HomeMy WebLinkAboutAgenda Report - March 18, 2015 C-09AGENDA ITEM Cd*9 Y, CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Accept Improvements Under Contract for Water Meter Program Phase 4 MEETING DATE: March 18, 2015 PREPARED BY: Public Works Director RECOMMENDED ACTION: Accept Improvements under contract for Water Meter Program Phase 4. BACKGROUND INFORMATION: The contract was awarded to Teichert Construction, of Davis, in the amount of $3,645,238, on March 19, 2014. The contract has been completed in substantial conformance with the plans and specifications approved by City Council. At the October 20, 2010 City Council meeting, a seven-year construction phasing was approved and the property owner meter payment was capped at $300 per parcel. The project area for Phase 4 is presented in Attachment A and included the installation of 1,338 meters and the replacement of 22,130 feet (4.2 miles) of water main. The contract completion date was November 17, 2014. The final contract price was $4,068,626.62. The difference between the contract amount and the final contract price is due to the change orders ($423,388.62, 12 percent of original contract) described below. a. Change Order No. 1: Includes various time and material changes as directed by City staff due to unknown conditions or City requested changes in the field. $97,470.06 (Attachment B) b. Change Order No. 2: Includes various time and material changes as directed by City staff due to unknown conditions or City requested changes in the field. $324,008.01 (Attachment C) c. Change Order No. 3: Includes work performed on a time and materials basis to replace several defective owner supplied ERT's ($1,627.07) and repairs not related to the new meter work at 14 Yale Way ($283.48). $1,910.55 Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: Water main leak and service repairs will be reduced. No additional costs will be incurred for reading of the meters as they are automatically read concurrent with the reading of the electric meters. FUNDING AVAILABLE: This project was funded by Water Capital Fund (181) :f F. Wally ndelin Public Works Director FWS/smh Attachment cc: Gary Wiman, Construction Project Manager Tony Valdivia, RMC Water and Environment Neil O. Anderson and Associates Teichert Construction APPR r, City Manager K:\WP\PROJECTS\WATER\Meters\Water Meter Program Phase 4\CAccept doc 3/3/2015 LW1.J U1 WW WWWU L , ' - , ., i t i ` .' I � 3JN'd�10 iii--i-W ) LL ° llyFj I'M IRTri L. HI f _ _1010,11,11aw1w O z NO1JNI-113M 3 0131OVd a ❑ H1NIa00 - ti wo wo z r a z o 0 d Q V d O sIw Ou Y w 0 3001a8WO w � 0 4 m � Ow SN 8 w O V JUJ Ix Z 7. a WVH r J w#f c p NOlJNIINnH i� f SNIn3N � - c NOldWVH i i CLOWE Tr. i NO 3H1'd- i VINIEDUI ,T �- 0 �- O ~ NOlJNISN3>411 0 S3a0V dOOM -k M w w D O _r (L z U) i_ U ¢ U rJ_L_T�aal:if_Wa_Ol Oc mZN311V V1SIAVn DLN3aaVz p2IAINIV'd : Va1n1NOl3aN2 ipExpiind. o Q vp011 d -f m 3lVJl J D J r -'W .. Q 31N30 p U aNV131 m OlN3wVHOVS a�Qjl w _ a w 7p89IS3M p �- z a �; l z O O N LD m LL Water Meter Program Phase 4 Change Order #1 Tally Teichert EW# Amount Description Notes 9001 $ 563.08 Open trench service to 2340 Cabrillo 9002 $ 18,763.22 Additional Pot Holing and trench realignment 9003 $ - Void 9004 $ 1,978.67 Service work obstructions at 2100 Cabrillo 9005 $ 16,533.75 RFI 2000 ADA ramp and SD work at Wood & Cabrillo 9006 $ 9,345.79 Mills Avenue treated subgrade extra work 9007 $ 1,947.21 Misc Plumbinf repairs 9008 $ 6,466.46 Service Changes on Mills Per RFI 2005 9009 $ 1,295.99 Replace Hydrant with Blow -off Per RFI 2003 9010 $ 12,526.65 Cabrillo Area C&G Remove and Replace 9011 $ 1,918.31 Preserve and reset Survey Monuments not shown on plans 9012 $ 947.94 Flush Cabrillo Water main 9013 $ 9,527.15 Additional Traffic Control Lodi Ave for Exisitng Main 9014 $ 4,229.60 Delayed Main shutdown 9015 $ 450.69 Jackson St SD Leak 9018 $ 918.91 Corbin Lane 409 bad valve Delay 9022 $ 5,387.85 Corbin Area C&G Remove and Replace 9023 $ 4,668.79 Unknown Obstruction s on Debbie Lane Total $ 97,470.06 Water Meter Program Phase 4 Change Order 2 Tally Teichert CR # Amount Descripton 9007 $ 964.18 Plumbing on Capel & Debbie 9020 $ 548.60 Sawcutting on Elm Street 9021 $ 20,918.67 RFI 2007 - Lodi Ave WM Valve Replacements 9025 $ 420.77 Broken Phone lines 9026 $ 4,728.02 Relocate Hot Tap on Mills Ave 9027 $ 7,790.60 O.T. due to existing conditions 9029 $ 65,163.07 Corbin Area Digouts 9030 $ 1,791.04 Additional Sawcutting on Elm St for SD repair 9031 $ 21,951.79 Abandonment Issues 9034 $ 8,642.71 2124 Jackson Driveway 9035 $ 3,570.82 Shady Acres 8" BF Valve 9036 $ 355.41 2160 Debbie Lane additional work 9037 $ 22,417.67 Elm/Loma Crosswalk Remove & Replace 9038 $ 1,823.94 Additional Traffic Control on Lodi Ave 9039 $ 2,301.33 Add Fire Hydrant on Bella Vista 9040 $ 3,531.89 Misc Service Repairs 9041 $ 1,179.29 Subgrade repair @ 2100 W Elm St. 9042 $ 6,111.53 Mismarked Services 9043 $ 313.84 Repair sewer at 623 Alto 9044 $ 12,372.15 Lodi Ave cobble obstruction issues 9045 $ 1,388.28 Mismarked WM Abandonments 9046 $ 1,808.67 Raise Survey Monuments on Shady Acres 9047 $ 3,000.30 Lodi Ave open cut services 9048 $ 1,550.18 Jerry Ln concrete R&R 9049 $ 3,392.35 Reconnect main & Service on Corbin 9050 $ 2,506.86 Lower Sac AC Section thickness 9051 $ 2,948.37 2070 Cabrillo service change 9052 $ 1,167.84 Fire Hydrant on Benson 9053 $ 344.41 Additional work at 348 Lower Sacramento Road 9054 $ 2,755.45 Remove gate valves on Allen Drive 9055 $ 411.26 Extra Service work at 8 Benson 9056 $ 16,695.30 Replace Type "A" Lids 9057 $ 7,402.56 Misc Patch Paving Areas 9058 $ 3,851.20 EW for 11/2" WS to 2396 Cabrillo 9060 $ 40,483.11 Elm St, Mills & Lodi Ave 6" Paving 9061 $ 6,180.20 RFI 2017 9062 $ 4,675.63 Lodi Ave Shutdown Items 9063 $ 269.60 Extra service work at 2370 Cabrillo 9064 $ 1,447.62 OT on 8/16/14 9065 $ 729.76 EW For Pool plumbing 9066 $ 1,259.21 WM Abandonment @ 142 S. Mills 9067 $ 3,121.66 EW Well Site Abandonment 9069 $ 2,114.74 EW @ 2224 Jackson St. 9070 $ 8,531.20 EW Patch Paving 9071 $ 11,779.95 C&D Curb Stop Material Change 9072 $ 5,175.00 ACP Pipe Removal from MSC 9073 $ 2,119.98 Add Duplex service on Elm St $ 324,008.01 Total CO #2 CITY COUNCIL STEPHEN SCHWABAUER City Manager BOB JOHNSON, Mayor CITY OF L O D I JENNIFER M. FERRAIOLO MARK CHANDLER, City Clerk Mayor Pro Tempore PUBLIC WORKS DEPARTMENT JANICE D. MAGDICH DOUG KUEHNE Cit Attorney MOUNCE CITY HALL, 221 WEST PINE STREET y y JOANNE ALAN P.O. BOX 3006 F WALLY SANDELIN NAMOUN I LODI. CALIFORNIA 95241-1910 Public Works Director (209)333-6706 FAX (209) 333-6710 EMAIL pwdept@lodi.gov http:\\www lodi gov March 11, 2015 RMC Water and Environment Neil O. Anderson and Associates Attn: Tony Valdivia 902 Industrial Way 2001 N. Main Street, Ste. 400 Lodi, CA 95240 Walnut Creek, CA 94596 Teichert Construction P.O. Box 1890 Davis, CA 95617 SUBJECT: Accept Improvements Under Contract for Water Meter Program Phase 4 Enclosed is a copy of background information on an item on the City Council agenda of Wednesday, March 18, 2015. The meeting will be held at 7 p.m. in the City Council Chamber, Carnegie Forum, 305 West Pine Street. This item is on the consent calendar and is usually not discussed unless a Council Member requests discussion. The public is given an opportunity to address items on the consent calendar at the appropriate time. If you wish to write to the City Council, please address your letter to City Council, City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the mail. Or, you may hand -deliver the letter to City Hall, 221 West Pine Street. If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's card (available at the Carnegie Forum immediately prior to the start of the meeting) and give it to the City Clerk. If you have any questions about communicating with the Council, please contact Jennifer M. Ferraiolo, City Clerk, at (209) 333-6702. If you have any questions about the item itself, please call me at (209) 333-6706. F. Wally Sandelin Public Works Director FWS/smh Enclosure cc: City Clerk NCCMTG DOC