AGENDA TITLE: Accept Improvements Under Contract for Electric Utility Substructures,
Highway 99 South of Kettleman Lane and Thurman Street West of Guild Avenue
MEETING DATE: July 7, 1999
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Electric Utility
Substructures, Highway 99 South of Kettleman Lane and Thurman Street
West of Guild Avenue" contract and direct the City Engineer to file a
Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Royal Electric Company, of
Sacramento, on April 7, 1999, in the amount of $52,270.00. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
The contract completion date was July 7, 1999, and the actual completion date was June 4, 1999. The
final contract price was $56,231.20. The difference between the contract amount and the final contract
price is mainly due to adjustments in the contract quantities for trenching and conduit work to pay the
contractor for the actual work performed.
FUNDING: Budgeted Fund: Electric Utility Fund Distribution System Improvements
Contract Amount: $56,300.00
Richard C. Prima, Jr.
Public Works Director
Prepared by Wesley Fujitani, Senior Civil Engineer
RCP/WKF/pmf
cc: Purchasing Officer
EUD Engineering and Operations Manager