HomeMy WebLinkAboutAgenda Report - August 7, 1996 (87)AGENDA TITLE: Acceptance of Improvements Under White Slough Water Pollution Control Facility
Chain Link Fence Contract
MEETING DATE: August 7, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "White Slough
Water Pollution Control Facility Chain Link Fence" contract and direct the
City Engineer to file a Notice of Completion with the County Recorder's
office.
BACKGROUND INFORMATION: The project was awarded to Weaver's Woven Wire of Carmichael,
California, on February 7, 1996 in the amount of $39,904. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
The contract completion date was May 3, 1996 and the actual completion date was May 10, 1996. The
final contract price was $40,154. Two additional fence posts were installed by the Contractor and this
increased the contract by $250.
FUNDING: As determined at contract award. I"
Jac L. Ronsko
Pub 'c Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/lm
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED:
H. Dixon Flynn -- Ci Manager
CACCPT.DOC 07126/96