HomeMy WebLinkAboutResolutions - No. 81-81RESOLUTION NO. 81-81
AWARD - CONTRACT FOR ROCK AND SAND MATERIAL -
FISCAL YEAR 1981 - 82
WHEREAS, in answer to notice duly published in accordance
with law and the order of this City Council, sealed bids were
received and publicly opened by the City Clerk of this City on
July 1, 1981 at 11:00 a.m. for the Contract for Rock and Sand
Material - Fiscal Year 1981 - 82 as described in the specifica-
tions therefor approved by the City Council June 17, 1981; and
WHEREAS, only one bid was received, said being as shown
on Exhibit "A" attached hereto and thereby made a part hereof;
WHEREAS, it has been determined that the above bid is a
reasonable bid; and
WHEREAS, the City Manager recommends that award be
made;
NOW, THEREFORE, BE IT RESOLVED by the City Council of
the City of Lodi that award of Contract for Rock and Sand
Material - Fiscal Year 1981 - 82 be made to Claude C. Wood Co.,
the only bidder, in the amounts shown on Exhibit "A"_ attached
hereto.
Dated: July 1,, 1981
I hereby certify that Resolution No. 81-81 was passed
and adopted by the City Council -of the City of Lodi
in a regular meeting held July 1, 1981 by the following
vote:
Ayes: Councilmen - Hughes, Murphy, Pinkerton, Katnich
and McCarty
Noes: Councilmen - None
Absent: Councilmen - None
ALICE M. RE CHE
City Clerk
PUBLIC WORKS DEPARTMENT
BIDS FOR ROCK b SAND MATERIALS
s
ITEM NO. 2
ITEM NO. 3
ITEM N0, 4
ITEM NO. 1
3/4" Class 2 Aggregate Base
Concrete Sand
1/4" x #10 Crushed Rock ScreeninE
4" x 8'' Cobbles
A
B
A
B
A
B
A
B
SUPPLIER
Plant
(100 Tons)
Stockpile
City Limits
City
(500 Tons)
F.O.B. Plant
(100 Tons)
Stockpile
City Limits
(400 Tons)
F.O.B. Plant
(100 Tons)
Stockpile
City Limits
(400 Tons)
F.O.B. Plant
(100 Tons)
Stockpile
City Limits
(300 Tons)
Claude C. Wood Co. Clcments
$ 4.081
$ 6.731
$ 4.77
$ 7.42
$ 7.155
$ 9.805
$ 6.201
$ 8.851
Cost per ton including tax
Plus: City cost for mileage
3.95
3.95
3.95
3.95
TOTAL
$ 8.031
$ 6.731
$ 8.72
$ 7.42
$11.105
$ 9.805
$10.151
$ 8.851
s