HomeMy WebLinkAboutAgenda Report - October 7, 1998 (97)AGENDA TITLE: Electric Rate Schedule G1 (General Service — Group 1 Commercial/Industrial) Change — five
percent reduction.
MEETING DATE: October 7, 1998
PREPARED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council introduce ordinance approving changes to the Electric
Rate Schedule G1 (General Service — Group 1 CommerciaUlndustrial) to be
effective on and after December 1, 1998, which will result in a net five
percent reduction from the current rate schedule.
BACKGROUND INFORMATION: The proposed rate schedule reduction is in response to industry competition.
The G1 customer class average yearly electric rate is now above that of the
surrounding investor owned utility due to AB1890's mandated ten percent
electric rate reduction. The proposed rate reduction will help restore our
competitive advantage by placing our G1 customer class average yearly
electric rate approximately three percent below our nearest competitor.
Based on sales revenue generated by G1 customers during FY1997-98, it is estimated that this rate reduction will
result in a yearly revenue reduction of $250,000.
FUNDING: Not applicable.
Ala . qall&v
Electric Utility Director
PREPARED BY: Jack Stone, Manager, Business Planning and Marketing
ANV/JS/pn
c: City Attorney
Finance Director
APPROVED: (�Ivmo —&& 461
H. Dixon Flynn -- Ci anager 10-07-98 JS
CITY OF LODI
ELECTRIC UTILITY DEPARTMENT
SCHEDULE G1
GENERAL SERVICE - GROUP 1 COMM ERCIAUINDUSTRIAL
APPLICABILITY
This schedule is applicable to customers with single-phase or three-phase service, or to a
combination thereof, whose energy consumption does not exceed 8,000 kilowatt-hours (kWh) per
billing cycle for three consecutive billing cycles. This schedule is not available for service when
another commercial/industrial schedule is applicable.
Assignment to Schedule: If, in the judgement of the City, an account is expected to have usage
below 8,000 kWh per billing cycle, the City has the option of placing the account immediately on
this schedule.
When an account billed on this schedule permanently changes the nature of electrical operations to
such an extent that the account would in time qualify for another rate schedule, such billing change
will be made as soon as practicable after verification of said changes.
If energy consumption equals or exceeds 8,000 kWh for three consecutive billing cycles, the City
will transfer the account to the appropriate rate schedule. If the demand reaches or exceeds 400
kW for three consecutive billing cycles, the account will be transferred to the appropriate rate
schedule.
RATES:
Customer Charge: (per meter per billing cycle)
Single -Phase Service .....................................
Three -Phase or Combination Service .............
Energy Charge: (per kWh)
Summer (May through October) ................
Winter (November through April) ..............
PURCHASED POWER COST ADJUSTMENT (PPCA):
........................... $7.00
........................... 10.35
..................... . 12967
..................... .08889
A purchased power cost adjustment may be included in each bill for service. The adjustment shall
be the product of the total kilowatt-hours (kWh) for which the bill is rendered times the adjustment
amount per kWh. The adjustment amount per kWh will be calculated to reflect amounts charged
the City by various suppliers of bulk power not covered in the above rates.
Effective December 1, 1998
Canceling Ordinance No. 1655 G1-1/3 Ordinance No......
SCHEDULE G1
GENERAL SERVICE - GROUP 1 COMMERCIAUINDUSTRIAL
CHEROKEE LANE ECONOMIC INCENTIVE DISCOUNT:
G1-Commercial/Industrial customers establishing accounts in the Cherokee Lane portion of the
Central City Revitalization Area on or after January 1, 1995, are eligible for the following discounts
on Energy and Demand charges:
July 1, 1996 - June 30, 1997............
July 1, 1997 - June 30, 1998 ............
July 1, 1998 - June 30, 1999............
July 1, 1999 - June 30, 2000 ............
After June 30, 2000 ......................
.............................................. 20%
.............................................. 15%
0
.............................................. 5%
........................... I.................. 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will be
applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
COMMERCIAL DEVELOPMENT INCENTIVE DISCOUNT:
G1-Commercial/Industrial customers establishing accounts in the City of Lodi on or after January 1,
1995, are eligible for the following discount on Energy and Demand charges.
July 1, 1996 - June 30, 1999...................................................................... 10%
July 1, 1999 - June 30, 2000 ......................... °
After June 30, 2000.......................................................................... 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will be
applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
COMMUNITY BENEFITS INCENTIVE DISCOUNT:
G1 -Non-profit (as defined in Federal Internal Revenue 501 (c) (3) ) Industrial/Commercial customers
who are currently receiving Federal Community Development Block Grant funds or have received such
funds not more than two years before preparation of the current billing cycle charge are eligible for the
following discount on Energy and Demand charges:
July 1, 1996 and after................................................................... 30%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will be
applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
Effective December 1, 1998
Canceling Ordinance No. 1655 G1-2/3 Ordinance No......
SCHEDULE G1
GENERAL SERVICE - GROUP 1 COMMERCIAUINDUSTRIAL
CORE AREA ECONOMIC INCENTIVE DISCOUNT:
G11-Commercial/Industrial customers establishing accounts in the Core Area of the Central City
Revitalization Area on or after January 1, 1995, are eligible for the following discounts on Energy
and Demand charges:
July 1, 1996 - June 30, 1997................................................................ 40%
July 1, 1997 - June 30, 1998................................................................ 30%
July 1, 1998 - June 30, 1999................................................................ 20%
July 1, 1999 - June 30, 2000 .................................... o
After June 30, 2000.......................................................................... 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will be
applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
BILLING CYCLE CHARGE (MONTHLY BILL):
The billing cycle charge is the sum of the Customer Charge, the Energy Charge and the PPCA.
Effective December 1, 1998
Canceling Ordinance No. 1655 G1-3/3 Ordinance No......
ORDINANCE NO. 1668
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF LODI
AMENDING CHAPTER 13.20 OF THE LODI MUNICIPAL CODE BY
REPEALING AND REENACTING SECTION 13.20.240, RELATING TO
ELECTRIC SERVICE - RATES
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF LODI AS FOLLOWS:
SECTION 1. Chapter 13.20 - Electrical Service - is hereby amended by repealing and reenacting Section
13.20.240, relating to Group 1 Commercial/Industrial Rates by__attaching new Exhibit F:
Section 13.20.240 - Schedule G1 - General Service - Group 1 Commercial/Industrial.:
For Group 1 commercial/industrial rates, see the schedule attached to the ordinance
codified in this chapter, marked Exhibit F and made a part hereof as if set out in full.
Section 2. - No Mandatory Duty of Care. This ordinance is not intended to and shall not be construed or
given effect in a manner which imposes upon the City, or any officer or employee thereof, a mandatory
duty of care towards persons or property within the City or outside of the City so as to provide a basis of
civil liability for damages, except as otherwise imposed by law.
Section 3. - Severability. If any provision of this ordinance or the application thereof to any person or
circumstances is held invalid, such invalidity shall not affect other provisions or applications of the
ordinance which can be given effect without the invalid provision or application. To this end, the provisions
of this ordinance are severable. The City Council hereby declares that it would have adopted this
ordinance irrespective of the invalidity of any particular portion thereof.
SECTION 4. All ordinances and parts of ordinances in conflict herewith are repealed insofar as such
conflict may exist.
SECTION 5. The increased rates shall be effective on applicable electric utility billings prepared by the
City of Lodi on or after December 1, 1998.
Approved this day of , 1998
JACK A. SIEGLOCK
MAYOR
ATTEST:
ALICE M. REIMCHE
City Clerk
State of California County of San Joaquin, ss.
I, Alice M. Reimche, City Clerk of the City of Lodi, do hereby certify that Ordinance No. 1668 was
introduced at a regular meeting of the City Council of the City of Lodi held October 7, 1998 and was
thereafter passed, adopted and ordered to print at a regular meeting of said Council held ,
1998 by the following vote:
Ayes: Council Members -
Noes: Council Members -
Absent: Council Members -
Abstain: Council Members -
I further certify that Ordinance No. 1668 was approved and signed by the Mayor on the date of its passage
and the same has been published pursuant to law.
ALICE M. REIMCHE
City Clerk
Approved to Form:
RANDALL A. HAYS
City Attorney
UWAYUL-Ii>�u7
CITY OF LODI
ELECTRIC UTILITY DEPARTMENT
SCHEDULE G1
This schedule is applicable to customers with single-phase or three-phase service, or to a
combination thereof, whose energy consumption does not exceed 8,000 kilowatt-hours (kWh) per
billing cycle for three consecutive billing cycles. This schedule is not available for service when
another commercial/industrial schedule is applicable.
Assignment to Schedule: If, in the judgment of the City, an account is expected to have usage
below 8,000 kWh per billing cycle, the City has the option of placing the account immediately on
this schedule.
When an account billed on this schedule permanently changes the nature of electrical operations
to such an extent that the account would in time qualify for another rate schedule, such billing
change will be made as soon as practicable after verification of said changes.
If energy consumption equals or exceeds 8,000 kWh for three consecutive billing cycles, the City
will transfer the account to the appropriate rate schedule. If the demand reaches or exceeds 400
kW for three consecutive billing cycles, the account will be transferred to the appropriate rate
schedule.
RATES:
Customer Charge: (per meter per billing cycle)
Single -Phase Service .................................................................... $7.00
Three -Phase or Combination Service ............................................. 10.35
Energy Charge: (per kWh)
Summer (May through October) ..................................................... .12967
Winter (November through April) ................................................... .08889
A purchased power cost adjustment may be included in each bill for service. The adjustment shall
be the product of the total kilowatt-hours (kWh) for which the bill is rendered times the adjustment
amount per kWh. The adjustment amount per kWh will be calculated to reflect amounts charged
the City by various suppliers of bulk power not covered in the above rates.
SCHEDULE G1
GENERAL SERVICE — GROUP 1 COMMERCIAL/INDUSTRIAL
CHEROKEE LANE ECONOMIC INCENTIVE DISCOUNT:
G1-Commercial/Industrial customers establishing accounts in the Cherokee Lane portion
of the Central City Revitalization Area on or after January 1, 1995 are eligible for the
following discounts on Energy and Demand charges:
July 1, 1996 - June 30, 1997.......................................................... 20%
July 1, 1997 - June 30, 1998.......................................................... 15%
..............
July 1, 1998 - June 30, 1999.......................................................... 10%
July 1, 1999 - June 30, 2000 .................. o
After June 30, 2000........................................................................ 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will
be applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
COMMERCIAL DEVELOPMENT INCENTIVE DISCOUNT:
G1-Commercial/Industrial customers establishing accounts in the City of Lodi on or after January 1,
1995 are eligible for the following discount on Energy and Demand charges:
July 1, 1996 - June 30, 1999 ......................................... o
July 1, 1999 - June 30, 2000...................................................................... 5%
After June 30, 2000.......................................................................... 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will
be applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
COMMUNITY BENEFITS INCENTIVE DISCOUNT:
G1 -Non-profit (as defined in Federal Internal Revenue 501 (c) (3) ) Industrial/Commercial
customers who are currently receiving Federal Community Development Block Grant funds or have
received such funds not more than two years before preparation of the current billing cycle charge
are eligible for the following discount on Energy and Demand charges:
July 1, 1996 and after..................................................................30%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will
be applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
GENERAL SERVICE — GROUP 1 COMMERCIAL/INDUSTRIAL
•- • •Rivellin
G1-Commercial/Industrial customers establishing accounts in the Core Area of the Central
City Revitalization Area on or after January 1, 1995 are eligible for the following discounts
on Energy and Demand charges:
July 1, 1996 - June 30, 1997 .............
July 1, 1997 - June 30, 1998 .............
July 1, 1998 - June 30, 1999 .............
July 1, 1999 - June 30, 2000 .............
After June 30, 2000 ...........................
........................................ 40%
........................................ 30%
0
........................................ 10%
........................................ 0%
It is the customer's responsibility to notify the Finance Department of this eligibility. Discounts will
be applied retroactively back to either the account start date or July 1, 1996, whichever is later.
This discount may not be used in conjunction with any other incentive discount.
BILLING CYCLE CHARGE (MONTHLY BILL
The billing cycle charge is the sum of the Customer Charge, the Energy Charge and the PPCA.
2