HomeMy WebLinkAboutResolutions - No. 4062RESOLUTION NO. 4062
AWARD - CONTRACT FOR 60/ 12 KV HENNING SUBSTATION
EQUIPMENT.
WHEREAS, in answer to notice duly published in accordance
with law and the order of this City Council, sealed bids were re-
ceived and publicly opened by the City Clerk of this City on April 29,
1975 at 11:00 a.m. for the contract for 60/ 12 KV Henning Substation
Equipment as described in the specifications therefor approved by
the City Council on March 5, 1975; and
WHEREAS, said bids have been compared, checked, and
tabulated and a report thereof filed with the City Manager as per
Exhibit "A" attached;
WHEREAS, the City Manager recommends that award be made
as follows:
Bidder Material Bid Price max Total Bid
Westinghouse Breakers $74, 5 11.00 $4, 470. 66 $78, 981. 66*
(Items 1, 2, 3)
Westinghouse Switchboard 37,804.00 2,268.24 40,072.24
(Item 4)
G. E. Supply Co. Structure 76,875. 00 4,612. 50 8 1,487. 50
(Items 5- 11)
Graybar Electric Console (Item 12) 7, 027. 00 42 1.62 7,448.62
*Estimated maximum escalation - $5, 655. 92
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Lodi that award of contract for 60/ 12 KV Henning Substation
Equipment be and the same is hereby made to Westinghouse Electric
Supply, G. E. Supply Company, and Graybar Electric as recommended
by the City Manager and for those amounts outlined above.
Dated: May 7, 1975
I hereby certify that Resolution No. 4062 was passed
and adopted by the City Council of the City of Lodi in
a regular meeting held May 7, 1975 by the following
vote:
Ayes:
Noes:
Absent:
Councilmen - Ehrhardt, Hughes, Katnich,
Pinkerton and Schaffer
Councilmen - None
Councilmen - None
4062
711
ALICE M. EI CHE
City Clerk
60/12 -KV SUBSTATION EQUIPMENT - UD -E75-1
Breakers (Items 1,2,3) Switchboard (Item 4) Structure (Items 5-11) Console (Item 12) . Total Including Tax
Supplier Basic Bid Escalation Basic Bid Escalation Basic Bid Escalation Basic Bid Escalation Basic Bid Escalation
S:estinghouse $74.511.00 $79.846.77 $58,503.00 $62,598.21 $84,676.00 Firm $ 8,555.00 $9,153.85 $239,820.00 $250,451.32 *1
S.' st Alt. Bid 7W 111 00 79 846 77 37 804 00 Firm 95 958 00 Firm 8,626.00 Firm 229,912.94 235,568.86
Graybar Elec. 85.174.00 86,874.00 48,172 00 Firm 82 59Z 00 Firm 7 OZ7.00 Firm 235,557.44 237,359.44
C' E Supply 87,626.00 Firm 51,000.00 Firm 76,875.00 Firm ZO $00 00 Fina 246,980.00 Firm
Valley Elec No Bird No Bird 88,932.48 Firm No Bid H.A. N.A.
McCraw -Edison 23,409.00* 24,673.09* No BA No BA No Bid N A N 0.
* Item 1 only - High Bid.
*'- Comments: Structure does not meet specifications