HomeMy WebLinkAboutResolutions - No. 80-29RESOLUTION NO. 80-29
AWARD - CONTRACT FOR MUNICIPAL SERVICE
CENTER, PHASE II
WHEREAS, in answer to notice duly published in accordance
with law and the order of this City Council, sealed bids were
received and publicly opened by the City Clerk of this City on
January 8, 1980 at 11:00 a.m. for the contract for Municipal
Service Center, Phase II as described in the specifications
therefor approved by the City Council September 19,1979; and
WHEREAS, said bids have been compared, checked, and tabulated
and a report thereof filed with the City Manager as follows:
BIDDER AMOUNT
Brown Sheet Metal and Mechanical, Inc. $6305109
Modern Engineering & Construction Co., Inc. 659,220
Fanos Construction 660,574
F 8 H Construction
Kimmel Construction, Inc.
664,000
698,725
WHEREAS, the City Manager recommends that award be made
to the low bidder, Brown Sheet Metal and Mechanical, Inc. in the
amount of $588,220, thereby deleting bid item 5, the construction
of the parking lot between the existing substation and the
Animal Shelter - ($411)889.)
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Lodi that award of contract for the Municipal Service
Center, Phase II be and the same is hereby made to Brown Sheet
Metal and Mechanical, Inc. the low bidder, in the amount of
$588,220.
Dated: February 6, 1980
I hereby certify that Resolution No. 80-29 was passed
and adopted by the City Council of the City of Lodi
in a regular meeting February 6, 1980 by the following
vote:
Ayes: Councilmen - Hughes, Katnich, McCarty, Pinkerton
and Katzakian
Noes: Councilmen - None
Absent: Councilmen - None
i
A�4m . REt CHH'
CITY CLERK
80-29