HomeMy WebLinkAboutAgenda Report - January 17, 1996 (34)AGENDA TITLE: Acceptance of Improvements Under Granular Activated Carbon Filter Systems for
Wells 4R, 22 and 23 Contract
MEETING DATE: January 17, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Granular Activated Carbon Filter Systems for Wells 4R, 22 and 23"
contract and direct the City Engineer to file a Notice of Completion with
the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Conco West, Inc. of Manteca, on
April 19, 1995, in the amount of $947,820. The contract has been
completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was October 20, 1995 and the actual completion date was
January 5, 1996. No liquidated damages were assessed on this project as all three filter systems were
in place by the October 20 deadline and the filter systems at Wells 22 and 23 were being used by the
City by the dates required in the specifications. Conco West was doing minor corrective work and
punch list items after the contract completion date.
The final contract price was $951,895. The difference between the contract amount and the final
contract price is mainly due to additional pipe work done at Well 4R and the deletion from the contract
of the installation of the activated carbon at Well 4R. The activated carbon at Well 4R will be installed
in the spring when the demand on the water system increases. The City has purchased the carbon
from the contractor and the supplier will be issued a purchase order to install the carbon. With Wells
16, 22 and 23 running this winter, there is plenty of water to meet the City's needs and, if the carbon at
Well 4R had been installed under this contract, we would have had to unnecessarily run Well 4R to
keep the carbon fresh and prevent bacteria from forming on the carbon.
FUNDING: As determined at contract award.
;f Jack L. Ronsko
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/Im
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED:
A. Dix n Flynn -- Ci Manager
CACC£PT.DOC 01/10/96
0 MEMORANDUM, City of Lodi, Public Works Department
To: City Manager
City Council
From: Public Works Director
Date: January 23, 1996
Subject: Acceptance of Improvements Under Granular Activated Carbon Filter Systems
for Wells 4R, 22 and 23 Contract
As directed by the City Council, this document is in response to the concerns raised by
Council Member Davenport at the last City Council Meeting. Council Member
Davenport's concerns are shown below, italicized, with staffs explanation following.
1. "Well 4R doesn't even have a pump on it as we speak. What's orally out
there at Well 4R, next to the Reid Substation, is an empty hole with no
pump with a No. 3 tub over the top of it. Well 4R has never been
tested. "
Well 4R is a fully developed and tested well and was used in 1994 and
was available last summer to meet the peak water demands. The City
rented a temporary pump, motor and electrical panel to use at Well 4R
until November of last year, at which time they were removed. The
permanent pump, motor and panel are scheduled to be installed this fall
With the water tank installation project. We will, however, again be
renting a temporary pump, motor and electrical panel to meet the 1996
summer water demands.
2. "There is some piping that has not been performed in the way of some
valves that have not been put in at none of the three sites. Part of the
contract has not been done."
All piping and valving under the contract has been installed by the
contractor, Conco West Inc. in addition, as discussed in the Council
Communication, additional piping has been installed per a contract
change order to give the City more flexibility where we discharge the
water from the filters.
There are additional valves we want installed on the filter systems at all
three sites, but these were not included in the contract. These additional
valves will allow the City to keep the carbon fresh, with water from the
City system, in the event either the pump or motor at the site is being
repaired. Should the pump and/or motor have to be pulled for
maintenance, the City would be able to flush the carbon with water from
the system. This work was not done under a change order due to the
long delivery time which would have further delayed the acceptance of
the project and the return of retention to the contractor. The City has
arranged for their installation this spring and will issue a purchase order
to Conco West Inc. for this work.
MCMRESP.DOC
City Manager
City Council
January 23, 1996
Page 2
3. "The carbon has not been put into the well at 4R. J am concemed about
the Public Works Director coming to us and telling the Council that we
need to immediately get these things done when in fact it's never been
tested nor used."
The granular activated carbon has not yet been installed and tested at
Well 4R for two reasons, both of which would cost the City additional
dollars:
1. Carbon installed in a filter has a limited life.
2. Once the carbon is installed, it must have water run through it on a
regular schedule to keep it fresh.
If the contractor had installed and tested the carbon at Well 4R, the City
would have spent additional money on the rental of a pump, motor and
electrical panel. The average life of the carbon in the vessels is two to
three years. By delaying the installation of the carbon until early
summer, the City is saving approximately six months on the life of the
carbon ($18,000) and on the installation of a temporary pump, motor and
electrical panel ($5,000). A fax from Northwestern Carbon is attached
indicating they will install the carbon in spring 1996 at a cost to the City
of $2,000. We withheld $2,000 from the contract with Conco West to
cover the carbon delivery and installation. We also withheld an
additional $500 because we also deleted the testing of the carbon from
their contract. The attached Contract Payment form for the final
payment shows the $2,500 is being deleted from the contract price.
The final testing of the Well 4R filtration system will take place in early
summer of 1995 when we again install a temporary pump, motor and
electrical panel. Under the contract guarantee, Section 4.10
GUARANTEE (copy attached), the work is guaranteed for 365 days from
acceptance. Since tests on the other two installations, Well 22 and
Well 23, passed without any problems, it was felt it was in the best
interest of the City to delay the installation of carbon, as explained in our
Council Communication on the contract acceptance (copy attached) and
thereby save the City over $23,000.
4. "The person that in fact got the contract would not have even got the
contract—they were not the lowest bidder --but for the fact that they
agreed to waive any penalties or any fees in order to get the job going
rapidly. And, I think that should have been disclosed of us."
Conco West was the low bidder on this contract without any agreement
on their part to waive any penalties or fees. Per the attached Council
Communication dated April 19, 1995, the City Council decided to award
the contract for this project with an accelerated schedule so that Wells
22 and 23 could be put on line in time to meet the peak summer water
MCMRESPDOC
City Manager
City Council
January 23, 1996
Page 3
demands in 1995. When looking at just the base bid for the project,
Pete Fuller Construction was the low bidder, but when either of the
accelerated schedules is included in the contract, Conco West's bid is
lower than that of Pete Fuller. This was clearly shown in the bid results
in the Council Communication submitted to the City Council for the
contract award made April 19, 1995. Conco West was awarded the bid
without any penalties or fees being waived.
5. "All I'm saying is that Mr. Ronsko, I believe, should disclose the tnfe facts
to us and not lead me in anyway for me to think that in fact all these tests
and everything has been done when in fact some things have not."
It was certainly not our intent to withhold any major facts related to the
acceptance of any project. The majority of the City's construction
projects are not constructed exactly as planned. That's why our Council
Communication for all acceptances includes the phrase:
'The contract has been completed in substantial conformance
with the plans and specification approved by the City Council."
However, if there is a major deviation, this would be shared with the
Council with an explanation of the change orders or modifications.
We attempted to do this on this project. The attached Council
Communication on this project acceptance went into some detail why the
activated carbon at Well 4R was not installed. We did assume the City
Council would know this work would be tested at a later date. If testing
was the real concern, this could have been confirmed by a phone call to
Public Works staff or me.
If you or the City Council has any questions concerning this response, please do not
hesitate to contact me.
ack L. Ronsko
lic orks Director
JLRIIm
attachments
cc: Lodi News Sentinel
Stockton Record
MCMRESP.DOC
i
12-,.0-&5 :12:3lpM : NORT Mi SM CARSON-*
W
�'
NORTHWESTERN
CARBON
FAX TRA.NSAUTTAL
ATTENTION: _ ttx_(aLvc-oJ
COMfPAWt�I era 4)mvOL-
209 238 2984# 1/ 2
FAXJ! Zai- 2319 - 2-79if DATE: 1-- - 272" #pAGF9 ;2. .
P i Y: I alt # �14 11
Regarding the final 90,000 lbs. of GAC for The City of Lodi, Well
Na. 4n;
Additional negotiations with the American GAC manufacturer have
resulted in remewed availability 4f the approved GAC to Kim at the
original pricing with the aandition that it be ordered for
immediate shipment and the invoice be paid in .7nn. 1996.
The order hao been placed And we expect the shipment to arrive At
the KWC facility in Red Bluff, CA early next month. Thore will be
no need for any adjustments or considerations from the City of Lodi
for this GAC.
in September, 1995 we Were asked to receive and hold this GAC for
a 1996 delivery and installation. We agreed to invoice Conco West
for 411 but a $2,000 del Ivory /instal.latton charge with The City
issuing a PO direct to NWC for delivery at heir convenience in
atirly 096. OUr invoice to Conoo Weet (0033351 dated 9-7-95)
reflects this arrangement and it should be in everyone's interest
to Continue or this program. For clarification, NWC is expecting
paymeAt,for all but the final $2,000 in January.
Please advise The City of Lodi of this development and lot me know
if they have any questions. TAely, of course, are welcome to visit
our plant an inspect the shipment when it arrives.
Arid, we are looking for the final "punch list's of site dstuil
requirements and are ready to complete this project ASAP.
p=hK 190 • Fled *A, CJtMM • Bus. pie) Sgt -2884 • Fax (0141 M-0544 • MM M -2M
R-etx Gld5270544 12-24 95 11:36A1t P001 448
P.02
JAN -18-1996 14:00 209 239 2384 93%
CITY OF LODI CONTRACT PAYMENT
4> PUBLIC WORKS DEPARTMENT
PROJECT: GAC Filter Systems for Well 4R, 22 and 23
Conco West
CONTRACTOR: P.O. Box 1228
Manteca, CA 95336 PAYMENT NUMBER 5
ootcrmm
WORK
UNIT
ITEM
TODATEI
UNITS
! ITEM
ACCT
PRICE
AMOUNT
A - 34% B
;
1
1
100%
LS
Mobilization
-33% C-
$30,000.00
$30,000.00
33%
Provide Design, Drawings and Calculations
2
1
100%
LS
for GAC System at Well 4R
A
$10,000.00 i
I
$10,000.00
Furnish GAC Filter System for Well 4R
3
1
100°k
LS
A
$218.000.00
$218,000.00
4
1
100%
LS
Furnish GAC Filter System for Well 22
E
B
I
$140,000.00
!
$140,000.00
"Furnish GAC Filter System for Well 23
i
5
1
100%
LS
C
$140,000.00
r
$140,000.00
6
1
100%
LS
lFurnish GAC Media for Well 4R
A
$82,000.00
$82,000.00
7
1
100%
LS
Furnish GAC Media for Well 22
B
$56,000.00 !
$56,000.00
8
1
100%
LS
Furnish GAC Media for Well 23
C
$56,000.00 #
$56,000.00
(Install GAC System at Well 4R and Site
9
1
96%
LS
Work
A
$63,500.00 =
!
$61,000.00
10
1
100%
LS
!Install GAC System at Well 22 and Site
B
$63,800.00 }
$63,800.00
Work
11
1
100%
LS
'Install GAC System at Well 23 and Site
C
$48,420.00
.$48,420.00
Work
j
I
A - 34% B
!
12
1
100%
LS
Worker Protection and Safety
-33% C-
$100.00
$100.00
33%
E
13
1
100
LS
Accelerate Schedule
B-50%
$40,000.00
$40,000.00
C-50%
€
CCO#1
Remove Concrete Pavement to Install GAC
1
1
LS
& Backwash line
B
$825.00 j
;
$825.00
CCO#21
"Piping Work @ Well 4R as requested by
1
LS
!Engineer
A
$5,750 ;
$5,750.00
% Work Completed
100%
Total Work Done to Date` $951,895.00
ACCOUNT NUMBERS
A: 018.1-460.60
Less 10 Per Cent Retention; $95,189.50
B: 018.1-460.22
Total Due to Date; $856,705.50
C: 018.1-490.23
Less Previous Payments; $779,440.50
D: 018.1-450.07
Less Liquidated Damages'
E:
(#Days @ $ "Day)?
Made by: WMM
Checked by: WF BALANCE DUE ON THIS ESTIMATE;
$77,265.00
Contract price $947,820+ $825 (CCO#1) + $5,750 (CCO#2) = $954,395.00
FOR PAYMENT OF
J:IPROJECTS\ - Conpay4
4.10
4.10 GUARANTEE
The guarantee period shall be for 365 days. Except for work
accepted as substantially complete, the guarantee period shall
commence on the date of acceptance of the work. or Work described
as complete, a guaran ee pe od shall commence on
the date of substantial completion. During the guarantee period,
the Contractor shall, upon the receipt of notice in writing from
the Owner, promptly make all repairs arising out of defective
materials, workmanship or equipment. The Owner is hereby autho-
rized to make such repairs, if ten days after giving of such notice
to the Contractor, the Contractor has failed to make or undertake
the repairs with due diligence. In case of an emergency, where, in
the opinion of the Owner, delay could cause serious loss or damage,
repairs may be made without notice being sent to the Contractor
and the expenses in connection therewith shall be charged to the
Contractor.
For the purpose of this paragraph, "acceptance of the work"
shall mean the acceptance of the project or a portion of the
project by the Owner, in accordance with paragraph 00710-7.07.
"Acceptance of the work" shall not extinguish any covenant or
agreement on the part of the Contractor to be performed or ful-
filled under this contract which has not, in fact, been performed
or�fulfilled at the time of such acceptance. All covenants and
agreements shall continue to be binding on the Contractor until
they have been fulfilled.
The Owner and the Contractor agree that guarantee on the
equipment possessed and used by the Owner in accordance with
paragraph 00710-7.06 shall commence on the date that the Owner
takes possession of the equipment and so notifies the Contractor
in writing. Owner and Contractor further agree that such taking
possession and use shall not be deemed as substantial completion or
acceptance of any part of the work. Takeover of equipment shall be
at the Owner's option and will not be made until the equipment can
be put into routine service on a permanent basis.
PART 5 --LIABILITY AND INSURANCE
5.01 LIABILITY OF CONTRACTOR
The Contractor shall be liable for any and all losses or
damages from whatever cause which, prior to final acceptance, may
occur on or to any part of the work. The Contractor shall not be
liable for losses or damages caused solely by the act of the Owner.
The Contractor shall be liable for damages and injury which
shall be caused to persons owning property, on or in the vicinity
of the work, or which shall occur to a person, or persons, or
property whatsoever, arising out of the Contractor's performance of
00710-28
O Ei
cQEt�o��,v'
COUNCIL COMM[JNICATION
AGENDA TITLE: Acceptance of Improvements Under Granular Activated Carbon Filter Systems for
Wells 4R, 22 and 23 Contract
MEETING DATE: January 17, 1996
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Granular Activated Carbon Filter Systems for Wells 4R, 22 and 23"
contract and direct the City Engineer to file a Notice of Completion with
the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Conco West, Inc. of Manteca, on
April 19, 1995, in the amount of $947,820. The contract has been
completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was October 20, 1995 and the actual completion date was
January 5, 1996. No liquidated damages were assessed on this project as all three filter systems were
in place by the October 20 deadline and the filter systems at Wells 22 and 23 were being used by the
City by the dates required in the specifications. Conco West was doing minor corrective work and
punch list items after the contract completion date.
The final contract price was $951,895. The difference between the contract amount and the final
contract price is mainly due to additional pipe work done at Well 4R and the deletion from the contract
of the installation of the activated carbon at Well 4R. The activated carbon at Well 4R will be installed
in the spring when the demand on the water system increases. The City has purchased the carbon
from the contractor and the supplier will be issued a purchase order to install the carbon. With Wells
16, 22 and 23 running this winter, there is plenty of water to meet the City's needs and, if the carbon at
Well 4R had been installed under this contract, we would have had to unnecessarily run Well 4R to
keep the carbon fresh and prevent bacteria from forming on the carbon.
FUNDING: As determined at contract award.
Jac L. Ronsko
Publ Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/lm
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED:
H. Dixon Flynn — City Manager
CACCEPT.DW 01/10/96
}71iF O
CITY OF LODI COUNCIL COMMUNICATION
}
AGENDA TITLE: Contract Award for Granular Activated Carbon Filter Systems for Wells 4R, 22 and 23
($947,820)
MEETING DATE: April 19, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the contract for the
above project to Conco-West, Inc. of Manteca in the amount of $947,820.00 (base
bid plus Bid Alternate B).
BACKGROUND INFORMATION: This project consists of furnishing and installing granular activated carbon
(GAC) filter systems at Wells 4R, 22 and 23, and other incidental and related
work, all as shown on the plans and specifications for the project.
Two alternate bid proposals were included in this bid proposal. The base bid for this project required that the GAC
filter system at Well 23 be ready for City operation by August 11, 1995, and the GAC filter system at Well 22 be
ready for City operation by August 25, 1995. Bid Alternate A accelerated the installation of these two sites so that
Well 23 would be ready by July 7, 1995, and Well 22 would be ready by July 21, 1995. The completion dates on
Bid Alternate B for Wells 23 and 22 are June 16, 1995 and June 30, 1995, respectively. Because of the need to
have both of these wells ready for the high demands of the summer months, and because of the small increase in
price to complete the filter systems at Wells 22 and 23 eight weeks ahead of the base bid schedule, it is
recommended that award of this contract include the accelerated schedule in Bid Alternate B.
Plans and specifications for this project were approved on March 15, 1995. The City received the following four
bids for this project:
Base Base Bid + Base Bid +
Bidder Location Bid Bid Alt. A Bid Alt. B
Engineer's Estimate $ 1,141,500
Conco-West, Inc. Manteca $ 907,820 $ 924,820 $ 947,820
Pete Fuller Const. Vacaville $ 896,091 $ 931,091 $ 961,091
Alan A. Bradford, Inc. Fairfield $ 949,000 $ 976,000 $1,009,000
Syblon-Reid Co. Folsom $ 1,135,942 $1,180,942 No bid
FUNDING: Originally Budgeted: 1995
Budgeted Fund: California Safe Drinking Water Bond Law Program
Total Project Estimate: $1,500,000
Bid Opening Date: April 19, 1995
J ck Ronsko
Pub' Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
Attachment
cc: City Attorney
Purchasing Officer
Water/Wastewater Superintendent
APPROVED:
THOMAS A. PETERSON recycled paper
City Manager
CAWARD2.DOC CCS