AGENDA TITLE: Contract Award for Rock and Sand Material for Fiscal Year 1996/97 ($8,180)
MEETING DATE: June 19, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding all three
items of the contract for rock and sand material for fiscal year 1996/97 as
follows, and appropriate funds in accordance with the recommendation
shown below.
Item 1. 100 tons/aggregate base FTG Construction Lodi $ 970
Item 2. 300 tons/concrete sand FTG Construction Lodi 3,234
Item 3. 250 tons/crushed rock Granite Construction Stockton 3,972
BACKGROUND INFORMATION: This contract provides rock and sand materials for various street
maintenance projects carried on throughout the City during the fiscal
year.
Specifications for this project were approved on May 15, 1996. The City received two bids for the three
items for this project as shown on the attached bid tab.
FUNDING: Requested Appropriation:
Project Estimate:
Bid Opening Date:
Prepared by George Bradley, Street Superintendent
JLR/GMB/dsg
Attachments
cc: City Attorney
Purchasing Officer
Street Superintendent
Street Maintenance Fund $8,180
$7,650
May 30, 1996
Ronsko
Vorks Director
APPROVED:
7Z�H. Dixon lynn -- City Wanager
GISPECS\R0CKBSND\CCO2-D0C WIN
Bid Opening 5/30/96, 11:00 am
Price/Ton
Tax
Total Price/Ton
1996-97
ROCK AND SAND MATERIALS
Bid Results
Granite Construction
FTG Construction
Teichert Construction
Item No. 1
Item No. 2
Item No. 3
Item No. 1
Item No. 2
Item No. 3
Item No. 1
Item No. 2
Item No. 3
$ 10.75
$ 0.83
$ 11.50
$ 0.89
$ 14.75
$ 1.14
$ 9.00
$ 0.70
$ 10.00
$ 0.78
$ 15.25
$ 1.18
$ -
$ -
$ -
$ 11.58
$ 12.39$
15.89 1
$ 9.70
$ 10.78
$ 16.43
NO BID
I NO BID I
NO BID
$ 8,176.50 Total Cost based on Bid
1995-96:
Price per ton includes delivery.
Low Bid 1996-97
Tons
Unit Price
Contract Price
Item No. 1
100
$ 9.70
$ 970.00
Item No. 2
300
$ 10.78
$ 3,234.00
Item No. 3
250
$ 15.89
$ 3,972.50
$ 8,176.50 Total Cost based on Bid
1995-96:
Tons
Unit Price
Contract Price
Item 1
100
$ 10.70
$ 1,070.00
Item 2
300
$ 12.05
$ 3,615.00
Item 3
250
$ 11.78
$ 2,945.00
$ 7,630.00
Percent of change from previous year
Item 1/Ton -9%
Item 2/Ton -11%
Item 3/Ton 35%
5% Average 5% increase per ton
81DRST96ALS Page 1 6/5196
RESOLUTION NO. 96-75
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE BID FOR ROCK AND SAND MATERIAL FOR
FISCAL YEAR 1996/97
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council sealed bids were received and publicly opened on May 30, 1996 at 11:00 a.m. for
Rock and Sand Material for Fiscal Year 1996/97, described in the specifications therefore
approved by the City Council on May 15, 1996 and
WHEREAS, said bids have been compared, checked, and tabulated and a report thereof
filed with the City Manager as follows:
Item A. 100 Tons/aggregate base
Item B. 300 Tons/concrete sand
Item C. 250 Tons/crushed rock
••,
FTG Construction, Lodi $ 970
FTG Construction, Lodi $ 3,234
Granite Construction, Stockton $ 3,972
WHEREAS, the City Manager recommends awarding all three items of the contract
for Rock and Sand Material for Fiscal Year 1996/97 as shown above; and
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of all
three items of the contract for Rock and Sand Material for Fiscal Year 1996/97, be and the same is
hereby awarded as shown above, in the amount of $8,180; and
FURTHER RESOLVED, that the City Council hereby approves appropriating $8,180.00
from the Street Maintenance Fund for this project.
Dated: June 19, 1996
I hereby certify that Resolution No. 96-75 was passed and adopted by the City Council of
the City of Lodi in a regular meeting held June 19, 1996, by the following vote:
AYES: COUNCIL MEMBERS - Davenport, Mann, Pennino, Sieglock
and Warner (Mayor)
NOES: COUNCIL MEMBERS - None
ABSENT: COUNCIL MEMBERS - None
ABSTAIN: COUNCIL MEMBERS - None
J IFER. PERRIN
City Clerk
96-75