HomeMy WebLinkAboutAgenda Report - August 7, 1996 (72)AGENDA TITLE: Acceptance of Improvements Under Blakely Park Pool Balance Tank and Filtration
System Replacement Contract
MEETING DATE: August 7, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Blakely Park
Pool Balance Tank and Filtration System Replacement" contract
and direct the City Engineer to file a Notice of Completion with the
County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Western Waterfeatures, Inc., of
EI Dorado Hills, on February 21, 1996 in the amount of $43,187.
The contract has been completed in substantial conformance with
the plans and specifications approved by the City Council.
The contract completion date was May 29, 1996 and the actual completion date was May 14, 1996.
The final contract price was $41,487. The difference between the contract amount and the final
contract price is mainly due to the removal of the fencing portion of the contract from the scope of work.
FUNDING: As determined at contract award. %) 1
L. Ronsko
Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/lm
cc: Purchasing Officer
Parks Superintendent
APPROVED:
H. Dixon Flynn -- C Manager
CACCPT.DOC WPM%