HomeMy WebLinkAboutResolutions - No. 2012-21RESOLUTION NO. 2012-21 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING CONTRACTAND AUTHORIZING THE CITY MANAGERTO EXECUTE AGREEMENTS FOR THE WATER METER PROGRAM PHASE 2 PROJECT AND FURTHER APPROPRIATING FUNDS WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council, sealed bids were received and publicly opened on February 8, 2012, at 11 :00a.m., for Water Meter Program Phase 2, described in the specifications therefore approved by the City Council on December 21,2011; and WHEREAS, said bids have been checked and tabulated and a report thereof filed with the City Manager as follows: Bidder Bid Teichert Construction $4,199,640 Navajo Pipelines $4,411,230 Knife River Construction $4,496,395 Mountain Cascade $4,598,370 Vinciguerra Construction $4,733,820 Mozingo Construction $4,769,280 Marques Pipeline $4,985,995 Preston Pipelines $5,318,775 Vulcan Construction $5,493,331 Arrow Construction $5,624,42911 Pacific Underground $5,750,517 West Valley Construction $7,324,961 *Corrected Total WHEREAS, staff recommends awarding the contract for Water Meter Program Phase 2 to the low bidder, Teichert Construction, of Roseville, California, in the amount of $4,199,640; and WHEREAS, staff recommends RMC Water and Environment, of Walnut Creek, perform construction administration services. This is a time -and -materials contract with a not -to -exceed maximum of $416, 993and WHEREAS, National Meter and Automation, Inc., of Santa Rosa, is the local supplier for Badger Meter, Inc., of Milwaukee, that was approved by City Council on August 4,2010,as the sole source provider of water meters to the Water Meter Program. Staff, along with RMC, has negotiated the necessary terms and requirements of the water meter assemblies' procurement and related field services. The total contract amount is $527,199and WHEREAS, staff recommends appropriation of $5, 690, 00from the Water Capital Fund to cover the cost of construction, construction administration services, water meter assemblies, Public Works Engineering staff, and contingency. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award the construction contract for Water Meter Program Phase 2 to the low bidder, Teichert Construction, of Roseville, California, in the amount of $4,199, 640;nd BE IT FURTHER RESOLVED that the Lodi City Council does hereby award the time - and -materials contract for construction administration services to RMC Water and Environment, of Walnut Creek, California, in an amount not to exceed $416,993; and BE IT FURTHER RESOLVED that the Lodi City Council does hereby award the contract for the water meter assemblies procurement and related field services to National Meter and Automation, Inc., of Santa Rosa, California, in the amount of $527,199; and BE IT FURTHER RESOLVED that the City Manager is hereby authorized to execute the agreements; and BE IT FURTHER RESOLVED that funds in the amount of $5,690,000 be appropriated from the Water Capital Fund for this project. Dated: March 7, 2012 ------------------------------------------------------------------------ ------------------------------------------------------------------------ I hereby certify that Resolution No. 2012-21 was passed and adopted by the City Council of the City of Lodi in a regular meeting held March 7, 2012, by the following vote: AYES: COUNCIL MEMBERS — Hansen, Johnson, Katzakian, and Mayor Mounce NOES: COUNCIL MEMBERS — Nakanishi ABSENT: COUNCIL MEMBERS— None ABSTAIN: COUNCIL MEMBERS— None 111*7 &�OIHL City Clerk 2012-21