HomeMy WebLinkAboutResolutions - No. 2016-57RESOLUTION NO. 2016-57
A RESOLUTION OF THE LODI CITY COUNCIL APPROPRIATING
FUNDS FOR WATER METER PROGRAM PHASE 5
WHEREAS, the City Council awarded the contract for the Water Meter Program Phase 5
to Knife River Construction, of Stockton, in the amount of $2,778,225, on March 4, 2015; and
WHEREAS, the Water Meter Program Phase 5 included the installation of 1,595 meters
and the replacement of 17,000 feet (3.2 miles) of water main; and
WHEREAS, 700 meter installations were added and two alleys were reconstructed due
to existing sewer conditions that required immediate attention; and
WHEREAS, the final contract price was $3,844,188.59. The difference between the
contract amount and the final contract price is due to change orders totaling $1,066,858.59 or
38 percent of the original contract amount; and
WHEREAS, staff recommends appropriating funds in the amount of $213,548 for the
Water Meter Program Phase 5 project.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
appropriate funds in the amount of $213,548 for the Water Meter Program Phase 5 project.
Dated: May 4, 2016
r I hereby certify that Resolution No. 2016-57 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held May 4, 2016 by the following vote:
AYES: COUNCIL MEMBERS — Johnson, Kuehne, Mounce, Nakanishi, and
Mayor Chandler
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
J N[F+PRAIOLO
ity Clerk
2016-57