HomeMy WebLinkAboutResolutions - No. 2002-210RESOLUTION NO. 2002-210
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE
CONTRACT FOR INSTALLATION OF STREETLIGHTS UNDER
STREETLIGHT COMPLETION PROJECT PHASE III
WHEREAS, in answer to notice duly published in accordance with law and the order
of this City Council sealed bids were received and publicly opened September 17, 2002 at
11:00 a.m. for installation of streetlights under Streetlight Completion Project Phase III,
described in the specifications therefore approved by the City Council on August 21, 2002;
and
WHEREAS, said bids have been compared, checked, and tabulated and a report
thereof filed with the City Manager as follows:
BIDDER/LOCATION
AMOUNT
Clayborn Contracting Group, Inc. Auburn CA
662 259.00
Royal Electric Co. Sacramento CA
$ 705 075.00
Kinnan Engineering,Inc. Camas Valley, OR
738 851.09
Pacific Excavation Inc. Elk Grove CA
789 300.00
Golden State Utility Company,Turlock CA
I $ 834 011.00
Steiny and Company, Inc. Valle'o CA
840 600.00
Collins Electrical Company, Inc. Stockton CA
$ 945 000.00
Underground Construction Co. Inc. Benicia CA
$1.127.174.00
WHEREAS, the City Manager recommends awarding the contract for the installation
of streetlights under Streetlight Completion Project Phase III, to Clayborn Contracting Group,
Inc., of Auburn, California.
NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council does hereby
award the contract for the installation of streetlights under Streetlight Completion Project
Phase III, to Clayborn Contracting Group, Inc., of Auburn, California, in the amount of
$662,259.00
Dated: October 16, 2002
I hereby certify that Resolution No. 2002-210 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held October 16, 2002, by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Howard, Land, Nakanishi, and
Mayor Pennino
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
SUSAN J. BLACKSTON
City Clerk
2002-210