HomeMy WebLinkAboutResolutions - No. 2006-57WHEREAS, the Kettleman Lane (Route 12) Gap Closure Project was awarded
to Teichert Construction, of Stockton, on September 7, 2003, in the amount of
$2,060,827.00, and
WHEREAS, the contract has been completed in substantial conformance with
the plans and specifications approved by City Council; and
WHEREAS, the project consisted of improving Kettleman Lane
(State Highwa y 12) from Lower Sacramento Road to Ham Lane and from Stockton
Street to Cherokee Lane. The improvements included constructing a raised landscaped
median at both locations, widening the westbound direction of Kettleman Lane from
Lakeshore Drive to Tienda Drive, modifying the Tienda Drive and Kettleman Lane traffic
signal to accommodate westbound dual left turns, widening the WalMart driveway to
accommodate: the two proposed inbound lanes, installing street lights, modifying the
Ham Lane/Kettleman Lane and Cherokee Lane/Kettleman Lane traffic signals to
accommodate: eastbound dual left -turn lanes, and constructing a traffic signal
interconnect system; and
WHEREAS, due to contract change orders, which added work to the contract
and addressed field conditions that were different than what was shown in the plans and
specifications, additional funds are necessary, and
WHEREAS, at the July 25, 2003, Board meeting, San Joaquin Council of
,3overnments, (SJCOG) approved an amendment to program $2.629 million in Measure
K Flexible Congestion Relief funds for the Kettleman Lane Widening/Gap Closure
Project; and
WHEREAS, as part of the cooperative agreement with SJCOG, the City of Lodi
agreed to participate by paying for 4% of the project costs; therefore, staff recommends
appropriating $102,800 from Street impact fees to cover the City's portion of this project.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Lodi
does hereby accept the improvements under the contract for Kettleman Lane (Route 12)
Gap Closure Project from Lower Sacramento Road to Ham Lane and from Stockton
Street to Cherokee Lane and directs the City Engineer to file a Notice of Completion
with the County Recorder's office; and
E 1T FURTHER RESOLVFD that the City Council of the City of Lodi does
hereby appropriate additional funds in the amount of $102,8030 from the Street Impact
Fees for this project.
Dated: April 19, 20061
7�,e
SUSAN J. BLAC STON
City Clerk