HomeMy WebLinkAboutAgenda Report - May 5, 1999 E-07OF
G� <0
r> COUNCIL• •
C9 �P
FOR�
AGENDA TITLE: Ratify the 1999/2000 Annual Financial Plan for the San Joaquin County
Council of Governments
MEETING DATE: May 5, 1999
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution ratifying the
1999/2000 Annual Financial Plan (AFP) for the San Joaquin County
Council of Governments (COG).
BACKGROUND INFORMATION: Enclosed is a summary of COG's AFP for fiscal year 1999/2000.
The COG Board adopted the AFP on March 25, 1999. Pursuant to
COG's Joint Powers Agreement, the budget is to be ratified by the
City of Lodi following adoption by the COG Board.
FUNDING: Not applicable.
�'Req
Richard C. Prima, Ji"
Public Works Director
Prepared by Carlos Tobar, Transportation Manager
RCP/CT/1m
Attachments
cc: City Attorney
Steve Dial, Dir. of Adm./Chief Financial Officer, COG
APPROVED:
Dixon Flynn City Manager
COGANNFINPLN.DOC 04/28/99
San Joaquin County Council of Governments
�4 � � • � ,�>a � ��re. a� � wr.�^,�A A2. vw <.:.s n s, '° Ae � ,:x� � .a# ��x "�,Se�K` �- � 'Yye�_:_ 4
Member Agencies: Cities of Escalon, Lathrop, Lodi, Manteca, Ripon, Stockton, Tracy, County of San Joaquin
��'��1ana9'ers; _
Or..�
April 5, 1999
Mr. Dixon Flynn
City Of Lodi
P.O. Box 3006
Lodi, CA 95241-1910
Dear Mr. Flynn:
Enclosed is a summary of the San Joaquin Council of Governments' Annual
Financial Plan (AFP) for Fiscal Year 1999/2000. Pursuant to the COG's Joint
Powers Agreement, following adoption of the budget by our Board, it is to be
delivered to member agencies for ratification by each governing body. The Board
unanimously adopted the Plan on March 25, 1999. A copy of the adopting
resolution is enclosed.
Therefore, I request that you place the COG's Annual Financial Plan for Fiscal Year
1999/2000 on a forthcoming agenda prior to June 30, 1999 for your Council's
approval.
The Annual Financial Plan implements the FY 1999/2000 Unified Work Program
(UWP) also adopted by the COG Board on March 25, 1999. The UWP continues
COG's commitment to:
1. Maintaining Air Quality Conformity
2. Delivery of Measure K
3. Research and Data Center
4. Habitat Planning
5. Transportation Modeling
6. Regional Transportation Plan/Strategic Investment Planning
7. Congestion Management Planning
8. Local Assistance
9. Intergovernmental Coordination/Cooperation
.,Regional Transportation Planning Agency, Local Transportation Authority, Congestion Management. Agency, Airport Land Use Commission
6 South El Dorado St., Suite 400 • Stockton, California 95202 • (209) 468-3913 • FAX (209) 468-1084 • sjccog@co.san joaquin.ca.us
Mr. Dixon Flynn
April 5, 1999
Page 2
The enclosed summary identifies revenues and expenditures anticipated for the year
including both operating and pass-through revenues and expenditures. Pass-
through are funds over which COG has fiduciary responsibility such as
Transportation Development Act, TEA -21 and the majority of Measure K funds. The
summary compares the FY 1999/2000 budget with the FY 1998/99 budget, both
originally adopted and amended.
The following assumptions are incorporated in the budget:
1. Work will not begin and expenses will not be incurred unless anticipated
revenues sources that are attained i.e., Air District grants, Freeway Service
Patrol, etc.
2. We anticipate being fully staffed for the entire fiscal year, therefore the
Salaries and Benefits cost category is fully funded.
3. Five percent has been included in Salaries and Benefits for merit based
increases to be determined by the Executive Director. No cost of living
adjustment will be considered this fiscal year.
LINE ITEMS WITH SIGNIFICANT CHANGE
The Salaries and Benefits group increases 12.6% reflecting previously approved full
staffing for the entire year and 5% for merit based salary adjustments.
Services and Supplies increases 5.9%. The majority of this increase is in the Rents
Structures and Grounds which has been increased to reflect possible future office
space acquisition.
Professional Services decreases 14.0% due to the partial completion of the ITS
Strategic Plan.
Fixed Assets are increased from $25,100 to $70,000 for potential leasehold
improvements.
The Annual Financial Plan is the instrument through which revenues are brought
into COG, programmed and then spent. The proposed budget is 3.8% more than
the currently adopted amended budget. Sufficient revenue sources exist as
presented in the report to support the budget.
Mr. Dixon Flynn
April 5, 1999
Page 3
COG staff would be pleased to appear before your policymakers to answer any
questions they might have regarding this matter.
Please let me know when this will be appearing before the Board. If you have any
questions regarding this matter, don't hesitate to contact me at 468-3913.
Thank you for your assistance.
Sincerely,
JULIA E. GREENS
Executive Director
San Joaquin Council of Governments
ANNUAL FINANCIAL PLAN
Fiscal Year 99/00
Adopted March 25, 1999
CHAIR
Gary Podesto. Mayor, City of Stockton
VICE -CHAIR
John Harris, Mayor Pro Tem, City of Manteca
BOARD OF DIRECTORS
Councilmember Phillip Pennino
Councilmember Richard Nickerson, MD
Councilmember Gloryanna Rhodes
Mayor Dan Bilbrey
Supervisor Robert Cabral
Supervisor Jack Sieglock
Councilmember David Ennis
Councilmember Curt Pernice
City of Lodi
City of Stockton
City of Lathrop
City of Tracy
County of San Joaquin
County of San Joaquin
City of Escalon
City of Ripon
EX OFFICIO DIRECTORS
Mark Leja Caltrans District 10
Martha Jean Shaver San Joaquin Regional
Transit District
Ron Coale Port of Stockton
SUBMITTED BY:
Julia E. Greene
Executive Director
Steve Dial
Director of Administration/
Chief Financial Officer
San Joaquin County Council of Governments
ANNUAL FINANCIAL PLAN
Fiscal Year 1999/2000
REVENUES
FY 97/98
Actual
FY 98/99
Adopted 4/23198
FY 98199
Amend#1(2111199)
FY 99/00
Adopted (3/25199)
Federal Grants
$886,229
$1,072,300
$1,022,300
$1,055,518
State Grants
$526,086
$221,300
$895,300
$731,700
Local
$634,738
$1,049,900
$996,900
$1,237,900
Interest
$26,910
$0
$0
$0
Other
$275,368
$50,000
$50,000
$50,000
COG OPERATING REVENUES
$2,349;331
$2,393,500
52,965;500
$3,0725;118
Federal Pass -Through
$6,325,562
$6,539,000
$6,539,000
$7,100,000
State Pass -Through
$894,289
$970,673
$970,673
$981,000
Local Pass -Through
$33,986,434
$38,340,000
$38,340,000
$41,578,440
Sales Tax Revenue Bonds
$65,000,000
$65,000,000
$65,000,000
$65,000,000
TOTAL COG REVENUE
$108,555,616
$113,243,173
$113,815,173
$117,734,558
EXPENDITURES
Salaries & Benefits
$1,223,953
$1,357,766
$1,464,183
$1,642,814
Services & Supplies
$357,414
$420,780
$429,930
$455,230
Office Expense
$81,784
$100,700
$106,900
$106,900
Communications
$35,456
$35,000
$21,200
$20,300
Memberships
$14,786
$18,720
$19,370
$21,370
Maintenance - Equipment
$32,815
$25,000
$18,000
$18,000
Rents & Leases - Equipment
$63,091
$76,700
$94,300
$89,500
Transportation,Travel & Training
$21,861
$49,100
$49,100
$49,100
Motor Pool-R/S Incentive -Bus Passes
$3,150
$2,500
$2,500
$2,500
Allocated Service Cost
$3,916
$4,100
$4,100
$4,100
Publications & Legal Notices
$1,391
$2,000
$4,500
$4,500
Insurance
$20,424
$22,000
$25,000
$25,000
Building Maintenance
$1,090
$3,500
• $3,500
$3,500
Rents - Structures & Grounds
$73,827
$76,460
$76,460
$105,460
Education Reimbursement
$3,823
$5,000
$5,000
$5,000
Professional Services
$747,196
$531,300
$1,046,287
$903,476
Fixed Assets
$20,768
$20,000
$25,100
$70,000
Unallocated/Reserve $0 $63,654 $0 $3,598
COG OPERATING EXPENDITURES $2,349,331',.- $2,3931500.: 5085,500; 53075,118
Pass -Through $106,206,285 $110,844,421 $110,844,421 $114,659,440
TOTAL COG EXPENDITURES $108,555,616 $113,243,173 $113,815,173 $117,734,558
Excess (Deficit) Revenues $0 $0 $0 ($0)
Over Expenditures (Operating)
RESOLUTION
SAN JOAQUIN COUNTY COUNCIL OF GOVERNMENTS
•
R-99-53
RESOLUTION APPROVING THE ADOPTION OF THE 1999-2000
UNIFIED WORK PROGRAM AND THE FY 1999-2000 ANNUAL FINANCIAL PLAN
FOR THE SAN JOAQUIN COUNCIL OF GOVERNMENTS
WHEREAS, annually the San Joaquin Council of Governments acting as the Metropolitan Planning Agency, and
the Regional Transportation Planning Agency for San Joaquin County adopts a Unified Work Program, and
WHEREAS, that Unified Work Program identifies the funding sources that the agency will utilize in the coming
year, and the work tasks and products that the agency will produce, and
WHEREAS, this Unified Work Program must be submitted to the required funding agencies for their review and
approval, and
WHEREAS, the Council of Governments must assure that the planning tasks identified are in compliance with all
State and Federal laws and regulations, and are coordinated with all effected agencies, and communities on a
regional basis, and
WHEREAS, it is also essential that the COG prepare a budget, constrained by the resources available, to carry out
and fund the work scheduled in the fiscal year.
NOW THEREFORE BE IT RESOLVED that the San Joaquin Council of Governments adopts the attached 1999-
2000 Unified Work Program and self -certifies the following:
The San Joaquin Council of Governments hereby certifies its planning process to be in accordance with all
applicable requirements of the Federal government, as follows:
1. Section 134 of Title 23, U.S.C. Section 8 of the Federal Transit Act (49 U. S. C. app. 1607) and 23
23 CFR 450 Subpart C;
2. Sections 174 and 1760 and (d) of the Clean Air Act (42 U.S.C. 7504, 7506 C and (d));
3. Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under
23 U.S.C. 324 and 29 U.S.0 794;
4. Section 1003(b) of the Intermodal Surface Transportation Efficiency Act to 1991 (Pub. L. 102-
240) regarding the involvement of disadvantaged business enterprises in the FHWA and the FTA
funded planning process (Sec. 105(f), Pub. L. 97-424, 96 Stat. 2100, 49 CFR Part 23); and
5. The provisions of the Americans with Disabilities Act of 1990 (Pub. L. 101-336, 104 Stat. 327,
as amended) and USDOT regulations "Transportation for Individuals With Disabilities" (49 CFR
Parts 27, 37, and 38).
3
Resolution #R-99-53
Page Two
BE IT FURTHER RESOLVED that the San Joaquin County Council of Governments does hereby approve the
fiscal year 1999-2000 budget and forward such to its member governments for their review and ratification.
PASSED AND ADOPTED this 25' day of March, 1999 by the following vote of the San Joaquin Council of
Governments, to wit:
AYES: Supervisor Cabral, San Joaquin County; Vice Chair
Harris, Manteca; Councilperson Nickerson, Stockton;
Councilperson Pennino, Lodi; Councilperson Rhodes,
Lathrop; Supervisor Sieglock, San Joaquin County;
Chairman Mayor Podesto, Stockton.
NOES: None
ABSENT: Councilperson Pernice, Ripon; Counc'erson Ennis,
Escalon; Councilperso Bilbrey, T acy.
i
MASDIAL\99-000W P\9900U WPF.RES
RESOLUTION NO. 99-71
A RESOLUTION OF THE LODI CITY COUNCIL
RATIFYING THE SAN JOAQUIN COUNTY COUNCIL OF
GOVERNMENTS (COG) 1999/2000 ANNUAL FINANCIAL
PLAN
WHEREAS, the San Joaquin County Council of Governments (COG) has
approved their Fiscal Year 1999-2000 Budget by adopting Resolution No. R-99-53 as
shown on the attached marked Exhibit A; and
WHEREAS, the San Joaquin County Council of Governments (COG) is required to
forward such Resolution to its member Governments for their review and ratification.
NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council hereby ratifies
the 1999-2000 Annual Financial Plan for the San Joaquin County Council of Governments
(COG).
Dated: May 5, 1999
------------------
------------------
I hereby certify that Resolution No. 99-71 was passed and adopted by the Lodi
City Council in a regular meeting held May 5, 1999 by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Mann, Nakanishi, Pennino and
Land (Mayor)
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
ALICE M. AMCH�E
City Clerk
99-71
EXHIBIT A
RESOLUTION
SAN JOAQUIN COUNTY COUNCIL OF GOVERNMENTS
11 *10 [C
R-99-53
RESOLUTION APPROVING THE ADOPTION OF THE 1999-2000
UNIFIED WORK PROGRAM AND THE FY 1999-2000 ANNUAL FINANCIAL PLAN
FOR THE SAN JOAQUIN COUNCIL OF GOVERNMENTS
WHEREAS, annually the San Joaquin Council of Govemments acting as the Metropolitan Planning Agency, and
the Regional Transportation Planning Agency for San Joaquin County adopts a Unified Work Program, and
WTIEREAS, that Unified Work Program identifies the funding sources that the agency will utilize in the coming
year, and the work tasks and products that the agency will produce, and
WHEREAS, this Unified Work Program must be submitted to the required funding agencies for their review and
approval, and
tiVHEREAS, the Council of Governments must assure that the planning tasks identified are in compliance with all
State and Federal laws and regulations, and are coordinated with all effected agencies, and communities on a
regional basis, and
WHEREAS, it is also essential that the COG prepare a budget, constrained by the resources available, to carry out
and fund the work scheduled in the fiscal year.
NbW THEREFORE BE IT RESOLVED that the San Joaquin Council of Governments adopts the attached 1999-
2000 Unified Work Program and self -certifies the following:
The San Joaquin Council of Governments hereby certifies its planning process to be in accordance with all
applicable requirements of the Federal government, as follows:
I. Section 134 of Title 23, U.S.C. Section 3 of the Federal Transit Act (49 U.S.C. app. 1607) and 23
23 CFR 450 Subpart C;
2. Sections 174 and 176D and (d) of the Clean Air Act (42 U.S.C. 7504, 7506 (0 and (d));
3. Title VI of the Civil Rights Act of 1964 and the Title VI assurance executed by each State under
23 U.S.C. 324 and 29 U.S.0 79.1;
4. Section 1003(b) of the Intermodal surface Transportation Efficiency Act to 1991 (Pub. L. 102-
240) regarding the involvement of disadvantaged business enterprises in the FHWA and the FTA
funded planning process (Sec. 105(0, Pub. L. 9742.1, 96 Stat. 2100, 49 CFR Part 23); and
5. The provisions of the Americans with Disabilities Act of 1990 (Pub. L. 101-336, 104 Stat. 327,
as amended) and USDOT regulations `Transportation for Individuals With Disabilities" (49 CFR
Parts 27, 37, and 33).
EEXCHIBIT
Resolution RR -99-53
Page Two
BE IT FURTHER RESOLVED that the San Joaquin County Council of Governments does hereby approve the
fiscal year 1999-2000 budget and forward such to its member governments for their review and ratification.
PASSED AND ADOPTED this 25`" day of March, 1999 by the following vote of the San Joaquin Council of
Governments, to wit:
AYES: Supervisor Cabral, San Joaquin County; Vice Chair
Harris, Manteca; Councilperson Nickerson, Stockton;
Councilperson Pennino, Lodi; Councilperson Rhodes,
Lathrop; Supervisor Sieglock, San Joaquin County;
Chairman Mayor Podesto, Stockton.
NOES: None
ABSENT: Councilperson Pernice, Ripon; Counc Derson Ennis,
Escalon; Councilpersop(Bilbrey, T acy.
0
>f 'SCL�L.'3'�-CCO Wp�g9CCL'L?F.ZS
San Joaquin County Council of Governments
AtNiPLAN AL FINA\CIAL PLA�
Fiscal Year 1999/2000
FY 97/9S FY 98199 FY 98199
REVENLActual Adopted 4123198 Amend'1(2111f99)
EXHIBIT +
FY 99/00
Adopted (3125199)
Federal Grants
$886,229
51,072,300
51,022,300
51,055,518
State Grants
S526,0866
$221,300
$895,300
$731,700
Local
5634,738
$1,049,900
5996,900
$1,237,900
Interest
S26,910
50
SO
50
Other
$275,368
$50,000
550,000
$50,000
COG OPERATMG REVENUES
$2,349,331
$2,393,500
$2,965,500
$3,075,118
Federal Pus -Through
$6.325.562
$6,539,000
56,539,000
57,100,000
State Pass -Through
5894,289
5970,673
$970.673
5981,000
Local Pass -Through
533,986,434
538,340,000
538,340,000
$41,578,440
Sala Tax Revenue Bonds
$65,000,000
565,000,000
565,000,000
$65,000,000
TOTAL COG REVENUE
5103,555,616
$113,243,173
$113,813,173
$117,734,558
EXPENDITURES
S76,460
5105,460
Education Reimbursement
$3,823
Salaries & Benefits
$1,223,953
51,357,766
51,464,183
51,632,814
Services & Supplies
$357,414
5420,780
5429,930
5455,230
Office Expense
$81,784
$100,700
5106,900
5106,900
Communications
$354456
$35,000
$21,200
$20,300
Memberships
$14,7866
516,720
519,370
521,370
Maintenance - Equipment
$32,815
$25,000
$18,000
518,000
Rena & Leases - Equipment
$63,091
576.700
$94,300
$89,500
Tratupotntion,Travel &Training
S21 561
$49,100
549,100
549,100
Motor Pool-R/S Incendve-Bus Passes
53,150
52,500
52,500
$2,500
Allocated Service Cost
53,916
54,100
$4,100
54,100
Publications & Legal Notices
S1,391
52,000
54,500
54,500
Insurance
$20,424
522,000
$25,000
525,000
Building Maintenance
51,090
53,500
•S3,500
$3,500
Rena - Structures & Grounds
573,827
576,460
S76,460
5105,460
Education Reimbursement
$3,823
$5,000
$5,000
$5.000.
Professional Services
5747,196
S531,300
51,046,287
$903,476
Fixed Assets
$20,758
$20,000
$25,100
$70,000
Unallocated/Reserve
SO
$63,65;
SO
$3,598
COG OPER.AM. G EXPENDMURES
52,349,331
52593,500
$2,965,500
53,075,118
Pass -Through
Si06,206 285
5110,844,421
$110,844,421
5114,659,440
TOTAL COG EXPENDITURES
$108,555,615
5113,243,173
$113,815,173
5117,734,558
Excess (Deficit) Revenues so SO SO (SO)
Over Expenditures (Operating)
CITY COUNCIL
KEITH LAND, Mayor
STEPHEN J. MANN
Mayor Pro Tempore
SUSAN HITCHCOCK
ALAN S. NAKANISHI
PHILLIP A. PENNINO
CITY OF NODI
CITY HALL, 22"1 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209) 333-6706
FAX (209) 333-6710
April 29, 1999
Mr. Steve Dial
Director of Administration/Chief Financial Officer
San Joaquin County Council of Governments
6 South EI Dorado Street, Suite 400
Stockton, CA 95202
H. DIXON FLYNN
City Manager
ALICE M. REIMCHE
City Clerk
RANDALL A. HAYS
City Attorney
SUBJECT: Ratify the 1999/2000 Annual Financial Plan for the San Joaquin County
Council of Governments
Enclosed is a copy of background information on an item on the City Council
agenda of Wednesday, May 5, 1999. The meeting will be held at 7 p.m. in the
City Council Chamber, Carnegie Forum, 305 West Pine Street.
This item is on the consent calendar and is usually not discussed unless a
Council Member requests discussion. The public is given an opportunity to address
items on the consent calendar at the appropriate time.
If you wish to write to the City Council, please address your letter to City Council,
City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the
mail. Or, you may hand -deliver the letter to City Hall, 221 West Pine Street.
If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's
card (available at the Carnegie Forum immediately prior to the start of the meeting) and
give it to the City Clerk. If you have any questions about communicating with the
Council, please contact Alice Reimche, City Clerk, at 333-6702.
If you have any questions about the item itself, please call Carlos Tobar at 333-6800,
ext. 678.
lajo4a)
Richard C. Prima, Jr.
Public Works Director
RCP/Im
Enclosure
cc: City Clerk
NCOGANNFINPLN.DOC