HomeMy WebLinkAboutResolutions - No. 2010-190RESOLUTION NO. 2010-190
A RESOLUTION OF THE LODI CITY COUNCIL
AUTHORIZING APPROPRIATION OF FUNDS
FOR CONTRACT CHANGE ORDERS FOR
DEBENEDETTI PARK (G -BASIN) STORM DRAIN
IMPROVEMENTS PROJECT
WHEREAS, the DeBenedetti Park (G -Basin) Storm Drain Improvements Project
was awarded to Teichert Construction, of Stockton, on October 7, 2009; and
WHEREAS, this project is the first step in multiple storm drainage and parks
projects at DeBenedetti Park. It is necessary for this project work to be completed prior
to the other projects being started, which required the work to continue through last
winter's above -normal rainfall; and
WHEREAS, Change Order No. 1 is for costs related to the construction of a
coffer dam in G -Basin ($24,313.54); and
WHEREAS, Change Order No. 2 includes lowering the elevation of the 72 -inch
line, removal of the temporary coffer dam, purchase of RCP pipe, increase in material
escalation costs for metal rebar, and other work related to the control of storm water
during the project ($119,551.19); and
WHEREAS, staff recommends appropriating $150,000 from the Storm Drain
Impact Fee Fund to cover the cost of the change orders.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize appropriation of $150,000 from the Storm Drain Impact Fee Fund for this
project.
Dated: November 17, 2010
I hereby certify that Resolution No. 2010-190 was passed and adopted by the
City Council of the City of Lodi in a regular meeting held November 17, 2010, by the
following vote:
AYES: COUNCIL MEMBERS — Hansen, Hitchcock, Johnson, Mounce, and
Mayor Katzakian
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS— None
ABSTAIN: COUNCIL MEMBERS— None
HL
City Clerk
2010-190