HomeMy WebLinkAboutAgenda Report - October 7, 1998 (82)CITY OF LODI COUNCII, COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Contract for Lodi Lake Park Entrance Improvements,
1101 West Turner Road
MEETING DATE: October 7, 1998
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Lodi Lake Park
Entrance Improvements, 1101 West Turner Road" contract and direct the
City Engineer to file a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Uprite Construction, of Stockton, on
June 3, 1998, in the amount of $68,724.85. The contract has been
completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was August 24, 1998, and the actual completion date was August 17, 1998.
The final contract price was $72,731.21. The net increase of $4,120.53 was due to additional demolition,
concrete and asphalt work.
FUNDING: Budgeted Fund: 1997/98 Parks and Recreation Capital Improvement Fund ($76,100.00)
Contract Amount: $72,731.21
�aj
Richard C. Prima, Jr.
Public Works Director
Prepared by Wes K. Fujitani, Senior Civil Engineer
RCPMIKF/do
cc: Purchasing Officer
Parks Superintendent
APPROVED: _J ka&�� -Am
H. Dixon Flynn -- City anager
Caccpt.doc 09/28/98