirements, staff orientation, operation of systems within the building and methods of operation as affected by the building systems (9 hours of Project Manager coordination time included in this proposal) If the City desires further training beyond that specified herein above, such further training shall be an additional service and shall be compensated as such. WMB Architects will not make exhaustive or continuous on-site inspections to check the quality or quantity of the work. The firm will also not be responsible for construction means, methods, techniques or procedures or for safety precautions and programs in connection with the work, and will not be responsible for the contractor's failure to carry out the work in accordance with the contract documents. Only services specifically described above are included in this proposal. CLIENT RESPONSIBILITIES The following are to be provided as a responsibility of the Client and be paid for by the Client: A. The Client shall designate, when necessary, a representative authorized to act in the Client's behalf with respect to the project. B. The Client shall pay all jurisdictional and utility agency costs required for permit approval and inspection. PROJECT SCHEDULE This proposal was developed with a 180 calendar day construction period timeframe assumption. FEE PROPOSAL WMB will provide these services for a fixed fee of $71,405 as incurred based on the Schedule of Hourly Rates attached, as itemized by discipline below. Reimbursable expenses are in addition to the fee and will be billed at cost plus 10 percent. WMB Architects $50,905 Alexander Scheflo & Associates, Mechanical Engineer $11,700 HCS Engineering, Electrical Engineer $8,800 Total Construction Administration Fee $71,405 Invoices shall be rendered monthly in proportion to the amount of services completed. PROPOSAL OF SERVICES I CITY OF LODI I CITY HALL ANNEX CONSTRUCTION ADMINISTRATION Page 2 March 19, 2015 If additional services are required beyond the Scope of Services described above, a Change in Project Scope agreement will be prepared for the Client's and Architect's signatures. Reimbursable expenses include printing and copying documents to develop the design and review the project, and sets required for building department processing, and bid and construction sets of drawings and specifications. WMB does not charge for mileage for client meeting or construction meeting travel. We look forward to the opportunity to work with you through the successful completion of this construction project. We have attached a Change in Project Scope for your review and signature. Consultant: WMB ARCHITECTS INC. Client: CITY OF LODI By. By: (Signature)" (Signature) Nae: Melanie Vieux, Principal Architect Name CA License C30857 WMB Architects Inc. 5757 Pacific Ave Suite 226 Stockton CA 95207 The terms of this document are valid for 90 days from date on page 1. If the proposal is not agreed to within 90 days and a contract signed, the proposal, including proposed fee and schedule, is void and the terms will be re -negotiated. Appllrovod as to f&M City Atkwney PROPOSAL OF SERVICES I CITY OF LODI I CITY HALL ANNEX CONSTRUCTION ADMINISTRATION Page 3 Schedule of Hourly Rates — 2015 WMB ARCHITECTS INC. Senior Principal Architect Principal Architect Project Architect Staff Architect Project Manager Interior Designer CADD Draftsperson / Project Support Clerical Mechanical Engineering ALEXANDER SCHEFLO & ASSOCIATES Principal Engineering Designer Drafting Computer Input Secretarial Electrical Engineering HCS ENGINEERING Principal Electrical Engineer Project/Electrical Engineer Project/Electrical Designer Project Support March 19, 2015 MR WMB ARCHITECTS Stockton I Sacramento REIMBURSABLE EXPENSE RATES $160 $135 $125 $110 $100 $100 $85 $55 $140 $120 $85 $75 $65 $65 $150 $110 $ 75 $ 50 Reimbursable Expenses are in addition to compensation for basic and additional services. Reimbursable expenses such as computer plots, reproduction, color prints, presentation materials, conference calls, postage, and shipping include actual expenditures incurred by WMB Architects in the interest of the project. Reimbursable expenses are billed at 1.1 times direct cost. PROPOSAL OF SERVICES I CITY OF LODI I CITY HALL ANNEX CONSTRUCTION ADMINISTRATION Page 4 RESOLUTION NO. 2015-40 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 3 TO THE PROFESSIONAL SERVICES AGREEMENT FOR THE CITY HALL ANNEX FIRST FLOOR PHASE 2 INTERIOR REMODEL PROJECT WHEREAS, City Council awarded the Professional Services Agreement for the City Hall Annex first floor remodel to WMB Architects, of Stockton, on August 15, 2012; and WHEREAS, Change Order No. 3 is for construction administration services during the construction project, allowing WMB to assist City staff in reviewing product data, drawing submittals, and resolving issues related to the daily construction activities as they arise. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize the City Manager to execute Change Order No. 3 to the Professional Services Agreement for the City Hall Annex First Floor Phase 2 Interior Remodel Project with WMB Architects, of Stockton, California, in the amount of $71,405. Dated: April 15, 2015 I hereby certify that Resolution No. 2015-40 was passed and adopted by the City Council of the City of Lodi in a regular meeting held April 15, 2015, by the following vote: AYES: COUNCIL MEMBERS — Chandler, Kuehne, Mounce, Nakanishi, and Mayor Johnson NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None NNIFER M. FERRAIOLO }ty Clerk 2015-40