HomeMy WebLinkAboutResolutions - No. 2005-205RESOLUTION NO. 2005-205
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on September 14, 2005, at
11:00 a.m., for Turner Road Underpass Pump Station Modifications, described in the
specifications approved by the City Council on August 3, 2005; and
WHEREAS, said bids have been compared, checked, and tabulated and a report thereof
filed with the City Manager as follows:
Engineer's Estimate
G faybo rn Construction
Diede Construction
TNT Industrial
WHEREAS, this project consists of installing a new access hatch for the storm drain
pump station that serves the Turner Road Underpass and replacing the aging pumps and
piping; and
WHEREAS, because the bids submitted were higher than the engineer's estimate, staff
recommends rejecting the bids and advertising this project in spring 2006 with revised
specifications to include any known cost saving measures.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council hereby rejects all
bids for the Turner Road Underpass Pump Station Modifications; and
BE IT FURTHER RESOLVED that the Lodi City Council hereby approves the
advertisement of this project in spring 2006 with revised specifications to include any cost
saving measures identified by staff or potential bidders.
Dated: October 5, 2005
I hereby certify that Resolution No. 2005-205 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held October 5, 2005, by the following vote:
SUSAN J, BLAC:t:CSTON
City Clerk