HomeMy WebLinkAboutResolutions - No. 2016-97RESOLUTION NO. 2016-97
A RESOLUTION OF THE LODI CITY COUNCIL
REJECTING NON-RESPONSIVE BID AND AWARDING
THE CONTRACT FOR THE SHADY ACRES
STORMWATER PUMP REPLACEMENT PROJECT TO
THE LOWEST RESPONSIVE BIDDER,
TTS CONSTRUCTION CORPORATION, OF LODI
WHEREAS, the Shady Acres stormwater pump station serves 806 acres of
developed land inside the B-1 Basin watershed; and
WHEREAS, the original three vertical turbine pumps were installed in 1983 and
have reached their expected service life; and
WHEREAS, this project consists of furnishing and installing three 40 -horsepower
vertical axial flow turbine pumps and other incidental and related work, all as shown on
the plans and specifications; and
WHEREAS, in answer to notice duly published in accordance with law and the
order of this City Council, sealed proposals were received and publicly opened on
May 18, 2016, at 11:00 a.m., for the Shady Acres Stormwater Pump Replacement
Project, described in the plans and specifications therefore approved by the City Council
on April 20, 2016; and
WHEREAS, said bids have been checked and tabulated and a report thereof
filed with the City Manager as follows:
BIDDER
Howk System
TTS Construction Corp.
Golden State Irrigation and Pump
Richard Townsend Construction
GSE Construction
** Non -Responsive Bid
LOCATION
BID
Modesto
$145,500.00**
Lodi
$148,702.00
Stockton
$158,499.98
Oakdale
$166,348.99
Livermore
$181,700.00
WHEREAS, the lowest apparent bidder, Howk System, did not submit its bid on
the required bid proposal form as specified in Addendum No. 1 of the project, deeming
the bid non-responsive; and
WHEREAS, staff recommends rejecting the non-responsive bid from
Howk System, and awarding the contract for Shady Acres Stormwater Pump
Replacement Project to the lowest responsive bidder, TTS Construction Corporation, of
Lodi, in the amount of $148,702.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
reject the bid from Howk System, of Modesto, as being non-responsive; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby award the
contract for Shady Acres Stormwater Pump Replacement Project to the lowest
responsive bidder, TTS Construction Corporation, of Lodi, California, in the amount of
$148,702; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to
execute the contract on behalf of the City of Lodi.
Dated: June 15, 2016
I hereby certify that Resolution No. 2016-97 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 15, 2016 by the following vote:
AYES: COUNCIL MEMBERS — Johnson, Kuehne, Mounce, Nakanishi,
and Mayor Chandler
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
NNIFER . FERRAIOLO
ity Clerk
2016-97