AGENDA TITLE: Receive Update on Emergency Condition at White Slough Water Pollution Control
Facility Digesters No. 1 and No. 2
MEETING DATE: April 1, 2015
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Receive update on emergency condition at White Slough Water
Pollution Control Facility Digesters No. 1 and No. 2.
BACKGROUND INFORMATION: White Slough Water Pollution Control Facility (WSWPCF) has four
covered anaerobic digesters that serve the purpose of breaking
down sewage sludge that enters the plant. On July 16, 2014,
Council declared an emergency condition in response to concurrent roof failures on Digesters No. 1 and
No. 2. Public contract code requires Council to review the emergency action at its next regularly -scheduled
meeting and each regularly -scheduled meeting thereafter until the emergency is terminated.
The completed Digester No. 2 roof structure is installed, and work to begin start up procedures continues.
Digester No. 2 is expected to be in service at the time of this Council meeting.
The new roof for Digester No. 1 has been fabricated, coated and set aside until it is time for installation. The
task of removing the contents of Digester No. 1 is underway and is expected to take approximately two
weeks to complete.
The procurement and construction schedule reflecting project milestones is provided below. The work is
progressing on the original schedule, and there is no substantial change from last report.
Project Definition Meeting
July 21, 2014
Issue Final Contract Documents
August 1, 2014
Receive GMP Proposals
August 20, 2014
Issue Notice to Proceed
September 15, 2014
Complete Digester No. 2 Improvements
April 2, 2015
Complete Digester No. 1 Improvements
August 27, 2015
FISCAL IMPACT: Not applicable
FUNDING AVAILABLE: Not applicable
�of F. Wally Sandelin
Public Works Director
Prepared by Charlie Swimley, City Engineer / Deputy Public Works Director
FWS/CES/smh
cc: Associate Civil Engineer Nathan Charlie Swimley, City Engineer / Deputy Public Works Director
Wastewater Plant Superintendent Construction Project Manager
r -
APPROVED:
'-Step en chwa suer, City Manager
K:\WP\PROJECTS\SEWER\WSWPCF\DigesterRepairs\Council Updates\CUpdate040115.doc 3/18/2015