HomeMy WebLinkAboutResolutions - No. 2013-99RESOLUTION NO. 2013-99
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
AND AUTHORIZING THE CITY MANAGER TO EXECUTE
CONTRACT FOR ALLEY IMPROVEMENT PROJECT — PHASE 4
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on May 1, 2013, at 11:00 a.m.,
for the Alley Improvement Project — Phase 4, described in the plans and specifications therefore
approved by the City Council on March 20, 2013; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Bid
A. M. Stephens Construction
$
151,356.75
Breneman, Inc.
$
194,684.00
All Phase Construction
$
198,929.00
Biondi Paving & Engineering
$
202,360.80
George Reed
$
238,421.00
FBD Vanguard Construction
$
247,982.40
Martin Brothers Construction
$
256,250.00
Robert Burns Construction
$
267,575.80
WHEREAS, staff recommends awarding the contract for the Alley Improvement Project
— Phase 4 to the low bidder, A. M. Stephens Construction Company, Inc., of Lodi, California, in
the amount of $151,356.75.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for the Alley Improvement Project — Phase 4 to the low bidder, A. M. Stephens
Construction Company, Inc., of Lodi, California, in the amount of $151,356.75; and
BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the
contract.
Dated: June 5, 2013
hereby certify that Resolution No. 2013-99 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 5, 2013, by the following vote:
AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS— None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — Moun5p---7
N Y011HL
City Clerk
2013-99