HomeMy WebLinkAboutAgenda Report - November 20, 1996 (71)CITY OF LODI COUNCIL COMMUNICATION •5. 0' AGENDA TITLE: Contract Award for Police Department Carnegie Basement Remodel ($45,320) MEETING DATE: November 20, 1996 PREPARED BY: Public Works Director RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the contract for the above project to GTS Construction, of Galt, in the amount of $45,320. Funds for this project will be coming from Police Development Impact Mitigation Fees and have already been appropriated. BACKGROUND INFORMATION: This project consists of moving and installing new walls and doors to create several new rooms, and modification of finishes, mechanical and electrical systems to accommodate use of this area by the Police Department's Investigations Division. Plans and specifications for this project were approved on October 16, 1996. The City received the following four bids for this project: Bidder Location Engineer's Estimate GTS Construction Galt Wall Construction Modesto Bobo Construction, Inc. Elk Grove McFadden Construction Stockton FUNDING: Project Estimate: $47,600 Bid Opening Date: November 6, 1996 Prepared by Dennis J. Callahan JLR/DC/lm Attachment 15'7)it.e J ck L. Ronsko P blic Works Director Building and Equipment Maintenance Superintendent cc: City Attorney Purchasing Officer Police Chief Police Captain Adams Building and Equipment Maintenance Superintendent Construction Manager Bid $39,100 $45,320 $46,000 $67,340 $69,950 APPROVED: H. Di,(.n Flynn -- ity Manager CAWARD.DCC 11/12196 RESOLUTION NO. 96-170 A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE BID FOR POLICE DEPARTMENT CARNEGIE BASEMENT REMODEL WHEREAS, in answer to notice duly published in accordance with law and the order of this City Council sealed bids were received and publicly opened on November 6, 1996 at 11:00 a.m. for the Police Department Carnegie Basement Remodel, described in the specifications therefore approved by the City Council on October 16, 1996; and WHEREAS, said bids have been compared, checked, and tabulated and a report thereof filed with the City Manager as follows: Bidder Location Bid Engineers Estimate $ 39,100 GTS Construction Galt $ 45,320 Wall Construction Modesto $ 46,000 Bobo Construction, Inc. Elk Grove $ 67,340 McFadden Construction Stockton $ 69,950 WHEREAS, the City Manager recommends award of the bid for Police Department Carnegie Basement Remodel, be made to the low bidder, GTS Construction of Galt, CA and NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of the bid for Police Department Carnegie Basement Remodel, be and the same is hereby awarded to GTS Construction of Galt, CA, the low bidder, in the amount of $45,320.00. Dated: November 20, 1996 -------------------------------------------------------------------- -------------------------------------------------------------------- I hereby certify that Resolution No. 96-170 was passed and adopted by the City Council of the City of Lodi in a regular meeting held November 20, 1996 by the following vote: AYES: COUNCIL MEMBERS - Davenport, Mann, Pennino, Sieglock and Warner (Mayor) NOES: COUNCIL MEMBERS - None ABSENT: COUNCIL MEMBERS - None ABSTAIN: COUNCIL MEMBERS - None til , NIFE PERRIN y Clerk 96-170