HomeMy WebLinkAboutResolutions - No. 2003-157RESOLUTION NO. 2003-157
A RESOLUTION OF THE LODI CITY COUNCIL APPROVING PLANS
AND SPECIFICATIONS AND AUTHORIZING ADVERTISEMENT FOR BIDS
FOR THE ALLEY SOUTH OF PINE STREET WASTEWATER MAIN
REHABILITATION PROJECT (CHURCH STREET TO HUTCHINS STREET);
AND FURTHER AUTHORIZING THE CITY MANAGER TO AWARD OR
REJECT THE CONTRACT UP TO $90,000, AND APPROPRIATING
FUNDS FOR THE PROJECT
WHEREAS, this wastewater main rehabilitation project was initiated at the request of
the California Regional Water Quality Control Board (Board) in a letter to the City of Lodi dated
February 2003; and
WHEREAS, the letter requested that the City take action to rehabilitate the wastewater
main located in the alleyway behind 212 West Pine Street, between Church Street and
Hutchins Street; and
WHEREAS; according to the letter, -Guild Cleaners is currently in the process of
installing a soil vapor extraction (SVE) system in the vicinity of the wastewater line. The Board
believes the rehabilitation of the pipeline is critical to the successful pilot study and long-term
operation of that SVE system, and it has requested that the City proceed with the
repair/rehabilitation of this pipeline as soon as practical; and
WHEREAS, although this location was not a high-priority,on the replacement program, it
is one that would be done in the foreseeable future. , Staff has therefore completed the design
documents for rehabilitating 1,190 LF of existing 6 -inch diameter wastewater main and
reinstating 53 active service connections using trenchless methods; and
WHEREAS, in order to expedite this project, staff recommends that the City Council
approve the plans and specifications and authorize advertisement for bids for the Alley South of
Pine Street Wastewater Rehabilitation Project (Church Street to Hutchins Street), authorize the
City Manager to award or reject the contract up to $90,000.00, and further appropriate funds for
this project.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve
the plans and specifications and authorize advertisement for bids for the Alley South of Pine
Street Wastewater Rehabilitation Project (Church Street to Hutchins Street) and authorize the
City Manager to award or reject the contract up to $90,000.00; and
BE IT FURTHER RESOLVED that funds in the amount of $90,000.00 be appropriated
from the Wastewater Fund for this project.
Dated: September 3, 2003
I hereby certify that Resolution No. 2003-157 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held September 3, 2003, by the following vote:
AYES: COUNCIL MEMBERS — Beckman, Howard, Land, and Mayor Hitchcock
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Hansen
ABSTAIN: COUNCIL MEMBERS — None
SUSAN J. BLACKSTON
City Clerk
2003-157