AGENDA TITLE: Award Contract for Lodi Lake Park Storage Building, 1101 West Turner Road ($55,380)
MEETING DATE: April 21, 1999
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the contract
for the above project to GTS Construction, of Galt, in the amount of
$55,376 and appropriate funds in accordance with the recommendation
shown below
BACKGROUND INFORMATION: This project will add a much needed storage facility to replace the
present deteriorating barn. The new storage facility will
accommodate scooters, small tools, chemicals, a workbench, and
other materials.
Plans and specifications for this project were approved on August 19, 1998. The City received the
following eight bids for this project:
Bidder
Location
Bid
Engineer's Estimate
$64,000
GTS Construction
Galt
$55,376
Coyne Construction
Lodi
$56,760
Casity Construction
Galt
$61,357
Hetzler Construction Co.
Lodi
$63,950
Diede Construction, Inc.
Woodbridge
$70,074
TMW & Associates, Inc.
Stockton
$71,977
Leroy Griffith Const., Inc.
Lathrop
$74,500
Meehleis Modular Buildings, Inc.
Lodi
$80,840
FUNDING: Requested Appropriation:
Project Estimate:
Bid Opening Date:
Funding Available
1998199 Parks Capital Improvement Project Fund
$64,000
$64,000
April 1, 1999
Finance Director
UeL d4ew
Richard C. Prima, Jr.
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
RCP/WKFIIm
Attachment
cc: City Attorney
Purchasing Officer
Parks Superintendent
APPROVED:
H. Dixon Flynn -- City Manager
CAWARD.DOC 04/06/99
RESOLUTION NO. 99-61
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
THE CONTRACT FOR LODI LAKE PARK STORAGE
BUILDING, 1101 WEST TURNER ROAD, AND
APPROPRIATING FUNDS TO COVER THE PROJECT
--------------------------------------------------------------------
--------------------------------------------------------------------
WHEREAS, in answer to notice duly published in accordance with law and the
order of this City Council, sealed bids were received and publicly opened on April 1, 1999,
-at 11:00 a.m. for the Lodi Lake Park Storage Building, 1101 West Turner Road, described
in the specifications therefore approved by the City Council on August 18, 1998; and
WHEREAS, said bids have been compared, checked, and tabulated and a report
thereof filed with the City Manager as follows:
Bidder Location Bids
Engineer's Estimate $ 64,000.00
GTS Construction Galt $ 55,376.00
Coyne Construction Lodi $ 56,760.00
Casity Construction Galt $ 61,357.00
Hetzler Construction Co. Lodi $ 63,950.00
Diede Construction, Inc. Woodbridge $ 70,074.00
TMW & Associates Stockton $ 71,977.00
Leroy Griffith Construction, Inc. Lathrop $ 74,500.00
Meehleis Modular Buildings, Inc. Lodi $ 80,840.00
WHEREAS, the City Manager recommends award of the bid for the Lodi Lake Park
Storage Building, 1101 West Turner Road be made to the low bidder, GTS Construction of
Galt, CA.
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of
the bid for the Lodi Lake Park Storage Building, 1101 West Turner Road, be and the same
is hereby awarded to GTS Construction of Galt, CA, the low bidder, in the amount of
$55,376.00; and
BE IT FURTHER RESOLVED that $64,000.00 be appropriated from the 1998/99
Parks Capital Improvement Project Fund to cover this project.
Dated: April 21, 1999
I hereby certify that Resolution No. 99-61 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held April 21, 1999, by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Mann, Nakanishi, Pennino and
Land (Mayor)
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
A�)h -44xz�
ALICE M. REIMCHE
City Clerk
99-61