AGENDA TITLE: Acceptance of Improvements Under Hutchins Street Square Community Center
Southeast Parking Lot Expansion Contract
MEETING DATE: November20, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Hutchins
Street Square Community Center Southeast Parking Lot Expansion"
contract and direct the City Engineer to file a Notice of Completion with
the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to A. M. Stephens Construction Company
of Lodi on August 7, 1996 in the amount of $73,500.00. The contract
has been completed in substantial conformance with the plans and
specifications approved by the City Council. As part of the contract
work, A. M. Stephens will be maintaining the new turfing and sprinklers until December 1, 1996.
The contract completion date was October 1, 1996 and the actual completion date was October 1, 1996.
The final contract price was $78,979.07. The difference between the contract amount and the final
contract price is mainly due to the replacement of 38 lineal feet of wastewater main. This work had to be
done so a new storm drain line could be installed to the parking lot.
FUNDING: As determined at contract award.
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/Im
cc: Purchasing Officer
Community Center Director
APPROVED:
CACCPT.DOC
1
�• vuc
Jack L. Ronsko
Public Works Director
H. Dixon Flynn City ktanager
11/13/96