CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Letter to U.S. representatives regarding Altamont Express Commuter Rail Service
and Transit Center in Stockton.
MEETING DATE: Wednesday June 5, 1996
PREPARED BY: Kirk J. Evans, Assistant to the City Manager
RECOMMENDED ACTION: That City Council approve a letter to Senators Boxer and Feinstein and
Congressmen Pombo and Baker regarding Altamont Express Commuter
Rail Service and a Transit Center in Stockton.
BACKGROUND INFORMATION: Council member Phil Pennino is Chairman of the Council of
Governments. He has a comprehensive knowledge of these
projects. Revenues generated by Measure K , Proposition 116, and
projected passenger fares will finance roughly 75% (see
attachments) of the startup costs of the Altamont Express Commuter
Rail Service. The rest of the funding needed to get this project
rolling, $10 million, is being sought from federal sources through the support of representatives such as
Congressman Pombo.
It should be noted Altamont Express is distinct from High Speed Rail Service for the State of California.
Altamont Express Commuter Rail Service is expected to begin in 1997. It will provide service between
Stockton and San Jose. If circumstances prove favourable, this service will be extended north to Lodi.
The best estimate for High Speed Rail Service commencing is 2013. While it is preferred that it go
through the Altamont Pass to the Bay Area, whether it does or not has no bearing on Altamont Express
Commuter Rail Service.
The San Joaquin Council of Governments has asked all local jurisdictions to prepare a letter for our U.S.
representatives. The attached draft from the City of Lodi with Mayor Wamer's signature is submitted to
City Council for consideration.
FUNDING: N/A
Krk J. Evans
Assistant to the City Manager
APPROVED: /
H. Dixon Olynn -- City hfanager
CITY COUNCIL
DAVID P. WARNER, Mayor
PHILLIP A. PENNINO
Mayor Pro Tempore
RAY G. DAVENPORT
STEPHEN J. MANN
JACK A. SIEGLOCK
June 6, 1996
CITY OF LODI
CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006
LODI, CALIFORNIA 95241-1910
(209)333-6700
FAX (209) 333-6807
Congressman Richard Pombo
Congressman Bill Baker
Senator Barbara Boxer
Senator Diane Feinstein
Dear (Senator/Congressman):
H. DIXON FLYNN
City Manager
JENNIFER M. PERRIN
City Clerk
RANDALL A. HAYS
City Attorney
The San Joaquin County region is seeking federal funding assistance for two major transportation
improvements. The City of Lodi is asking for your assistance and effort in supporting these
requests.
The San Joaquin region has embarked on a very aggressive public transportation system. In the
near future this transportation package includes two significant projects:
• Altamont Express Commuter Rail Project
• San Joaquin Regional Transit District Transit Center
Commuter rail transportation is a major program for this region. Federal assistance is needed to
supplement local and state dollars in this effort. Local sales tax override revenues, passenger
fares and private contributions will total $18.78 million - financing 44% of the cost of this project.
Requested federal funding accounts for less than one quarter of the cost of this project.
The transit center is also an important project for the metropolitan center of Stockton. This region
is recommending funding of both projects totaling $15.5 million. However, as funds may not be
available for that total amount, our first priority is the Altamont Express Commuter Rail Project.
After the funding request for the Altamont Express Commuter Rail Project has been fulfilled, the
transit center in Stockton is endorsed for funding. We urge your support in funding these projects.
Thank you for your continued support in dealing with the future requirements of this region of
California.
Sincerely,
David P. Wamer
Mayor
05/24/96 C:\KJEW0RK\TRANSIT\ALTALET2.D0C
RAIL CORRIDOR SERVICE
PROJECT: Altamont Pass Rail Service Phase I 9b
PROJECT SPONSOR: Reginnal Rail Commission
PROJECT SCOPE:
Phase I is a two year demonstration passenger rail service over the Altamont Pass onl�the
Union Pacific tracks. Service is proposed from Stockton, through Lathrop/Manteca, Traicy.
Livermore, Pleasanton, Fremont, and Santa Clara to San Jose, and includes two commute hour
round trips per weekday.
Phase I involves both capital and operating and maintenance costs. Other project related costs
include Rail Negotiations, Advocacy, and Programming Planning and Management. The capital
costs include track improvements, passenger platforms, and the leaselpurchase of rolling
stock. Operating and maintenance costs for the Phase I Altamont Rail service includes
operator costs (transportation expenses, maintenance of way and structures, maintenance of
equipment, miscellaneous expenses) and administration and management (insurance, st0tion
maintenance, ticketing sales/collecting, Altamont Pass Passenger Rail administration sand
marketing).
This: project anticipates the need for five passenger platforms. One would be located to serve
passengers from the Tracy area, another would be located to benefit passengers from 66th
Lathrop and Mantecar and a third platform would be located in Stockton. Two additignai
platforms would be constructed outside of San Joaquin County: one in Livermore, the wither
in Pleasanton.
Schedule and cost information are from the Altamont Pass Passenger Rail Corridor Std
Phase II. Track improvement costs, as well as track access fees, are subject to negotiation
and may change.
The informartion assumes that the demonstration service will begin in January, 1997, with 4
daily train trips. Initiation of service by January, 1997 is dependent on timely completion of
capital improvements and negotiated agreements with other service beneficiaries on issues of
operating costs being shared, service oversight and management and track usage rights
Related Projects: Altarnont Service Enhancements provides capital and operating support to
passenger rail service in the Altamont Corridor beyond the Phase I service. Another related
praject titled Service Extensions provides support for planning activities related to;
1 } Coordinating the enhancements and extensions of Intercity rail service to benefitithe
residents of San .Joaquin County and the San .Joaquin Valley
2) Integrating Altamont Commuter service with the State's Intercity rail services;
3) Extending Altamont Commuter rail service to Sacramento, Modesto and San Franc sco.
_L�
RAIL CORRIDOR SERVICE
PROJECT COST ESTIMATES ($1995):
Track Improvements (Design, Preconstruction) ...... ......... $ 150,00-0
Track Improvements {Construction) ...................... 414,393,00()
Negotiations ......................................... $275.000
Operatians/Maintenance ............... .............. 58,480,000
RcIling Stock (Lease or Purchase) ....................... S14,7()0,00()
PtatforruslParking .................................... 31,807,040
Advocacy ........................................... $355.000
Planning, Project Management ............... ......... $1.904,000
Total Cost ............... —.— ....... ........... $42.664,000
EXPECTED REVENUE SOURCES ($1995):
Measure K for Capital .............................. $8,235,000
Measure K for Operation .................. ............ 05,710,000
Measure K for Advocacy ............................. $224,000
Measure K for Negotiations ............................... $275,000
Measure K fGr-Prennina & Program Managremen .............. $1,258,000
Total Measure K ................................... $15,702,000
Local:
Private Sector Contributions .............................. $42,000
Fares ........................................... $2,660,000
State:
Proposition 116 Altamont Commuter Rail (PUC 99644) ....... $12,000,000
Federal:
Congestion Mfgation & Air Quality ...................... $2,210,000
Pending Discretionary Funding Grant .... ............... 010.000.000
I I
L
Total Revenues
....... $42,664,000
Short -Fall $0
RAIL CORRIDOR SUIVICS
PROJECT SCHEDULE:
Start Date
Completion Dace
Track design, prelim. engineering:
Oct. 1995
June 1996
.i
Track improvements. construction:
Jul. 1996
:i
Oct. 1997
OperationsfMaintenence:
Oct. 1997
Sept. 1999"
Negotiations: Jul. 1996 Sept. 1999"
Rolling Stock (LeaseMurchase): Jul. 1996 June 1997
platforms: Feb. 1997 Oct. 1997
Advocacy. Jan. 1994 Sept. 1999•
These tasks are ongoing and continue into the Measure K Rail Corridor Service Project titled:
"Altamont Service Enhancements."
ISSUES:
• Cash flow projections assume that demo project will begin in FY 1997-98 (October
1997), and track improvements will be needed in year prior.
• Negotiations are currently underway between the Regional Rail Commission and Pe
Union Pacific and Southern Pacific railroads concerning the implementation of this
project. Actual costs. route alignment and operating schedules are all subject ta':
these negotiations.
-I
I
• The pending merger of the Union Pacific and Southern Pacific Railroads may have a
significant impact on this project. A final agreement between the Rail Commis#n
and the railroads for implementing this service may not be reached until after thei
Interstate Commerce Commission (IM takes action on the proposed merger. ICS
action may not occur until August, 1996. It is estimated that once an agreementis
reached with the railroad, operations can begin within 18 months.
• The "Altamont Pass Passenger Rail Corridor Study --Phase Il Report" suggests that
Alameda County contribute $3.2 million to this service. Alameda County has not
made a firm commitment of funds to support this project. Until such a comma _ fl-nt
is made, these funds are not shown. When the commitment is made, it will offset
funding commitments from San Joaquin Measure K funds.
Ifiervised 5treteoc Plan Charts - May 24, 19961
D -Z
SUS TRANSIT PROJECTS PROPOSED AMENDMENT TO STRATEGIC PLAN
PROJECT; Downtown Transit Center 49a
PROJECT SPONSOR! San Joaquin Regional Transit District
PROJECT SCOPE:
This project includes the design, construction, and related environmental requirements far; a
passenger transit center in downtown Stockton and pedestrian/transit friendly street
improvement along a major corridor of the Central Business Distract.
The project will consist of construction of a passenger waiting and bus staging area,
landscaping, sidewalk improvements and passenger amenities in downtown Stockton.
It is important to distinguish between the downtown transfer center functions and those of a
muitimodaltrall station. While the two may be compatible, rail corridor and local bus servile
routes may require two separate locations. For example, the SP Depot is about seven bloAs
east of the primary convergence of downtown SMART bus routes.
I •!
Related Project: Two transfer centers are proposed for the SMARTfClty of Stockton service
area. The Weberstown/Sherwood Mall transfer center would provide enhanced passenger
waiting areas and roadway improvements to improve bus circulation for the thirteen rouies
serving the shopping malls.
PROJECT COST ESTIMATES ($1995):
Planning & Project Management $200,000
Phase 1:
Planning Activities ans Site Selection $1215,000
Phase 2:
Environmental Review $115.000
Preliminary Engineering 0100,000
Phase 2:
Land Acquisition $1,600,000
Architectural, Engineering and Construction Contractor Services $4001000
Phase 4:
Construction $4.260,00
is
aUS TRANSIT PROJECTS PROPOSED AMENDMENT TO STRATEGIC PLAN I'
Total Cost $7.000,000
1=
EXPECTED REVENUE SOURCES 01995I:
Measure -K for Capital (see issues)
Mgasurr.K for Planning & Procurement (20%)
City of Stockton
Federal:
Section 9
Section 3
Tota! Revenues Xa~
ratal Cast
Surplus/lShortfailE
$1,100,004
$25,000
$275,000
$100,000
$5,500,000
$7,000,000
$7,000,000
$0
BUS TRANSIT PROJECTS PROPOSED AMENDMENT TO STRATEGIC PLAN
PRCMCT SCHEDULE:
Starr Date
CQ Im—ionDate
Phase 1:
Planning Activities and Site Selection
May 1996
Sep 1998
Phase 2--
:Environmental
EnvironmentalReview
Sep. 1996
Dec. 1996 I,
Preliminary Engineering
Jan. 1997
Mar. 1997 ! ;
Phase 3:
'
Land Acquisition
Feb. 1997
June 1997
AIE, Construction Contractor Services
Apr. 1997
July 1996
Phase 4:
Construction
Oct. 1997
July 1998
ISSUE:
e SMART has proposed to change the project scope to a Downtown Transit Center. That
proposal includes a request for increased Measure K allocation.
i'•