AGENDA TITLE: Contract Award for Police Department Carnegie Basement Remodel ($45,320)
MEETING DATE: November 20, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the contract
for the above project to GTS Construction, of Galt, in the amount of
$45,320. Funds for this project will be coming from Police Development
Impact Mitigation Fees and have already been appropriated.
BACKGROUND INFORMATION: This project consists of moving and installing new walls and doors
to create several new rooms, and modification of finishes,
mechanical and electrical systems to accommodate use of this
area by the Police Department's Investigations Division.
Plans and specifications for this project were approved on October 16, 1996. The City received the
following four bids for this project:
Bidder
Location
Engineer's Estimate
GTS Construction
Galt
Wall Construction
Modesto
Bobo Construction, Inc.
Elk Grove
McFadden Construction
Stockton
FUNDING: Project Estimate:
$47,600
Bid Opening Date:
November 6, 1996
Prepared by Dennis J. Callahan
JLR/DC/lm
Attachment
15'7)it.e
J ck L. Ronsko
P blic Works Director
Building and Equipment Maintenance Superintendent
cc: City Attorney
Purchasing Officer
Police Chief
Police Captain Adams
Building and Equipment Maintenance Superintendent
Construction Manager
Bid
$39,100
$45,320
$46,000
$67,340
$69,950
APPROVED:
H. Di,(.n Flynn -- ity Manager
CAWARD.DCC 11/12196
RESOLUTION NO. 96-170
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE BID FOR POLICE DEPARTMENT
CARNEGIE BASEMENT REMODEL
WHEREAS, in answer to notice duly published in accordance with law and the
order of this City Council sealed bids were received and publicly opened on November 6,
1996 at 11:00 a.m. for the Police Department Carnegie Basement Remodel, described in
the specifications therefore approved by the City Council on October 16, 1996; and
WHEREAS, said bids have been compared, checked, and tabulated and a report
thereof filed with the City Manager as follows:
Bidder Location Bid
Engineers Estimate
$ 39,100
GTS Construction
Galt
$ 45,320
Wall Construction
Modesto
$ 46,000
Bobo Construction, Inc.
Elk Grove
$ 67,340
McFadden Construction
Stockton
$ 69,950
WHEREAS, the City Manager recommends award of the bid for Police Department
Carnegie Basement Remodel, be made to the low bidder, GTS Construction of Galt, CA
and
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of
the bid for Police Department Carnegie Basement Remodel, be and the same is hereby
awarded to GTS Construction of Galt, CA, the low bidder, in the amount of $45,320.00.
Dated: November 20, 1996
--------------------------------------------------------------------
--------------------------------------------------------------------
I hereby certify that Resolution No. 96-170 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held November 20, 1996 by the following
vote:
AYES: COUNCIL MEMBERS - Davenport, Mann, Pennino, Sieglock
and Warner (Mayor)
NOES: COUNCIL MEMBERS - None
ABSENT: COUNCIL MEMBERS - None
ABSTAIN: COUNCIL MEMBERS - None
til ,
NIFE PERRIN
y Clerk
96-170