HomeMy WebLinkAboutAgenda Report - August 6, 2014 C-10AGENDA ITEM c.tD Crry or Lour CouNcIr, CoTvtMUNIcATIoN IM AGENDA TITLE: MEETING DATE: PREPARED BY: Adopt Resolution Awarding Contracts for Fire Station No. 2 Replacement Project to Diede Construction, lnc., of Woodbridge, for Construction ($4,227,740) and Neil O. Anderson and Associates, of Lodi, for Construction Testing and lnspection Services ($150,000) and Appropriating Funds ($S,231,400) August 6,2014 Public Works Director RECOMMENDED ACTION: Adopt resolution awarding contracts for Fire Station No. 2 Replacement Project, to Diede Construction, lnc., of Woodbridge, for construction, in the amount of 94,227,74e, and Neil O. Anderson and Associates, of Lodi, for construction testing and inspection services, in the amount of $150,000, and appropriating funds in the amount of $5,231,400. BAGKGROUND INFORMATION: The project will replace the existing Fire Station No. 2 with a new 7,900-square-foot facility, complete with two apparatus bays, four sleeping rooms, living areas, equipment storage, exercise room, offices, public lobby and 1,80O-square-foot support vehicle storage building. Drawiñgs of the project site, floor plan and elevations are attached for reference as Exhibit A. The projéct was designed and'O¡O to allow for design/build of the building structural system. Staff is recommending Bid Alteinate No. 1 be accepted. Bid Alternate No. 1 would replace all on-site asphalt paving with structural concrete pavement. Concrete pavement will hold up to the weight and turning of the fire vehicles and decrease long{erm maintenance costs. The cost of the alternate is $36,000 and is included in the requested awaid amount. The project will also include numerous off-site improvements. The Public Works Department will take advantage of the project timing to perform necessary improvements to area streets and utilities. Neil O. Anderson and Associates will provide the required construction testing and inspection services for this project. Plans and specifications for this project were approved on Aprll2,2014. The City received the following four bids for this project on June 26,2014. Diede Construction, lnc., has signed ihe required Local Hire forms and will conform to the requirements. Bidder Engineer's Estimate Diede Construction, lnc. Simile Construction Service, lnc Bobo Construction, lnc. Meehleis Modular Buildings, lnc*Corrected total APPROVED: K:\WP\PROJECTS\MISC\F|reSta2\Fire Station #2 Location Woodbridge Modesto Elk Grove Lodi Base Bid $3,216,941 $4,191,740* $4,359,037" $4,942,150 $5,100,211 Replacement 20 1 3\CAward.doc er 7t30t2014 Adopt Resolution Awarding Contracts for Fire Station No. 2 Replacement Project to Diede Construction, lnc., of Woodbridge, for Construction ($4,227,740) and Neil O. Anderson and Associates, of Lodi, for Construction Testing and lnspection Services ($150,000) and Appropriating Funds ($5,231 ,400) August 6,2014 Page 2 FISCAL IMPACT The new Station will eliminate ongoing maintenance costs at the former Fire Station No. 2 facility. FUNDING AVAILABLE: This project will be funded through a combination of contributions from one- time funds, debt service savings, contributions from the Fire Department Vehicle Replacement fund, contributions from Streets and Water funds for off-site improvements, sale of property and unbudgeted property tax receipts in Fiscal Year 2014115. Details for each funding source are listed below. An appropriation adjustment form is attached. The difference between the total project funding and the project budget is the remaining rent on the modular facilities at the existing Fire Station No. 2. Source General Fund Capital Outlay (Fund 1211) Debt Service Savings (Fund 1211) Fire Dept. Vehicle Replacement (Fund 120) Measure K (Fund 325) Water Capital Fund (Fund 181) Sale of Property (Fund 1211) Property Tax (Fund 100) Total $5,231,400 Jordan Ayers Deputy City Manager/lnternal Services Director F. Wally n Public Works Director Prepared by Gary Wiman, Construction Project Manager FWS/GWpmf Attachment cc: Fire Chief Amount $690,000 $3,388,100 $125,300 $199,000 $189,000 $400,000 $250,000 ti K:\WP\PROJECTS\MISC\F|reSta2\Fire Station #2 Replacement 2013\CAward.doc 7t30t2014 FIELD BRICKFASCIA/METAL CAP“Seattle Red”ACCENT BRICK 1ACCENT BRICK 2 City Of Lodi Fire Station #2 Replacement Project Budget July 15, 2014 K:\WP\PROJECTS\MISC\FireSta2\Fire Station #2 Replacement 2013\FS2R Project Budget CC.xls 7/30/2014 Budget Item Amount Construction Utility Services (PG&E, EUD, AT&T)$50,000 Construction Contract (Bid Amount + Alt)$4,227,740 Plan Check/Permit Fee (Building Dept.)$50,223 Plan Printing Costs (ARC)$5,000 Project Management (City Staff)$100,000 Copy/Shipping Expenses Estimate $2,500 Testing & Inspection (NOA)$150,000 Construction Total $4,585,463 Equipment Purchase Office Furniture (Durst Contract Interiors)$20,000 Data/Communications Equipment Advantel/Kratos/Delta Wireless $100,000 Moving $15,000 Equipment Total $135,000 Sub Total $4,720,463 Project Contingency 10%$472,046 Project Total Budget $5,192,509 RESOLUTION NO. 2014-138 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING AND AUTHORIZING THE CITY MANAGER TO EXECUTE CONTRACTS AND coNTRAcTCHANGEoRDERSFoRTHEFIRESTATIoNNo.2 REPLACEMENT PROJECT AND FURTHER APPROPRIATING FUNDS ======================================================================== WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on .June 26, 2014, al 11:00a.m., for the Fire Station No.2 Replacement Project, described in the plans and specifications therefore approved by the City Council on April 2,2014i and WHEREAS, said bids have been checked and tabulated and a report thereof filed with the City Manager as follows: Bidder Diede Construction, lnc. Simile Construction Service, lnc Bobo Construction, lnc. Meehleis Modular Buildings, lnc *Corrected total WHEREAS, staff recommends accepting Bid Alternate No. 1, in the amount of $36,000, to replace all on-site asphalt paving with structural concrete pavement, which will hold up to the welght and turning of the fire vehiclès and decrease long-term maintenance costs; and WHEREAS, staff recommends awarding the contract for the Fire Station No. 2 Replacement project to the low bidder, Diede Construction, lnc., of Woodbridge, California, in the amount of $4,227 ,740; and WHEREAS, Diede Construction, lnc., has signed the required Local Hire forms and will conform to the requirements; and WHEREAS, staff recommends Neil O. Anderson and Associates, of Lodi, perform construction testing and inspection services for the project, for a contract amount of $150,000. NOW, THEREFORE, BE lT RESOLVED that the Lodi city council does hereby award the construction contract for the Fire Station No. 2 Project to the low bidder, Diede Construction, lnc., of Woodbridge, California, in the amount of $4,227,740 and the construction testing and inspection servicel contract to Neil O. Anderson and Associates, of Lodi, California, in the amount of $150,000; and BE lT FURTHER RESOLVED that the city Manager is hereby authorized to execute the contracts and contract change orders within the budget appropriation amount; and BE lT FURTHER RESOLVED that funds in the amount of $5,231,400 be appropriated for the project from General Fund Capital Outlay, Debt Service Savings, Fire Department Vehicle neplacement, Measure K, Water Capital Fund, Sale of Property, and Property Tax. Dated: August 6,2014 ========================================================================I hereby cerlify that Resolution No. 2014-138 was passed and adopted by the City Council of the City of [odi in a regular meeting held August 6, 2014, by the following vote: Base Bid $ 4,191,740* $ 4,359,037* $ 4,942J50 $ 5,100,211 COUNCIL MEMBERS - Hansen, Mounce, Nakanishi, and Mayor Katzakian COUNCIL MEMBERS - Johnson COUNCIL MEMBERS - None COUNCIL MEMBERS - None NNIFE AYES: NOES: ABSENT: ABSTAIN Bô'6rAd>- 2014-138 ity Clerk M. ROBISON