HomeMy WebLinkAboutAgenda Report - October 1, 2014 C-10AGENDA ITEM C,lt)
Crrv on Lour
C ouNcrr, C oIvIMUNICATIoN
TM
AGENDA TITLE:
MEETING DATE: October 1,2014
PREPARED BY: Public Works Director
Adopt Resolution Authorizing City Manager to Execute Change Order No. 6 to the
2013-2015 Sidewalk Repair Program and Miscellaneous Concrete Work Contract
with Popuch Concrete Contracting, lnc., of Lodi ($218,514)
RECOMMENDED ACTION Adopt resolution authorizing City Manager to execute Change Order
No. 6 to the 2013-2015 Sidewalk Repair Program and
Miscellaneous Concrete Work contract with Popuch Concrete
Contracting, lnc., of Lodi, in the amount of $218,514.
BACKGROUND INFORMATION: Beginning in 2013, the Public Works Department took an aggressive
ü,3i,",i'i,11Å:t;i'+låHïï:ii':llili'iil:"H1'åL'*'0"
Sidewalk Survey that identified approximately 11,000 sidewalk offset locations. Staff currently uses three
different methods for removing the sidewalk offsets, depending on the offset height. These methods are
sidewalk grinding, asphalt patching, and full replacement. Part-time staff in the Streets Division perform
the asphalt patching, while the sidewalk grinding and replacements are performed through two separate
contracts. The grinding is performed through the 2013-2015 Sidewalk Grinding Program and the
sidewalk replacement work is performed through the 2013-2015 Sidewalk Repair Program and
Miscellaneous Concrete Work (Contract).
The two-year Contract was publically bid in May 2013 and awarded by City Council on June 19, 2013, to
the lowest bidder, Popuch Concrete Contracting, lnc., for $198,600. At project award, $300,000 was
budgeted over FY 2013114 and FY 2014115 ($150,000 each year). The funding includes a combination
of Measure K and Transportation Development Act (TDA) Bike/Pedestrian funding,
Since the original contract was executed, additional funding has been added by change order to
accommodate extra work requested by the City (Public Works and other departments) and to extend
contract funding for the second year of the two-year term. An example of additional work requested by
the City includes ADA ramp installations ($39,559), Parks Department concrete work ($19,450), Library
concrete work ($3,514), WaterAlVastewater concrete work ($3,097), and the Fire Station No. 1 driveway
replacement ($34,938). lf the proposed Change Order is not approved, sidewalk replacement work
performed between now and the end of the fiscal year will be minimal since the current remaining
balance on the Contract is approximately $50,000.
The change orders and the funding to cover the contract extension increased the total contract amount to
$375,000, which is 25 percent above the $300,000 approved for the two budget years. Proposed
Change Order No. 6 ($218,514) will increase the total Contract amount to $593,514, The additional
contract amount will be used to continue the aggressive sidewalk replacement work through the end of
FY 2014115.
APPROVED
enS
K:\WP\PROJ ECTS\STREETSU0l 3 SidewalkRepaiACC-Change-Orders.doc
er, City Manager
sl1sl2014
Adopt Resolution Authorizing City Manager to Execute Change Order No. 6 to the 2013-2015 Sidewalk
Repair Program and Miscellaneous Concrete Work contract with Popuch Concrete Contracting, lnc., of
Lodi ($218,514)
October 1,2014
Page 2
ïhe Proposed Change Order No. 6 breakdown is as follows
Measure K: $ 200,000 (available from2014115 budget)Library: $ 3,514 (to add to the contract total for previously completed work)Water: $ 7,500 (for both previously completed and future work)
Wastewater: $ 7,500 (for both previouslv completed and future work)Total: $ 218,514
Gontract Summary:
$198,600 Original Contract
$ 19,450 Change Orders 1-4 (Parks Department)
$156.950 Chanqe Order 5 (Fiscal Year 2014115 Additions)
$375,000
$218,514
Current Contract
Proposed Chanqe Order No. 6
$593,514 Proposed Contract Amount
F|SCAL IMPACT: Funding amounts were already approved in the 2014115 budget. Money
spent from this change order will reduce the risk of liability associated with
the tripping hazards and/or non-compliant concrete improvements. lf the
change order is not executed, all unused funds will go back into their respective accounts for future use,
FUNDING AVAILABLE This change order will be funded by Measure K (325054), Water
Operations (180456), Wastewater Operations (170a0a), and Library
Operations (210801) previously approved in the Fiscal Year 2014115
Budget.
c\fu.(Øv
Jordan Ãyèrs ì /
Deputy City Manager/lnternal Services Director
F. Wally in
Public Works Director
Prepared by Sean Nathan, Associate Civil Engineer
FWS/SN/pmf
Attachment
cc: Associate Civil Engineer Nathan
Utility Superintendent
City Engineer/Deputy Public Works Director
K:\WP\PROJECTS\STREETSU0l 3 SidewalkRepaiACC-Change-Orders.doc 9t1512014
CITY OF LODI
PROPOSED CHANGE ORDER
PROJECT : 2013-2015 SIDEWALK REPAIR
CONTRACTOR:Popuch Concrete Contracting, Inc.PCO No.:
RFI No.:
ARCHITECT/ENGINEER:FI No.:
$200,000 (325054.7727)
$ 3,514 (210801.7334)
$ 7,500 (170404.7352)
$ 7,500 (180456.7352)
Request, Proposal, Recommendation And Approval
Requesting Official:Lance Roberts Request Date: 8/19/2014 Schedule Impact: 0 Days
Contractor Proposal Date:N/A Add Amount: $218,514.00 Deduct Amount
Reason For Change:Account:
ORIGINAL CONTRACT: 198,600.00$
PREVIOUS ADDS: 176,400.00$
Contractor Date PREVIOUS DEDUCTS: -$
THIS CHANGE ORDER: $218,514.00
Deputy Public Works Director Date TOTAL CONTRACT AMOUNT
INCLUDING ALL CHANGE ORDERS:
Public Works Director Date CONTRACT TIME ADJUSTMENT 0 DAYS
ORIGINAL COMPLETION DATE:6/30/2015
City Manager Date ADJUSTED CONTRACT
COMPLETION DATE:
See Above
6/30/2015
N/A
N/A
N/A
Brief Description Of Work
Submit Proposal Within 15 Days Upon Receipt of This Request
This Change Order is being processed based on additional funding that is available. Section 6-04.01 of the project
specifications states that:
"Work orders will be issued for curb, gutter and sidewalk repairs as they are needed during the 2013/14 and
2014/15 fiscal years. The quantities shown on the bid proposal are approximate quantities. The City is anticipating
approximately $300,000 available for sidewalk and miscellaneous concrete installation in the fiscal years 2013/14
and 2014/15 ($150,000 each year). Funding from other sources may increase the amount of work performed by the
Contractor."
CO No.:6
CONTRACTOR AGREES TO FURNISH ALL LABOR AND MATERIALS AND PERFORM ALL WORK REQUIRED TO COMPLETE THE
ABOVE DESCRIBED WORK CHANGE IN ACCORDANCE WITH THE REQUIREMENTS FOR SIMILAR WORK COVERED BY THE
CONTRACT EXCEPT AS OTHERWISE STIPULATED HEREIN FOR THE STATED CONSIDERATION. TO PERFORM THE CHANGES FOR
THE AMOUNT INDICATED WHICH INCLUDES ANY EXTENDED OR JOBSITE OVERHEAD, DISRUPTION, RIPPLE EFFECT AND OTHER
IMPACT COSTS. NO WORK WILL BE STARTED UNTIL THIS PROPOSAL IS ACCEPTED. IF THE CONTRACTOR DOES NOT SIGN
ACCEPTANCE OF THIS ORDER, THE CONTRACTOR SHOULD REFER TO SECTION 4-1.03A OF THE STANDARD SPECIFICATIONS
REGARDING FILING A WRITTEN PROTEST WITHIN THE SPECIFIED TIME.
593,514.00$
The following amounts are being added:
PROGRAM AND MISC. CONCRETE WORK
City of Lodi, Public Works
$0.00
Work Needed for Other Departments.
MiscConcreteCO6.xls 9/10/2014
RESOLUTION NO. 2014-17 4
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING THE CITY MANAGER TO EXECUTE
CONTRACT CHANGE ORDER NO. 6 TO THE
2013.2015 SIDEWALK REPAIR PROGRAM AND
MISCELLANEOUS CONCRETE WORK CONTRACT
WITH POPUCH CONCRETE, INC., OF LODI
------
WHEREAS, the 2013-2015 Sidewalk Repair Program and Miscellaneous
Concrete Work contract was publically bid in May 2013 and awarded by City Council on
June 19, 2013, to the lowest bidder, Popuch Concrete Contracting, lnc., for $198,600.
At project award, $300,000 was budgeted over FY 2013114 and FY 2014115 ($150,000
each year); and
WHEREAS, since the original contract was executed, additional funding has
been added by change order to accommodate extra work requested by the Public Works
Department, Fíre Department, Parks Department and Library and to extend contract
funding for the second year of the two-year term; and
WHEREAS, staff recommends approval of Change Order No. 6 as otherwise
sidewalk replacement work performed between now and the end of the fiscal year will be
minimal since the current remaining balance on the Contract is approximately $50,000.
NOW, THEREFORE, BE lT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute Change Order No. 6 to the 2013-2015 Sidewalk
Repair Program and Miscellaneous Concrete Work contract with Popuch Concrete
Contracting, lnc., of Lodi, California, in the amount of $218,514.
Dated: October 1,2014
==== ====== ========== ======= ======================= =========== == ====
I hereby certify that Resolution No. 2014-174 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held October 1, 2014, by the
following vote:
AYES COUNCIL MEMBERS - Hansen, Johnson, Mounce, and
Nakanishi
NOES:
ABSENT
ABSTAIN
COUNCIL MEMBERS - None
COUNCIL MEMBERS - Mayor Katzakian
COUNCIL MEMBERS - None
-h(nvv"--
ON
2014-174
Clerk
ROBIS