HomeMy WebLinkAboutResolutions - No. 91-197i
RESOLUTION NO. 91-197
----------------------
----------------------
A RESOLUTION OF THE LODI CITY COUNCIL
APPROVING MODIFYING THE PARKING LIMIT FROM TWO-HOUR TO TWO-HOUR OR ALL
DAY PARKING WITH ZONE B PERMITS ON THE WEST SIDE OF CHURCH STREET FROM
PINE STREET NORTH TO THE ALLEY (FIVE PARKING STALLS) AND THEREBY
AMENDING TRAFFIC RESOLUTION NO. 87-163, SECTION 6 - PERMIT PARKING
RESOLVED, that the Lodi City Council hereby approves the
modification of the parking limit from two-hour to two-hour or all day
parking with Zone B permits on the west side of Church Street from Pine
Street north to the alley (five parking stalls); and
BE IT FURTHER RESOLVED, that the Lodi City Council hereby
approves amending Traffic Resolution No. 87-163, Section 6(A) - Permit
Parking - to modify the parking limit from two-hour to two-hour or all
day with Zone B permits on the west side of Church Street from Pine
Street north to the alley (five parking stalls) - as shown on Exhibit A
attached; and
FURTHER RESOLVED, that the Traffic Resolution No. 87-163 Section
6 is further amended to authorize the City Manager to allow all -day
parking for vehicles displaying Civic Center parking permits in
designated downtown parking areas (Zone B).
Dated: October 16, 1991
I hereby certify that Resolution No. 91-197 was passed and
adopted by the City Council of the City of Lodi in a regular
meeting held October 16, 1991 by the following vote:
Ayes: Council Members - Pennino, Pinkerton, Sieglock, Snider
and Hinchman (Mayor)
Noes: Council Members - None
Absent: Council Members - None
Aw �t -6ax�
Alice M. Rei the
City Clerk
91-197
RES91197/TXTA.02J
J
la--
1zjs
c
�lt11 w��
M
3C�oNd
4�1 1at J-1 i-:�,
M1
Cl�)
PH1-;�?N-4
1t w2Ga
33J�1d � 3
J.1»
V 12%VxLY
1�175`�d 71H-7, L2
�4'tc: �4
'd5 X11-
1N3WIdVd30 SMOM Wend eN
lclol Jo AilD W*7
_ f
STATE OF CALIFORNIA—THE RESOURCES AGENCY PETE WILSON, Governor
DEPARTMENT OF WATER RESOURCES
1416 NINTH STREET, P.O. BOX 942836 ,92 _
n.:
SACRAMENTO, CA 94236-0001 �.
(916) 653.5791
.. , vTrce
21 1992
Honorable David M. Hinchman, Mayor
City of Lodi
Post Office Box 3006
Lodi, California 95241-1910 -
Dear Mayor Hinchman:
Enclosed is an original executed Contract, Number E54402 between the
City of Lodi in San Joaquin County, and the State of California, for a
$4,758,000 loan under the Safe Drinking Water Bond Law of 1988. These
funds are to assist your community in meeting safe drinking water standards
for your domestic water supply.
You must submit a summary of all bids to DWR before awarding
construction contracts over $10,000, or contracts in any amount and for any
purposes for which competitive bids are required under your enabling
authority.
Enclosed are copies of claim forms 4135, 4135A and 4135C, together
with a sample of the completed forms. When requesting funds, you must
submit the original and four copies of the forms and attachments for
processing to the Department of Water Resources, Bond Financing and
Administration Office, Attention: Sarah Richey, Room 816, Post Office Box
942836, Sacramento, California 94236-0001. If you have any questions about
claim forms please call Sarah Richey at (916) 653-4763.
I am pleased to assist the City -of Lodi in providing safe drinking
water for the community it serves. If you need further information please
contact Lorri Silva at (916) 653-9634.
Sincerely,
Ox'lginal signed by
Chester M. Winn, Chief
Division of Fiscal Services
Enclosures
cc: (see next page)
Ar
r
Mr. Thomas A. Peterson, City Manager
City of Lodi
Post office Box 3006
Lodi, California 95241-1910
Mr.. Homer Vaughn, Acting District Engineer
_Stockton District
_ �Off-ice of Drinking Water
Department of Health Services
31 E. Channel Street
State Building, Room 270
Stockton, California 95202
i
•r
STATE OF CALIFORNIA—THE RESOURCES AGENCY PETE WILSON, Governor
DEPARTMENT OF WATER RESOURCES
1416 NINTH STREET, P.O. BOX 942836 _ v •�
SACRAMENTO, CA 94236-0001 i
(916) 653.5791
JAN 2 1192
Honorable.David M. Hinchman, Mayor
City of Lodi _
Post Office Box -3006
Lodi, California 95241-1910
Dear Mayor Hinchman:
Enclosed is an original executed Contract, Number E54402 between the
City of Lodi in San Joaquin County, and the State of California, for a
$4,758,000 loan under the Safe Drinking Water Bond Law of 1988. These
funds are to assist your community in meeting safe drinking water standards
for your domestic water supply.
You must submit a summary of all bids to DWR before awarding
construction contracts over $10,000, or contracts in any amount and for any
purposes for which competitive bids are required under your enabling
authority.
Enclosed are copies of claim forms 4135, 4135A and 4135C, together
with a sample of the completed forms. When requesting funds, you must
submit the original and four copies of the forms and attachments for
processing to the Department of Water Resources, Bond Financing and
Administration Office, Attention: Sarah Richey, Room 816, Post Office Box
942836, Sacramento, California 94236-0001. If you have any questions about
claim forms please call Sarah Richey at (916) 653-4763.
I am pleased to assist the City of Lodi in providing safe drinking
water for the community it serves. If you need further information please
contact Lorri Silva at (916) 653-9634.
Sincerely,
Chester M. Winn, Chief
Division of Fiscal Services
Enclosures
cc: (see next page)
Q
rr -
'.J
Enclosed is an original executed Contract, Number E54402 between the
City of Lodi in San Joaquin County, and the State of California, for a
$4,758,000 loan under the Safe Drinking Water Bond Law of 1988. These
funds are to assist your community in meeting safe drinking water standards
for your domestic water supply.
You must submit a summary of all bids to DWR before awarding
construction contracts over $10,000, or contracts in any amount and for any
purposes for which competitive bids are required under your enabling
authority.
Enclosed are copies of claim forms 4135, 4135A and 4135C, together
with a sample of the completed forms. When requesting funds, you must
submit the original and four copies of the forms and attachments for
processing to the Department of Water Resources, Bond Financing and
Administration Office, Attention: Sarah Richey, Room 816, Post Office Box
942836, Sacramento, California 94236-0001. If you have any questions about
claim forms please call Sarah Richey at (916) 653-4763.
I am pleased to assist the City of Lodi in providing safe drinking
water for the community it serves. If you need further information please
contact Lorri Silva at (916) 653-9634.
Sincerely,
Chester M. Winn, Chief
Division of Fiscal Services
Enclosures
cc: (see next page)
City Construction
Loan Contract No. E54402
FOR A CONSTRUCTION LOAN UNDER THE
CALIFORNIA SAFE DRINKING WATER BOND LAW OF 1988
E54(11-16-89)
TABLE OF CONTENTS
SPECIAL CONTRACT PROVISIONS
Section
Page
1.
Purpose of Loan ...............................................
1
2.
Incorporation of Standard Conditions, Security Requirements,
and Plans and Specifications..... ..................................
1
3.
Estimate of Project Cost ......................................
2
4.
Loan Amount ...................................................
2
5.
Supplier's Cost ...............................................
2
6.
Requirements for Disbursement .................................
2
7.
Rate of Interest ..............................................
2
8.
Water Conservation ............................................
2
9.
Operation and Maintenance of Project ..........................
3
10.
Other Assistance ..............................................
3
11.
Repayment of Principal and Interest ...........................
3
12.
Project Officials and Notices .................................
4
EXHIBIT A
LOAN CONTRACT STANDARD CONDITIONS
Article Pave
A-1. Definitions................................................... Al
A-2. Term of Contract .............................................. A2
A-3. Basic Conditions Precedent .................................... A3
A-4. Compliance with Laws, Regulations, and Permit Requirements.... A3
E54(11-16-89) -i-
f
TABLE OF CONTENTS (continued)
Article Page
A-5. Loan
Disbursements by State ...................................
A4
(a)
Cost Statement ...........................................
A4
_. (b)
Disbursement .............................................
A4
(c)
Withholding of Loan Disbursements by Supplier............
A4
A-6. Withholding of Loan Disbursements by State ....................
A4
(a).
Conditions. for -Withholding ...............................
A4
(b)
Withholding Entire Loan Commitment .......................
A4
(c)
Withholding Balance of Loan Commitment ...................
A4
A-7. Timing and Manner of Project Construction .....................
A5
(.a)
Project. Completion Date ..................................
A5
(b)
Construction Pursuant to Project Plans and Specifications
A5
(c)
Determination of Project Completion ......................
A5
(d)
Competitive Bidding ......................................
A5
(e)
Sign Referring to Safe Drinking Water Bond Law Financing.
A5
(f)
Audit Requirement ........................................
A6
A-8.
Statement of Principal Amount of Loan .........................
A6
(a) Remittance of Unexpended Funds ...........................
A6
(b) Transmission of Statement to Supplier ....................
A6
A-9.
Repayment of Principal Amount of Loan .........................
A6
(a),.Repayment Terms ..........................................
A6
(b) Advance Payment Option ...................................
A8
A-10.
Interest Payments .............................................
A8
A-11.
Delinquency in Interest Payment ...............................
A8
A-12.
Security Requirements .........................................
A8
A-13.
Payment Capacity Impairments ..................................
A8
(a) Transfer of Water Outside of Service Area ................
A8
(b) Changes in Supplier's Organization .......................
A9
A-14,.
Accounting and Deposit of Joan Proceeds .......................
A9
(a) Separate Accounting of Loan Disbursements and Interest;
- . Records ..................................................
A9
(b) Disposition of Money Disbursed ...........................
A9
(c):. Interim and Final Audits .................................
A9
A-15.
Reports on Expenditures and Project Construction ..............
A9
A-16.
Inspections of Project by State and State Department of Health
Services......................................................
A9
A-17. Prohibition Against Disposal of Project Without State Permis-
sion.......................................................... A10
E54(11-16-89) -ii-
TABLE OF CONTENTS (continued)
Article
Page
A-18.
Nondiscrimination Clause ......................................
A10
A-19.
Worker's Compensation Clause ..................................
All
A-20.
Successors and Assigns ........................................
All
A-21.
State to be.Held Harmless...-... ...............................
All
A-22.
Remedies not Exclusive ........................................
All
A-23.
Amendments ...................................................
All
A-24.
Opinions and Determinations ..................................
All
A-25.
Contracting Officer of the State .............................
All
A-26.
Waiver of Rights .............................................
Al2
A-27.
Notices........................................................
Al2
A-28.
Inspection of Books, Records, and Reports ....................
Al2
A-29.
Suit on Contract .............................................
Al2
A-30.
Claims Dispute Clause ........................................
Al2
EXHIBIT B
LOAN CONTRACT SECURITY REQUIREMENTS
B-1. No Priority for Additional Loans ............................. Bl
B-2. Rates and Charges ............................................ B1
B-3. Performances and Assurances .................................. B1
B-4. Security Interest ............................................ B1
B-5. Default Provisions ........................................... B1
B-6. Reserve Fund ................................................. B2
E54(11-16-89) -iii-
FA -
CONTRACT NO. E54402
STATE OF CALIFORNIA
THE RESOURCES AGENCY
DEPARTMENT OF WATER RESOURCES
CONTRACT BETWEEN STATE OF CALIFORNIA
DEPARTMENT OF WATER RESOURCES AND
CITY OF LODI
UNDER THE CALIFORNIA SAFE DRINKING WATER BOND LAW OF 1986
THIS CONTRACT, entered into by and between the State of
California, acting by and through its Department of Water Resources, herein
referred to as the "State" and the City of Lodi . a public agency in the
County of San Joaquin . State of California, duly organized,
existing, and acting pursuant to the laws thereof, herein referred to as the
"Supplier", which parties do hereby agree as follows:
CONTRACT SPECIAL PROVISIONS
SECTION 1. PURPOSE OF LOAN
This loan is made by the State to the Supplier to assist in
financing construction of a project that will enable the Supplier to meet
safe drinking water standards established pursuant to Chapter 7 (commencing
with Section 4010 ) of Part 1 of Division 5 of the Health and Safety Code.
Loan funds may be used only for such Eligible Project as defined in the final
plans and specifications, approved by the State Department of Health
Services, and any revisions thereof, and Article A-1 of the Loan Contract
Standard Conditions.
Supplier is solely responsible for design, construction,
operation and maintenance of the project. Review or approval of plans,
specifications, bid documents or other construction documents by the State is
solely for the purpose of proper administration of loan funds by the State
and shall not be deemed to relieve or restrict the Supplier's responsibility.
SECTION 2. INCORPORATION OF STANDARD CONDITIONS AND SECURITY REQUIREMENTS,
AND PLANS AND SPECIFICATIONS AND SUPPLIER COMMITMENTS
This Contract incorporates Exhibit A, "Loan Contract Standard
Conditions" (hereinafter referred to as "Standard Conditions") and Exhibit B,
"Loan Contract Security Requirements" (hereinafter referred to "Security
Requirements), and any attachments thereto. Upon their completion, the final
plans and specifications approved by the State Department of Health Services
and referred to in Section 1 also shall be attached and are incorporated
herein and made a part of this Contract. The Supplier accepts and agrees to
comply with all terms, provisions, conditions, and commitments of this
-54(11-16-89) -1-
r
SECTION 9. OPERATION AND MAINTENANCE OF PROJECT
For a period of 20 years, which is the reasonably expected
life of the Project, in consideration of the loan made by the State, the
Supplier agrees to commence and to continue operation of the Project upon
completion and shall cause the Project to be operated in an efficient and
economical manner; shall provide'__for the-making'of all repairs, renewals, and
replacements necessary to the efficient operation of the same; and shall
cause the same to be maintained in as good and efficient condition as upon
its construction, ordinary and reasonable wear and depreciation excepted.
Refusal of the Supplier to operate and maintain the Project in accordance
with this provision may, at the option of the State, be considered a material
breach of Contract and may be treated as default under Article B-5 of
Exhibit B.
SECTION 10. OTHER ASSISTANCE
Supplier certifies that it has applied for and made reasonable
efforts to secure federal assistance for the Project and has secured the
approval of_the___$.tate_and the --State Department of Health Services to make
application for federal assistance in order to maximize and to utilize best
the amounts of such assistance available.
Supplier further agrees that if federal funds become available
for this Project within three years of Project completion, Supplier will
remit to the State all or a portion of the federal funds received up to the
amount necessary to discharge the remaining debt, provided remittance is not
contrary to the terms upon which federal funds were received.
SECTION 11. REPAYMENT OF PRINCIPAL AND INTEREST
The Supplier shall execute a fiscal services agreement with a
Fiscal Agent in a format acceptable to the State. A Fiscal Agent shall be
retained until .the Principal Amount of the Loan and interest have been paid
in full.
The Supplier shall open a special account with the Fiscal Agent
into which sufficient funds sha-11-be•maintained for servicing the loan as
provided in Article B-6 of the Security Requirements. Funds from this
account shall be used only for payment of principal and interest on the loan
when due, or any delinquencies thereon, until the loan is repaid in full.
Once a fiscal services agreement has been approved by the State,
the Supplier shall not amend the agreement, close the special account, or
retain a new Fiscal Agent without 90 days advance notice and prior written
approval of a new fiscal services agreement by the State.
A public agency may employ the services of its controller or
treasurer as Fiscal Agent only with the prior written approval of the State.
The State shall have no obligation to disburse funds until the -
Fiscal Agent has been engaged and the agreement between the Supplier and the
Fiscal Agent has been approved by the State.
E54(11-16-89) -3-
SECTION 12. PROJECT OFFICIALS AND NOTICES
The State Project Manager shall be the Chief, Division of Fiscal
Services of the Department of Water Resources.
The State Project Manager shall be the State's representative for
administration of the Contract and shall have authority to make determina-
tions and findings with respect to each controversy arising under or in
connection with the interpretation, performance,,or payment for work
performed under the Contract. _Disputes shall be resolved in accordance with
Article A-30 of Exhibit A.
The Supplier Project Director shall be the Public Works Director
for the City of Lodi The Supplier Project Director
shall be the Supplier's representative for the administration of the Contract
and shall have full -authority to act on behalf of the Supplier. All communi-
cations given to the Project Director shall be as binding as if given to the
Supplier.
Either party may change its Project Manager or Project Director
upon written notice to the other party.
- Notices required to be given in writing by the Supplier under
this Contract shall be sent to:
State of California
Department of Water Resources
Attention: Program Manager
Safe Drinking Water Program
1416 9th Street, Room 338
P. 0. Box 942836
Sacramento, CA 94236-0001
Notices required to be given in writing by the State under this
Contract shall be sent to:
Honorable Mayor
Citv of Lodi
Post Office Box 3006
Lodi, California 95241-1910
E54(11-16-89) -4-
r
A change of address for delivery of notice may be made by either
party by written notice of such change of address to the ocher party.
All such notices shall be enclosed in a properly addressed, post-
age prepaid envelope and deposited in a United States Post Office for
delivery by registered or certified mail.
__.. IN.WITNESS_WHEREOF,.the parties hereto have -executed this
Contract on AN 2 = tg92
Approved as to Legal_Form__._. STATE OF CALIFORNIA
and Sufficiency: DEPARTMENT OF WATER RESOURCES
B By C!: e-
Chief Counsel Chief
Department of Water Resources Division of Fiscal Services
P. 0. Box 942836
Sacramento, CA 94236-0001
Citv of Lodi
Sup l'
Signature
Thomas A. Peterson
City Manager
Print Name
e
Post Office Box 3006
Address
Lodi, California 95241-1910
Attest:
Alice M. Rei he
City Clerk
Approved as to form
Bob McNatt
E54(11-16-89) -5- City Attorney
Date: X% -Al
herein and made a part of this Contract. The Supplier accepts and agrees to
comply with all terms, provisions, conditions, and commitments of this
Contract, including all incorporated documents, and to fulfill all assur-
ances, declarations, representations., and statements made by the Supplier in
the application, documents,.amendments, and communications filed in support
of its request for Safe Drinking Water financing.
SECTION 3. ESTIMATE OF PROJECT COST
The reasonable cost of the Project is,estimated to be
$4,758.000
SECTION 4. LOAN AMOUNT
Pursuant to the California Safe Drinking Water Bond Law of 1988,
its applicable rules and regulations, and subject to the availability of
funds, the State will lend to the Supplier in accordance with the terms of
this Contract and amount not to exceed $4,758.000 A five percent
administrative fee will be added to the amount of loan funds disbursed as
part of the Loan Principal to be repaid by.the Supplier.
SECTION 5. SUPPLIER'S COST
The Supplier agrees to fund the difference between the estimate
of the project cost (Section 3) and the loan amount (Section 4). Such
Supplier's cost in the amount of $ -0- shall be expended
prior to the expenditure of State loan funds.
SECTION 6. REQUIREMENTS FOR DISBURSEMENT
By February 29. 1992 . the Supplier shall meet
all conditions precedent to the disbursement of money under this Contract,
including Basic Conditions Precedent under Article A-3 of the Standard
Conditions. Failure by Supplier to comply with this date may, at the option
of the State, result in termination of the Contract under Article A-6 of the
Standard Conditions.
SECTION 7. RATE OF INTEREST
The rate of interest to be paid by the Supplier shall be
3.41 percent per annum of--tife unpaid balance of the loan.
SECTION 8. WATER CONSERVATION
For a period of 20 years, which is the reasonably expected
life of the Project, Supplier shall undertake all reasonable efforts to
conserve water in a cost effective manner.
E54(11-16-89) -2-
��
EXHIBIT A
STATE OF CALIFORNIA
_.... _. THE RESOURCES AGENCY.
DEPARTMENT OF WATER RESOURCES
LOAN CONTRACT STANDARD CONDITIONS
ARTICLE A-1. DEFINITIONS
Whenever in this Contract the following terms are used, their
meaning shall be as follows unless the context clearly requires otherwise:
.__ State Department -of Health Services --The State of California
Department of Health Services or the local health agency that has
jurisdiction to issue the necessary water permit under the provisions of
Chapter 7 (commencing with Section 4010) of Part 1 of Division 5 of the
Health and Safety Code.
Contract --The Contract to which these Loan Contract Standard
Conditions are appended, which shall be considered a promissory note for the
purpose of meeting the Loan Security Requirements of Exhibit B.
Daps --Calendar days unless otherwise expressly indicated.
Month --Calendar months unless otherwise expressly indicated.
Year --Calendar year unless otherwise expressly indicated.
Project -'All work, -not incldding construction equipment, for the
construction, improvement, or rehabilitation of the domestic water system,
including water supply, treatment, works, storage facilities, and all or part
of a water distribution system proposed by the Supplier pursuant to the plans
and specifications that describe the plan of the Project approved by the
State Department of Health Services and all addenda and changes to the
foregoing documents approved by the State Department of Health Services.
Supplier --Any person, partnership, corporation, association, or
other -entity or political subdivision of the state which owns or operates a
domestic water system.
System --All facilities owned, under control of or operated by the
Supplier for the provision of piped water to the public for human
consumption, which may include any water supply, treatment, storage, or
distribution facilities.
Eligible Project --A project for the construction, improvement, or
rehabilitation of a domestic water system determined to be eligible under the
California Safe Drinking Water Bond Law.
E54(11-16-89) -Al-
Eligible Project Costs --Reasonable costs associated with an
eligible project including the engineering, legal, and administrative fees
associated with the Project, and also including those reasonable costs
incurred by the applicant to prepare the application and to establish
eligibility prior to or after the effective date of this Contract. Eligible
Project costs do not include:
(a) Operation and maintenance costs.
(b) Cost of providing water for industrial or agricultural use.
(c) Costs for purchase of equipment.
(d) Payment of principal or interest of existing indebtedness or
any interest payment unless:
(1) The debt is incurred after the issuance of a letter of
commitment of funds by the State; and
(2) The State agrees in writing to the eligibility of the
costs for reimbursement before the debt is incurred; and
(3) The purposes for which the debt is incurred are
otherwise Eligible Project Costs.
(e) Establishment of a reserve fund.
Treatment Works --Any devices or systems used in the treatment of
water supplies, including necessary lands, that render such supplies pure,
wholesome, and potable water for domestic purposes.
Loan Commitment --The maximum sum of money that the State agrees
to lend to the supplier under this Contract, not to exceed $5,000,000 plus
any administration fee.
Principal Amount of the Loan --The total amount disbursed to the
Supplier under the Contract, plus an administrative fee not to exceed five
percent, less any amount of such total amount disbursed that may have been
repaid or remitted to the State by the Supplier.
Term of Loan --The period of time between the date of first
disbursement of money to the Supplier and the date the Principal Amount of
the Loan is repaid in full".
Repayment Term --The period of time between the date of final
disbursement of money to the Supplier and the date the Principal Amount of
the Loan is repaid in full.
Fiscal Agent --A bank,-iTavings and loan, or any other financial
institution approved by the State, to which funds for the repayment of this
loan are deposited, or are under the control of, for the purpose of
disbursing repayments of the loan to the State according to the repayment
schedule referred to in Article A-9 of Exhibit A.
ARTICLE A-2. TERM OF CONTRACT
Subject to the provisions of Article A-3, this Contract shall
become effective on the date of its execution and shall remain in effect
until the Principal Amount of the Loan, all interest thereon, and any other
sums of money due to the State have been paid in full_
E54(11-16-89) -A2-
ARTICLE A-3....BASIC CONDITIONS.. PRECEDENT
The State shall have no obligation to disburse money under this
Contract unless and until:
(a) The Supplier provides a copy of a resolution passed by its
governing body accepting the loan, and designating a representative to
execute this Contract and to sign requests for disbursement of State funds.
(b) The Supplier demonstrates to the State's satisfaction the
proposed Project has the support of a majority of the affected community by
holding an election; or by holding a widely publicized public meeting pur-
suant to direction by the State; or by any other suitable, lawful method of
determining community support, at which public comments and questions are
received and answered. If Supplier determines that an election is not
required by law prior to Supplier's execution of this Safe Drinking Water
Bond Law loan contract, it shall transmit to the State a written opinion from
Supplier's counsel stating that no election is required and stating the legal
basis for Supplier's determination.
(c) The Supplier demonstrates the availability of sufficient
funds to complete the Project.
(d) All other sources of funds for the Project have been
utilized.
(e) The Supplier has satisfied the security provisions of
Article A-12.
(f) The Supplier has engaged the services of a Fiscal Agent under
an agreement approved by the State.
(g) The Supplier submits an initial budget of Eligible Project
Costs approved by the State Department of Health Services on a form provided
by the Department of Water Resources. The Supplier shall thereafter submit
to the State in writing any substantial changes in the budget. The Supplier
shall obtain written approval of changes from the State Department of Health
Services and the State before the changes are made.
(h) The Supplier demonstrates to the State's satisfaction that
the Supplier has and. -will contEAULr-to have sufficient water available at all
times and a right to use the water required to operate the Project through-
out the repayment period of the loan.
(i) The Supplier obtains all necessary permits required by other
State, federal and/or local agencies, including an Amended Water Permit from
the State or County agency which issucs your permit to operate a water
system. _
ARTICLE A-4. COMPLIANCE WITH LAWS, REGULATIONS, PERMIT REQUIREMENTS
The Supplier shall at all times comply with, and require its
subcontractors to comply with, all applicable federal and state laws, rules
and regulations, permits, and all applicable local ordinances, specifically
including, but not limited to, environmental, procurement and safety laws,
rules, regulations, permits, and ordinances.
E54(11-16-89) -A3-
ARTICLE A-5. LOAN DISBURSEMENTS BY STATE
(a) Cost Statements
After the Basic Conditions Precedent in Articles A-3 and A-4 are
met, the State will disburse the whole or portions of the loan commitment to
the .Supplier.following: receipt ,..from the Supplier of a statement or statements
of incurred Eligible Project Costs on forms provided by the State. Requests
for State funds shall be filed monthly or for such longer period as the State
and Supplier may mutually agree and the Supplier shall provide the following
information:
(1) A statement of the incurred Eligible Project Costs for work
performed in constructing the Project during ,the period identified in the
particular statement.
(2) A statement of other incurred Eligible Project Costs that
have been incurred for the Project during the period identified in the
particular statement, including, but not limited to, legal, engineering, and
administrative fees associated with the Project and reasonable costs of the
Supplier to prepare the application and establish eligibility.
After the State gives notice to the Supplier that the State has
determined that the Project has been completed or terminated, the Supplier
shall furnish a final statement of incurred Eligible Project Costs.
(b) Disbursement
Following the review by the State of each statement of costs, the
State will disburse to the Supplier the amount approved, subject to the
availability of funds. Any and all money disbursed to the Supplier under
this Contract and any and all interest earned by the Supplier on such money
shall be used solely to pay Eligible Project Costs.
(c) Withholding of Loan Disbursement by Supplier
The Supplier shall withhold not less than five percent (5.0%)
from any loan disbursement or the combination of loan disbursements until the
Project is determined to be completed pursuant to Article A-7.
ARTICLE A-6. WITHHOLDING OF LOAN --DISBURSEMENTS BY STATE
(a) Conditions for Withholding
If the State determines that the Project is not being carried out
substantially in accordance with the provisions of this Contract, or if the
State determines that the Supplier has failed in any other respect to
substantially comply with the provisions of this Contract, and if the
Supplier does not remedy any such failure to the State's satisfaction, the
State may withhold from the Supplier all or any portion of the loan
commitment and take any other action that it deems necessary to protect its
interests.
(b) Withholding Entire Loan Commitment
If the State notifies the Supplier that it has decided to with -
E54(11 -16-89) -A4-
hold all of the loan commitment from -the Supplier pursuant to Subdivision (a)
of this Article, this Contract shall terminate upon receipt of such notice by
the Supplier and shall no longer be binding on either party hereto.
(c).Withholding Balance of Loan Commitment
Where_ a. portion of the loan commitment has been disbursed to the
Supplier and the State notifies the Supplier that it has decided to withhold
the balance..of.the..loan commitment -from the, Supp 1ier-pursuant. to Subdivision
(a) of this Article, the portion that has been disbursed shall thereafter be
repaid forthwith to the State with interest as directed by the State.
Refusal of the Supplier to so repay may, at the option of the State, be
considered a material. breach. of contract and may be treated as default under
Article B-5 of Exhibit B.
ARTICLE A-7. TIMING OF PROJECT
(a) Project Completion Date
The Supplier shall cause the project to be completed not later
than January 31. 1993 . provided that said date for completion
may be extended upon written approval of the State.
(b) Project Pursuant to Project Plans and Specifications
The Project shall be constructed in accordance with the final
plans and specifications approved by the State Department of Health Services,
together with any revisions thereof approved by the State Department of
Health Services.
(c) Determination of Project Completion
For the purposes of this Contract, the Project shall be
considered to be completed or terminated when so determined by the State.
(d) Competitive Bidding
Any contract let for the construction of the Project, or any part
thereof, which is in excess of $10,000, or which is in excess of any smaller
amount for which bids are required under the enabling authority of the
Supplier, shall be -.let by competitive bid procedures which assure award of
the Contract to the lowest responsible bidder, except as may be otherwise
authorized in writing by the State. Requests for approval of competitive
bidding, for award of a contract to other than the low bidder, or for a
supplier to proceed on the basis of force account or day labor, or for any
other procedure which deviates from the principle of competitive bidding
shall be submitted in writing to the State before the procedure is
implemented. State's prior written approval of the procedure will be based
on compliance with applicable laws and policies. The State expressly
reserves the right to approve or disapprove of such requests.
(e) Sign Referring to Safe Drinking Water Bond Law Financing
During construction of the Project, the Supplier shall cause a
sign to be installed at a prominent location which shall include a statement
that the Project is financed under the California Safe Drinking Water Bond
E54(11-16-89) -AS-
Law.Program administered by the State of California, Department of Water
Resources, and the State Department of Health Services.
(f) Audit Requirement
Pursuant to Government Code Section 10532, the contracting
parties shall .be subject to the examination. -and audit of the State and the
State Auditor General for a period of three years after final payment under
this.,Contract-with respect.to-all matters connected- with- .the. performance of
this Contract, including, but not limited to, the cost of administering this
Contract. All records of the Supplier or subcontractors shall be preserved
for this purpose for at least three years after completion of the Project.
ARTICLE A-8. STATEMENT OF PRINCIPAL AMOUNT OF LOAN
(a) Remittance of Unexpended Funds
The Supplier, within a period of thirty (30) days from the final
disbursement from the State to the Supplier of loan funds, shall remit to the
State any unexpended funds that were disbursed to the Supplier under this
Contract and were not needed to pay Project Costs incurred.
Unexpended funds remitted to the State under this subdivision
shall not be considered to be.a repayment of any part of the loan, but shall
be deemed to be a return to the State of part of the funds disbursed and a
reduction in the total amount loaned to the Supplier pursuant to this
Contract.
(b) Transmission of Statement to Supplier
Within sixty (60) days after final disbursement of money, the
State shall transmit to the Supplier a written statement setting forth the
Principal Amount of the Loan consisting of all disbursements plus an
administrative fee not to exceed five percent to be repaid by the
Supplier to the State pursuant to Article A-9 thereof.
ARTICLE A-9. REPAYMENT OF PRINCIPAL AMOUNT OF LOAN
(a) Re�avment Terms
The. Supplier shall -make semiannual payments to the State for a
period not to exceed 20 years as set forth in the following repayment
schedule, entitled "Estimated Schedule of Loan Repayment", until the
Principal Amount of the Loan is repaid in full, provided that in any event
the final semiannual payment shall be in an amount equal to the then unpaid
portion of the Principal Amount of the Loan. The first amount of the
semiannual payment shall be due and payable on October 1. 1993 The
remaining amounts shall be made semiannually thereafter commencing on
April 1, 1994 until the Principal Amount of the Loan is -repaid in full;
provided, however, as to the foregoing that the Supplier shall only be
required to make such payments from any funds which accrue in the special
fond �elititled SafeOD i king, itey,Fffd, established by Resolution No.
adopted o' into which are deposited
the collected assessments or user charges defined in Article B-2 of Exhibit
B. Supplier shall not be obligated to make such payments from any other
source of funds, including the Supplier's General Fund.
E54(11-16-89) -A6-
s
Estimated schedule of Repayment of the Loan
City of Lodi
E54402
-A7-
Loan Amount:
54,758,000
5% Administrative Fee:
1237,900
_
Principal:
54,995,900
Interest:
3.4100%
Term:
20 Years
Repayment
Schedule' - -
-
Principal
Payment
Semiannual
Interest
Principal
Principal
Reduction
No.
Payment
Balance
Factor
------- --------------
---------------------------------------------
--------------------
S4,995,900.00
1
$173,313.37
585,180.10
$88,133.27
54,907,766.73
1.764112%
2
5173,313.37
583,677.42
589,635.95
54,818,130.78
1.794190%
3
5173,313.37
582,149.13-
$91,164.24
54,726,966.54
1.824781%
4
$173,313.37
$80,594.78
$92,718.59
54,634,247.95
1.855894%
5
$173,313.37
579,013.93
$94,299.44
$4,539,948.51
1.887536%
6
1173,313.37
577,406.12
595,907.25
54,444,041.26
1.919719%
7
$173,313.37
575,770.90
$97,542.47
54,346,498.79
1.952451%
8
$173,313.37
$74,107.80
599,205.57
$4,247,293.22
1.985739%
9
$173,313.37
572,416.35
5100,897.02
54,146,396.20
2.019597%
10
5173,313.37
570,696.06
$102,617.31
54,043,778.89
2.054030%
11
5173,313.37
568,946.43
$104,366.94
53,939,411.95
2.089052%
12
5173,313.37
567,166.97
5106,146.40
$3,833,265.55
2.124670%
13
$173,313.37
$65,357.18
5107,956.19
53,725,309.36
2.160896%
14
5173,313.37
563,516.52
5109,796.85
$3,615,512.51
2.197739%
15
5173,313.37
$61,644.49
5111,668.88
$3,503,843.63
2.235210%
16
$173,313.37
559,740.53
5113,572.84
53,390,270.79
2.273321%
17
$173,313.37
$57,804.12
5115,509.25
53,274,761.54
2.312081%
18
5173,313.37
$55,834.68
5117,478.69
53,157,282.85
2.351502%
19
5173;313.37
553,831.67
$119,481.70
53,037,801.15
2.391595%
20
$173,313.37
$51,794.51
$121,518.86
52,916,282.29
2.432371%
21
$173,313.37
149,722.61
5123,590.76
$2,792,691.53
2.473844%
22
$173,313.37
$47,615.39
$125,697.98
$2,666,993.55
2.516023%
23
1173,313.37
$45,472.24
1127,841.13
$2,539,152.42
2.558920%
24
$173,313.37
-$43,292.55
$130,020.82
12,409,131.60
2.602551%
25
1173,313.37
-$41,075.69
..5132,237.68
52,276,893.92
2.646924%
26
$173,313.37
$38,821.04
5134,492.33
12,142,401.59
2.692054%
27
1173,313.37
$36,527.95
1136,785.42
$2,005,616.17
2.737953%
28
1173,313.37
$34,195.76
1139,117.61
11,866,498.56
2.784636%
29
1173,313.37
$31,823.80
$141,489.57
11,725,008.99
2.832113%
30
$173,313.37
$29,411.40
5143,901.97
$1,581,107.02
2.880401%
31
$173,313.37
$26,.957.87
$146,355.50
$1,434,751.52
2.929512%
32
$173,313.37
124,462.51
1148,850.86
$1,285,900.66
2.979461%
33
$173,313.37
121,924.61 --4131,388.76
11,134,511.90
3.030260%
34
$173,313.37
$19,343.43
1153,969.94
1980,541.96
3.081926%
35
$173,313.37
$16,718-24
5156,595.13
1823,946.83
3-134472%
36
$173,313.37
$14,048.29
5159,265.08
$664,681.75
3.187916%
37
$173,313.37
$11,332.62
5161,980.55
$502,701.20
3.242269%
38
$173,313.37
$8,571.06
1164,742.31
$337,958.89
3.297550%
39
$173,313.37
15,762.20
$167,551.17
$170,407.72
3.353774%
40
$173,313.17
$2,905.45
$170,407.72
$0.00
3.410955%
-A7-
(b) Advance Payment Option
The Supplier shall have the option of paying in advance on any
semiannual payment due date all or any part of the unpaid portion of the
Principal Amount of the Loan, provided that any interest accrued hereunder
shall be paid at the same time, and, provided further, that any such payment
shall not relieve the Supplier of its obligations to make payments in the
amount and at the time specified in Subdivision (a) of this Article until the
Principal Amount of the Loan_is_repaid.in full.
ARTICLE A-10. INTEREST PAYMENTS
The Supplier shall pay interest to the State at the rate
specified in Section 7 of Contract Special Provisions on the unpaid balance
of the loan. Interest on the principal shall not be deferred.
The Department will invoice the Supplier semiannually for
interest accrued during the Project construction period. The interest amount
of each disbursement shall be calculated as the fraction x/182.5 times the
interest rate, where x is the number of calendar days remaining in the
semiannual period from the date on which the disbursement was made. Interest
accrued during the construction period iss due and payable within 30 days of
the date of the invoice.
. Upon completion of the Project, interest and principal shall be
due and payable semiannually until the Principal Amount of the Loan is repaid
in full.
ARTICLE A-11. DELINQUENCY IN INTEREST PAYMENT
Upon_ every amount of interest money required to be paid by the
Supplier to the State pursuant to Article A-10 of this Contract which remains
unpaid after it -becomes due and payable, interest shall accrue at the rate of
one percent (1.0%) per month of the amount of such delinquent payment from
and after the due date until it is paid, and the Supplier hereby agrees to
pay such interest, provided that no such interest shall be charged to or be
payable by the Supplier under this article unless such delinquency continues
for more than thirty (30)..days. Delinquency for a period of one year may, at
the discretion of the State, be considered a material breach of contract and
may be treated as default under Article B-5 of Exhibit B.
ARTICLE A-12. SECURITY REQUIREMENTS
The Supplier shall meet the security requirements provisions set
forth in Exhibit B, "Loan Contract Security Requirements", to adequately
protect the interest of the State during the term of the loan.
ARTICLE A-13. PAYMENT CAPACITY IMPAIRMENTS
(a) Transfer of Water Outside Service Area
No sale or other transfer of water made available by the
constructed project shall be made outside the Supplier's existing service
area which, in the judgement of the State, would materially impair the
Supplier's capacity to make payments to the State as provided for in this
Contract. The Supplier shall notify the State as promptly as feasible of all
E54(11-16-89) -A8-
proposed sales or_other.transfers of Project water outside the Supplier's
service area.
(b) Changes in Supplier's Organization
The Supplier shall notify the State as promptly as feasible of
any proposed change in the Supplier's organization or service area. While
this Contract is in effect, no changes shall be made in the organization of
the Supplier without permission of the State. The Supplier shall take no
action which may materially impair the Supplier's capacity to make payments
to the State.
ARTICLE A-14. ACCOUNTING AND DEPOSIT OF LOAN DISBURSEMENTS
(a) Separate Accounting of Loan Disbursements and Interest;
Records
The Supplier shall account for the money disbursed pursuant to
this Contract separately from all other Supplier's funds. The Supplier shall
maintain audit and accounting procedures that are in accordance with
generally accepted accounting principles and practices, consistently applied.
The Supplier shall keep complete and accurate records of all receipts,
disbursements, and interest earned on expenditures of such funds. The
Supplier shall require its contractors or subcontractors to maintain books,
records, and other documents pertinent to their work in accordance with
generally accepted accounting principles and practices. Records are subject
to inspection by the State at any and all reasonable times.
(b) Disposition of Money Disbursed
All money disbursed pursuant to this Contract shall be deposited,
administered, and accounted for pursuant to the provisions of law applicable
to the Supplier.
(c) Interim and Final Audits
The State reserves the right to conduct an audit at any time
between the execution of this Contract and the completion of the Project.
After completion of the Project, the State may require the Supplier to
conduct a final audit, at the Supplier's expense, such audit to be conducted
by and a report prepared by an-in89pbndent Certified Public Accountant.
Failure or refusal by Supplier to comply with this provision
shall be considered a substantial failure to comply with this Contract, and
the State may elect to pursue any remedies provided in Article A-7 or take
any other action it deems necessary to protect its interests.
ARTICLE A-15. REPORTS ON EXPENDITURE AND PROJECT CONSTRUCTION
During the planning and construction phases, the Supplier agrees
to provide to the State an annual summary of the information required by
Articles A-5 and A-14.
E54(11-16-89) -A9-
0-1
ARTICLE A-16. INSPECTIONS OF PROJECT BY STATE AND STATE DEPARTMENT OF HEALTH
SERVICES
The State and -State Department of Health Services shall have the
right to inspect the work being performed at any and all reasonable times
during the term of the Contract. This right shall extend to any subcon-
tracts -,...and Supplier shall include.provisions ensuring such access in all its
contracts or subcontracts entered into pursuant to its Contract with the
State.. --_
Supplier shall notify the State and the State Department of
Health Services of the final inspection of the Project or any component by
the Supplier at least ten (10) days prior to the date set for the inspection.
ARTICLE A-17. PROHIBITION AGAINST DISPOSAL OF PROJECT WITHOUT STATE
PERMISSION
The Supplier shall not sell, abandon, lease, transfer, exchange,
mortgage, hypothecate, or encumber in any manner whatsoever all or any
portion of any real -or other property necessarily connected or used in
conjunction with the Project, or with the Supplier's service of domestic
water, without prior permission of the State. Supplier shall not take any
action, including but -not limited to actions relating to user fees, charges
and assessments, that could adversely affect the ability of the Supplier to
make timely payments or to otherwise meet its obligations under this
Contract, without prior written permission of the State. The State may
require that the proceeds from the disposition of any real or personal
property be remitted to the State to be applied to Supplier's indebtedness
under this Contract.
ARTICLE A-18. NONDISCRIMINATION CLAUSE
During the performance of this contract, the supplier, its
contractor and subcontractors shall not deny the Contract's benefits to any
person on the basis of religion, color, ethnic group identification, sex,
age, physical or mental disability, nor shall they discriminate unlawfully
against any employee or applicant for employment because of race, religion,
color, national origin, ancestry, physical handicap, mental disability,
medical condition, marital status,.age, or sex. Supplier shall insure that
the evaluation and treatment of employees and applicants for employment are
free of such discrimination.
Supplier, its contractors and subcontractors shall comply with
the provisions of the Fair Employment and Housing Act (Government Code,
Section 12900 et seq.), the regulations promulgated thereunder (California
Code of Regulations, Title 2, -Section 7285.0 et seq.), the provisions of
Article 9.5, Chapter 1, Part 1, Division 3, Title 2 of the Government Code
(Government Code, Sections 11135-11139.5) and the regulations or standards
adopted by the awarding State Agency to implement such article.
Supplier, its contractors and subcontractors shall give written
notice of their obligations under this clause to labor organizations with
which they have a collective bargaining or other agreement.
Supplier shall include the nondiscrimination and compliance
provisions of this clause in all subcontracts to perform work under the
contract.
E54(11-16-89) -A10-
The Supplier's signature on this Contract shall constitute a
certification under the penalty of perjury under the laws of the State of
California that the Supplier has, unless exempted, complied with the
nondiscrimination program requirements of Government Code, Section 12990, and
Title 2, California Code of Regulations, Section 8103.
ARTICLE A-19. WORKERS' COMPENSATION CLAUSE
Supplier affirms that it is aware of the provisions of Section
3700 of the California Labor Code, which requires every employer to be
insuredagainst liability for workers' compensation or to undertake self-
insurance in accordance with the provisions of that code, and Supplier
affirms that it will comply with such provisions before commencing the
performance of the work under this Contract and will make its contractors and
subcontractors aware of this provision.
ARTICLE A-20. SUCCESSORS AND ASSIGNS
This Contract and all of its provisions shall apply to an bind
the successors and assigns of the parties hereto. No assignment or transfer
of this Contract or any part hereof, rights hereunder, or interest herein by
the Supplier shall be valid unless and until it is approved by the State and
made subject to such reasonable terms and conditions as the State may impose.
ARTICLE A-21'. STATE TO BE HELD HARMLESS
The Supplier agrees to indemnify the State of California,
Department of Water Resources and the State Department of Health Services,
and their officers, agents, and employees against and to hold the same free
and harmless from any and all claims, demands, damages, losses, costs,
expenses, or liability due or incident to, either in whole or in part, and
whether directly or indirectly, the Project.
ARTICLE A-22. REMEDIES NOT EXCLUSIVE
The use by either party of any remedy specified herein for the
enforcement of this Contract is not exclusive and shall not deprive the party
using such remedy of, or limits.the application of, any other remedy provided
by law.
ARTICLE A-23. AMENDMENTS
This Contract may be amended at any time by mutual agreement of
the parties, except insofar as any proposed amendments are in any way
contrary to applicable law. Requests by the Supplier for amendments must be
in writing stating the amendment request and tha reason for the request.
ARTICLE A-24. OPINIONS AND DETERMINATIONS
Where the terms of this Contract provide for action to be based
upon opinion, judgement, approval, review, or determination of either party
hereto, such terms are not intended to be and shall never be construed as
permitting such opinion, judgement, approval, review, or determination to'be
arbitrary, capricious, or unreasonable.
E54(11-16-89) -All-
ARTICLE A-25. CONTRACTING OFFICER OF THE STATE
The contracting officer of the State shall be the Director of the
Department of Water Resources of the State of California and his successors,
.or .the.ir. duly. authorized. representatives . The -contracting officer shall be
responsible for all discretionary acts, opinions, judgements, approvals,
reviews, and determinations required by the State under the terms of this
Contract.
ARTICLE A-26. WAIVER OF RIGHTS
It is the intention of the parties hereto that from time to time
either party may waive any of its rights under this Contract unless contrary
to law. Any waiver by either party hereto of rights arising in connection
with this Contract shall not be deemed to be a waiver with respect to any
other rights or•matters.
ARTICLE A-27. NOTICES
All notices that are required either expressly or by implications
to be given by one party to the other under this Contract shall be signed for
the State by its contracting officer and for the Supplier by such officers,
as from -time to time, it may authorize in writing to so act. All such
notices shall be deemed to have been given if delivered personally or if
enclosed in a properly addressed postage -prepaid envelope and deposited in a
United States Post Office for delivery by registered or certified mail.
ARTICLE A-28. INSPECTION OF -BOOKS, RECORDS, AND REPORTS
During regular office hours, each of the parties hereto and their
duly authorized representatives shall have the right to inspect and to make
copies of any books, records, or reports of either party pertaining to this
Contract or matters related hereto. Each of the parties hereto shall
maintain and shall make available at all times for such inspection accurate
records of all its costs, disbursements, and receipts with respect to its
activities under this Contract. Failure or refusal by Supplier to comply
with this provision shall be considered a substantial failure to comply with
this -Contract, and the State may withhold disbursements to the Supplier or
take any other action it deems necessary to protect its interests. -
ARTICLE A-29. SUIT ON CONTRACT`
Each of the parties hereto may sue and be sued with respect to
this Contract.
ARTICLE A-30. CLAIMS DISPUTE.CLAUSE
Any claim that Supplier may have regarding the performance of
this agreement including, but not limited to, claims for additional
compensation or extension of time, shall be submitted to the Director,
Department of Water Resources, within thirty days of its accrual. State and
Supplier shall then attempt to negotiate a resolution of such claim and
process an amendment to this agreement to implement the terms of any such
resolution.
E54(11-16-89) -Al2-
f
EXHIBIT B
LOAN CONTRACT SECURITY REQUIREMENTS
ARTICLE -B-1. NO PRIORITY FOR -ADDITIONAL LOANS
The Supplier agrees to.incur no additional indebtedness having
any priority in payment of principal or interest or pledge of revenues or
facilities or equipment in existence at the date of this Contract or to be
constructed or obtained under terms of this Contract without obtaining prior
written consent of the State.
ARTICLE B-2. RATES AND CHARGES
The Supplier agrees that it will levy and collect assessments or
user charges as may -be necessary to operate and to maintain the Project and
to meet the payments of the loan when the same becomes due and if, for any
reason, gross revenues prove insufficient to service the loan contract,
Supplier agrees to raise sufficient funds through increased user charges or
assessments or any other legal means available to it to meet loan payments
and to operate and to maintain the Project.
ARTICLE B-3. PERFORMANCE AND ASSURANCES
Supplier agrees to faithfully and expeditiously perform or cause
to be performed all Project work as described in'the final plans and
specifications as submitted or as later amended and approved by the State
Department of Health Services under this Contract and to apply State funds
received only to Eligible Project Costs and to operate and maintain the
Project in accordance with applicable provisions of the law. In the event
the State finds it necessary to enforce this provision or any right of power
under this Contract in the manner provided by law, Supplier agrees to pay all
costs incurred by the State including, but not limited to, reasonable
attorneys' fees, legal expenses, and costs.
ARTICLE B-4. SECURITY INTEREST
The Supplier agrees to grant to the State a security interest in
both real and personal property as the State determines is reasonably
necessary to secure payment of Supplier's obligations. The Supplier shall
execute any and all documents feq-aired by the State to create such a security
interest, including any amendments, notifications, or new documents as may be
reasonably necessary to maintain, preserve, and protect the State's interest
in the property.
ARTICLE B-5. DEFAULT PROVISIONS
Supplier will be in default under this agreement -if any of the
following occur:
(1) Failure to pay any installment when due, or the entire
indebtedness to the State when due at the designated due date, on accelerated
maturity, or otherwise;
(2) Failure to make any remittances required by this Contract;
(3) Substantial breach of this agreement, or any supplement or
amendment to it, or any other agreement between Supplier and the State
E54(11-16-89) -B1-
evidencing or securing Supplier's obligations;
(4) Making any false warranty, representation, or statement with
respect to this Contract;
(5) Loss, theft, or damages to any collateral;
(6) Seizure of, or levy on any collateral; and/or
(7) Dissolution or cessation of operations by Supplier, termina-
tion of Supplier's existence, insolvency of Supplier, or from filing of a
voluntary of involuntary bankruptcy petition by or on behalf of Supplier.
When an event of default occurs, the State may do any or all of
the following:
(1) Declare the Supplier's obligations immediately due and
payable, with demand or notice to Supplier, which Supplier expressly waives;
(2) Terminate any obligation to make future payments to Supplier;
(3) Exercise all rights and remedies available to a secured
creditor after default, including, but not limited to, the rights and
remedies of secured creditors under the California Uniform Commercial Code;
(4) Perform any of Supplier's obligations under this Contract for
Supplier's account;
(5) Take over all of Supplier's property and operate the
Supplier's water system at its discretion; and
(6) Take any other action which it deems necessary to protect its
interests.
Supplier agrees that any remedy provided in this Contract is in
addition to and not in derogation of any other legal or equitable remedy
available to the State as a result of a breach of contract by the Supplier,
whether such breach occurs before or after completion of the project.
No waiver by the State of any breach or default will be a waiver
of any breach or default occurellfg"later. A waiver will be voluntary if
signed by the State or its authorized agent.
ARTICLE B-6. RESERVE FUND
The Supplier agrees to provide for the accumulation of necessary
reser—es in accordance with Section 11 of this Contract to assure that funds
will be available to make the semiannual payments when due. A reserve of two
semiannual payments will be required to be accumulated during the first ten-
year period for all repayment methods except those based on the quantity of
water used, for which a reserve of four semiannual payments shall be
accumulated during the first ten years. This reserve shall be maintained at
this level thereafter with the withdrawals being replaced at the same
original rates until the reserve is returned to the maximum amount. The
reserve fund shall be maintained and administered by the Fiscal Agent.
E54(11-16-89) -B2-
JAN 2 1 1992
Mr. Thomas A. Peterson, City Manager
City of Lodi
Post office Box 3006
Lodi, California 95241-1910
Mr. Homer Vaughn, Acting District Engineer
Stockton District
Office of Drinking Water
Department of Health Services
31 E. Channel Street
State Building, Room 270
Stockton, California 95202
f
STATE OF CALIFORNIA—THE RESOURCES AGENG. PETE WILSON, Governor
DEPARTMENT OF WATER RESOURCES
1416 NINTH STREET, P.O. BOX 942836
SACRAMENTO, CA 94236.0001
(916) 445-9248
To: Loan and Grant Contractors
Safe Drinking Water Bond Law Program
Under the Safe Drinking Water Bond Law Program you have signed a contract
for a loan or grant with the State of California, Department of Water
Resources. Your DWR contract reflects your estimated total project or
study costs, the amount of State funding, and critical dates for your
completion of contract requirements and of the project or study. The
study or project elements eligible for State funding have been defined to
DWR by the Department of Health Services in a written certification.
Unanticipated circumstances and events may impact the scope and terms of
your DWR contract, and may require that you request a contract amendment.
You should maintain a suspense file for critical dates and other variables
within your DWR contract so that you can request consideration of an
amendment to the contract with sufficient lead time for review and approval
by both DWR and DHS.
At the earliest indication that there may be a need for a contract
amendment you must contact by phone DWR staff in Sacramento, and follow up
with a written request to DWR. Your request must identify the contract
terms which may need amendment and include full justification. You must
indicate whether any elements of your approved project are expected to
change. Discuss alternative measures you have considered. Please follow
the euidelines on the reverse.
After receipt of your written request for a contract amendment, DWR will
ask for the DHS District Engineer's comments and recommendation. The
contract amendment will be issued by DWR, then executed by your
organization and DWR for attachment to your executed contract.
If you are requesting an increase in State funding, you must indicate the
source of r:payment of the additional loan. The bond law requires the
State to make a loan to the extent an applicant is able to repay a loan.
Grants may be awarded to public agencies only, after loan capacity has been
exhausted, up to the limits of the bond law.
If there are questions call your DWR contact person in the Bond Financing
and Administration Office at (916) 653-9497.
BFA 612 (9-11-91)
State of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.
Contact Person:
Periodic Estimate No.: for Period
DEPARTMENT OF WATER RESOURCES
BUDGET AND EXPENDITURE SUMMARY
19 , to
Do to
DWR Contract No.:
Telephone:
, 19
The Resources Agency
Page-of-
Do
ageof
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
INITIAL SUBMISSION ONLY: Reviewed by Registered Civil Engineer RCE No. Date
SUBMIT: One Copy to Department of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236-0001
State of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.:
Contact Person:
Periodic Estimate No.: for Period
DEPARTMENT OF WATER RESOURCES
BUDGET AND EXPENDITURE SUMMARY
, 19 , to
Do to .
DWR Contract No.:
_Telephone:_
, 19
The Resources Agency
Page of
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
+Yr,
SUB TOTAL THIS PAGE
SUB TOTAL PAGE
SUB TOTAL PAGE
TOTAL
INITIAL SUBMISSION ONLY: Reviewed by Registered Civil Engineer RCE No. Date
SUBMIT: One Copy to Department of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236-0001
Stote of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.:
Contact Person:
Periodic Estimate No.: for Period
DEPARTMENT OF WATER RESOURCES
BUDGET AND EXPENDITURE SUMMARY
19 , to
Do to ,
DWR Contract No.:
Telephone:,
, 19
The Resources Agency
Page of
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
1
SUB TOTAL THIS PAGE
SUB TOTAL PAGE
SUB TOTAL PAGE
TOTAL
INITIAL SUBMISSION ONLY: Reviewed by Registered Civil Engineer RCE No. Date
SUBMIT: One Copy to Department of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236-0001
State of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.:_
Contact Person:
DEPARTMENT OF WATER RESOURCES
BUDGET AND EXPENDITURE SUMMARY
Periodic Estimate No.: for Period , 19 , to
Date.
DWR Contract No.:
—Telephone:—
,
elephone:_, 19
The Resources Agency
Page of
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
4
INITIAL SUBMISSION ONLY: Reviewed 6y Registered Civil Engineer
SUBMIT: One Copy to Department of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236-0001
RCE No. Date
State of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.:
Contact Person:
Periodic Estimate No.: for Period
DEPARTMENT OF WATER RESOURCES
BUDGET AND EXPENDITURE SUMMARY
19 , to
Do to
DWR Contract No.:
Telephone: _
, 19
The Resources Agency
Poge of
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
w�
SUB TOTAL THIS PAGE
SUB TOTAL PAGE
SUB TOTAL PAGE
TOTAL
INITIAL SUBMISSION ONLY: Reviewed by Registered Civil Engineer RCE No. Date
SUBMIT: One Copy to Department of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236.0001
INSTRUCTIONS FOR DWR 4133 A
(To be filled out by the Public Agency for periodic payment)
PART A:
Public Agency: The name should be identical to the name used in the contract with the Department of Water Resources.
Address and Telephone Number: Self-explanatory.
DWR Contract Number: The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4135, Budget and Expenditure Summary.
Attachment Number: Numerically identify each attachment, corresponding to DWR 4133 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds still available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE IN THE BLOCKS MARKED "FOR DWR USE".
If additic)IIA space is required. USS a Second 1 AVIV 4 1:55 :1 and identify it in the upper right hand Curn(T.' oUll ( N I.1' the last ll11'R 41:15 A.
INSTRUCTIONS FOR PAR'T'IAL PAYMENT ESTIMATE, DWR 1135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identify each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Price.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C:
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. .Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D:
Part D, 1, 2. and :3 must be signed.
Part D. 2 i, always signed by a registered civil engineer unless otherwise approved in writing by DW l{. Part D, ,3 is ahvnys signed by
the Public Agency.
All signatures on original set of the estimate must be original signatures. Additional copies mai• f.e made from this set. Please
submit the original and four copies of the entire estimate package to the Department of Water Resource,, Bond Financing and
Administration, 11. 0. Box 942836, Sacramento, CA 9.1236.0001.
DWR 413:A i,Backi ;New 6/87)
State of California C DEPARTMENT OF WATER RESOURCES
Proposition PERIODIC ESTIMATE FOR PARTIAL PAYMENT
GENERAL OBLIGATION LOAN/GRANT
PART A (See Instructions on Reverse Side)
Name of Public Agency
Address:
Telephone No.:
Periodic Estimate No.
PART B — Expenditure Summary
for Period
DWR
Contract No.:
, 19_, to
The Resources Agenc,.
Page of
M
BUDGET
ATTACH-
PROJECT
STATE
LINE TEM NO.
MENTNO
DESCRIPTION
EXPENDITURES
FUNDS REQUESTED
PART C — Totals
Total this
1
periodic estimate
Total all prior
2
periodic estimates
3
Total periodic ezpendi-
tures to date
(rOR DWR USE ONLY)
(I . 2 above
Total retention this
Amount of thisS
Patna; Payment
4
periodic estimate
PAYMENT APPROVED:
Total retention oil prior
5
periodic estimates
6
Total retention to date
(4
AUTHORIZED SIGNATURE
OEPARTMENT OF WATER RESOURCES
+ S obove)
Work Order N o .
7
DWR Contract Amount
Dare Paid
Total Funds obligated'"
8
(3 + 6 above)
Claim No.
9
Funds still available"
-
(7 - 8 above)FOR
DWR 'JSE
S'J RN AM= -
DWR a135.A
JUbh11 I : Uriginal and tour copies to the Department of Water Resources.
.� _� 6''371
INSTRUCTIONS FOR DWR 4135 A
(To be filled out by the Public Agency for periodic payment)
PART A:
Public Agency: The name should be identical to the name used in the contract with the Department of Water Resources.
Address and Telephone Number: Self-explanatory.
DWR Contract Number: The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4133, Budget and Expenditure Summary.
Attachment Number: Numerically identify each attachment, corresponding to DWR 4135 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds still available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE IN THE BLOCKS MARKED "FOR DWR USE".
If aclditiollal .pace i, re(Juired. use a second I )WR 4 t:t.i e\ and identify it Ill the upper rig lit hand cUrnel'. I'utal 0N[N the last DWR .41:35 A.
INSTRUCTIONS FOR PARTIAL PAYMENT ESTIMATE, DWR 4135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identify each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Price.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C:
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D:
Part 1), 1, 2, and :3 must lie signed.
Part 1). 2 is always signed by a registered civil engineer unless otherwise approved in writing by DWR. Part D,:3 is ahvays signed by
the Public Ag;encc.
All signatures on original set of the estimate must be original signatures. Additional copies may I,e inade from this set. Please
submit the original and four copies of the entire estimate package to the Department of Water Resources, Bond Financing; and
:Administration, P. 0. Box 942836, Sacramento, CA 91236-(H)0I.
GWR 4135A .Back) (Ne- 6 871
State of California
Proposition_
PART A
Name of Public Agency
Address:
DEPARTMENT OF WATER RESOURCES
PERIODIC ESTIMATE FOR PARTIAL PAYMENT
GENERAL OBLIGATION LOAN/GRANT
(See Instructions on Reverse Side)
Telephone No.:
Periodic Estimate No. for Period
PART B — Expenditure Summary
DWR
Contract No.:
, 19_, to
The Resources Agenc
Page _ of —
19
BUDGET
LINE
TEM NO.
ATTACH-
ENT NO
DESCRIPTION
PROJECT
EXPENDITURES
STATE
FUNDS REQUESTED
PART C — Totals
Total this
1
periodic estimate
2
Total all prior
periodic estimates
3
Total
tures to date expendi-
1 + 2 above
!FOR DWR USE ONLY)
4
Total retention this
periodic estimate
-
Amount of this5
Po,I,al Payment
PAYMENT APPROVED:
5
Total retention all prior
periodic estimates
1
V
Total retention to date
(4 - S above)
AUTHORIZED SIGNATURE
DEPARTMENT OF WATER RESOURCES
O,de, No.
DWR Contract Amount
Dare Pa,dobligatedecev„.
g
Total funds
(3 + b above)
<,gc,:�r•.: a.a.
=
9
Funds still ovailable
(7 - 8 above)
Claim No.
,OR DWR USE
SU RN A'A E:
:)'NR 4135A ;New 627; JUbMi I : Urlginal and tour copies to the Department of Water Resources.
INSTRUCTIONS FOR DWR 4135 A
(To be filled out by the Public Agency for periodic payment)
PART A:
Public Agency: The name should be identical to the name used in the contract with the Department of Water Resources.
Address and Telephone Number: Self-explanatory.
DWR Contract Number: The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4135, Budget and Expenditure Summary.
Attachment Number: Numerically identify each attachment, corresponding to DWR 4135 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds still available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE. IN THE BLOCKS MARKED "FOR DWR USE".
If additional space is rr(yuircd, Lis,—.1. Iecontl 1)11'li 4 V5 A and identit'v it in the upper right hand corner. Total ONLY' the last DWR 4135 A.
INSTRUCTIONS FOR PARTIAL PAYMENT ESTIMATE, DWR 4135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identify each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Price.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C:
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D:
Part D, 1, 2, and:3 must lie signed.
Part D. 2 is always signed by a registered civil engineer unless otherwise approved in writing by DWR. fart D, 3 is nlivays signed by
the Public agency.
All signatures on original set of the estimate must lie original signatures. Additional copies may he made from this set. Please
submit the original and four copies of the entire estimate package to the Department of Witter Resources, Bond Financing and
Administration, P. O. Box 942836, Sacramento, CA 94236-0001.
DWR 4135A .Back; :New 6%87)
State of California
Proposition
PART A
Name of Public Agency
Address:
Telephone No.:
Periodic Estimate No.
PART B — Expenditure Summary
r
DEPARTMENT OF WATER RESOURCES
PERIODIC ESTIMATE FOR PARTIAL PAYMENT
GENERAL OBLIGATION LOAN/GRANT
(See Instructions on Reverse Side)
for Period
DWR
Contract No.:
, 19_, to
The Resources Agenr
Page_ of
M
SUOGET
LIME
ATTACH.
PROJECT
STATE
TEM NO.
MENTNO
DESCRIPTION
EXPENDITURES
FUNDS REQUESTED
PART'C — Totals
Total this
periodic estimate
Total oil prior
periodic estimates
3
l periodic expendi-
tures to date
(FOR DWR USE ONLY)
1 . 2 above
retention this
-
Amount of this STotal
Partial Payment
4
periodic estimate
PAYMENT APPROVED:
Total retention all prior
S
periodic estimates
6
Total retention to date
AF EO SIGNATURE
DEPARTMENT OOF WATER RESOURCES
(4 + CJ above)
Wor4 Order No.
l
DWR Contract Amount
Date Paid
Total funds obligated
$
Q 5 above)
4 _
9
Funds still available
(7 - S above)
Claim No.
FOR 0-R USE
sU 9N A•,._
DWR '35A New 6 d7) JUbMI I : Uriginal and four copies to the Department of Water Resources.
::
INSTRUCTIONS FOR DWR 4135 A
(To be filled out by the Public Agency for periodic payment)
PART A:
Public Agency: The name should be identical to the name used in the contract with the Department of 'Vater Resources.
Address and Telephone Number: Self-explanatory.
DWR Contract Number: The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4135, Budget and Expenditure Summary.
Attachment Number: Numerically identify each attachment, corresponding to DWR 4135 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds still available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE IN THE BLOCKS MARKED "FOR DWR USE".
If addilimlid space is rc-quired. usu a .second 1 AVR 41:;5 A unci identify it in the upper right huncl corner. Total ONLY the last I)WR 41:3: A.
INSTRUCTIONS FOR PARTIAL PAYMENT ESTIMATE, DWR 4135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identify each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Piice.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C:
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D: -
Part D, 1, 2, and :.3 must be signed.
Part I). 2 is always signed by a registered civil engineer unless otherwise approved in writing by DWR. Part D,:3 is always signed by
:he Public Agency.
All signatures on original set of the estimate must be original signatures. Additional copies may lie made from this set. Please
submit the original and four copies of the entire estimate package to the Department of Water Resources, Bond Financing and
Administration, 1'. 0. Box.942836, Sacramento, CA 9423(i-0001.
DWR 4135A BacKi ;New 6/37)
Stare of California DEPARTMENT OF WATER RESOURCES The Resources Agenc
Proposition PERIODIC ESTIMATE FOR PARTIAL PAYMENT Page_ of _
GENERAL OBLIGATION LOAN/GRANT
PART A (See Instructions on Reverse Side)
Name of Public Agency
Address:
DWR
Telephone No.: Contract No.:
Periodic Estimate No. for Period 19_, to 19
PART B — Expenditure Summary
BUDGET
ATTACH.
PROJECT
STATE
LINE
:TEM NO.
MEN TNO]
DESCRIPTION
EXPENDITURES
FUNDS REQUESTED
PART C — Totals
Total this
1
periodic estimate
Total all prior
2
periodic estimates
3
Total periodic expendi-
FOR DWR USE ONLY)
1 . 2 abovel
Total retention this
Amz,unr of this 5
Partial Poyment
4
periodic estimate
PAYMENT APPROVED:
Total retention oil prior
5
periodic estimates
L
Total retention to date
AUTHORIZED SIGNATURE
DEPARTMENT OF WATER RESOURCES
v
(A + S obove)
'Nark Order No.
DWR Contract Amount
ft
.. 1
Dcte Paid
Total funds obligated,""
$
(3 6 above)
9
Funds still ovoiloble.�Y'
`.r r
Claim No.
(7 -8 above)
Q. •:x
FOR O. R t_.SE
SJ RN A,:r_;
J\.VR 4135:1 :Ne- 6�87) JUbMI I : Uriginal Grid four copies to the Department of Water Resources.
C C
INSTRUCTIONS FOR DWR 4135 A
(To be filled out by the Public Agency for periodic payment)
PART A:
Public Agency: The name should be identical to the name used in the contract with the Department of Water Resources.
Address and Telephone Number: Self-explanatory.
DWR Contract Number: The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4135, Budget and Expenditure Summary.
Attachment Number: Numerically identify each attachment, corresponding to DWR 4135 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds stili available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE IN THE BLOCKS MARKED "FOR DWR L?SE".
If additionitl space is rcquired. uav a scc•ond DWR a L::5 A and identify it in the upper tight halal corner. Total ONLY the last DWR 41:15 A.
INSTRUCTIONS FOR PARTIAL PAYMENT ESTIMATE, DWR 4135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identify each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Price.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C.
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D:
Part I), 1, 2, and :3 must he signed.
Part I). 2 is always signed by a registered civil engineer unless otherwise approved in writing by DWR. Vart D, a is ahvnys signed by
the Public Agency.
All signatures on original set of the estimate must be original signatures. Additional copie-s may be o.nade from this set. Please
submit the original and four copies of the entire estimate package to the Department of Water Resources, Bond Financing and
Administration, I'. 0. Box 9428:36, Sacramento, CA 9.1236-0001.
D:^NR 4135A :Back) (New 6.87)
State of California
Proposition
PART A
Name of Public Agency
Address:
Telephone No.:
Periodic Estimate No.
PART B – Expenditure Summary
DEPARTMENT OF WATER RESOURCES
PERIODIC ESTIMATE FOR PARTIAL PAYMENT
GENERAL OBLIGATION LOAN/GRANT
(See Instructions on Reverse Side)
for Period
DWR
Contract No.:
r 19_, to
The Resources Agenc
Page— of
M
BUDGET
LINE
ATTACH.
PROJECT
STATE
TEM NO.
,MENTNO
DESCRIPTION
EXPENDITURES
FUNDS REQUESTED
PART C — Totals
Total this
1
periodic estimate
Total all prior
2
periodic estimates
3
Total periodic expendi-
tures to date
(FOR DWR USE ONLY)
1 . 2 above
Amount of this
5
Total retention this
'
Partial Payment
4
periodic estimate
PAYMENT APPROVED:
Total retention all prior
5
periodic estimates
6
Total retention to date
AUTHORIZED SIGN 4TURE
DEPARTMENT OF WATER RESOURCES
(d + 5 obove)
Nor'. Order No.
DWR Contract Amount
Vii:%
-:
:i..4... _
Date Pald
Total funds obligated
$
(3 . 6 above)
Claim No.Funds
9
still ovailable
(7 - 8 above)
r�
• �� a ��
i3OR p'NR •_SSE
SJ R.., Am
V`N� 4131-54 .New 0:87} SUbMI I : Uriginal and lour copies to the Department of Water Resources.
PART C
M
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By (Signature of Au[hor<zrd Repreaenlal+vel
19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and./or material supplied
to date.
Signed
'Er.4-eer)
Date:
3. Request for Payment by Public Agency or Water Company
!Rego:rauon .\'n rrebrA
Tho construction .,f the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
t.>re nine Periodic f:stirnate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
''f.s _ for reimbursement of eligible project costs estimated above.
,A,!hor::ed. 0-4—trd 'g—turel
DWR 4135C i3cck) New 61871
THIS PERIOD
TOTAL TO DATE
Amount Earned
g
$
Amount Retained
S
$
Previous Payments
S XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job Completed
74
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By (Signature of Au[hor<zrd Repreaenlal+vel
19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and./or material supplied
to date.
Signed
'Er.4-eer)
Date:
3. Request for Payment by Public Agency or Water Company
!Rego:rauon .\'n rrebrA
Tho construction .,f the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
t.>re nine Periodic f:stirnate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
''f.s _ for reimbursement of eligible project costs estimated above.
,A,!hor::ed. 0-4—trd 'g—turel
DWR 4135C i3cck) New 61871
State of California
PART A
NAME OF CONTRACTOR:
NAME OF PUBLIC AGENCY,WATER CO.
PARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
TELEPHONE NO.
The Resources Agency
Attachment No. OF
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original S From
Revised Revised $ To
n ESCRIPTION OF JOB:
P aR3 B
'Show Originul ltems and Change Orders Separately.
CONTRACT ITEMS
THIS PERIOD TOTAL TO DATE
ITEM'"
UNIT
QUANTITY UNIT PRICE
QUANTITY
AMOUNT QUANTITY AMOUNT
i
'Show Originul ltems and Change Orders Separately.
PART C C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
Con vartor) By )Signature of Authoraed Representative)
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,EnFuuery
Date:
3. Request for Payment by Public Agency or Water Company
(Reg'strat,on Numb-)
Tho (onstrurtii)rn ,)i rh), prv,jt?ct is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
forl,r Hing Pen(�dic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
Pk•rf(-rmed. anti i hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
for reimbursement of eligible project costs estimated above.
1..rn,,,e_.d. pvaegnated tiq[natu rvl
DWR 4135. ,3cci; New 6:87}
THIS PERIOD
TOTAL TO DATE
Amount Earned
S
$
Amount Retained
$
$
Previous Payments
S XXXXXXXXXXXXXXXXXXX
$
Amount Cue
$
$
Estimated Percentage of Job
Completed
c
Is Contractor's Construction Progress on Schedule? 1:1 Yes ❑ No
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
Con vartor) By )Signature of Authoraed Representative)
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,EnFuuery
Date:
3. Request for Payment by Public Agency or Water Company
(Reg'strat,on Numb-)
Tho (onstrurtii)rn ,)i rh), prv,jt?ct is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
forl,r Hing Pen(�dic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
Pk•rf(-rmed. anti i hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
for reimbursement of eligible project costs estimated above.
1..rn,,,e_.d. pvaegnated tiq[natu rvl
DWR 4135. ,3cci; New 6:87}
State of California OF WATER RESOURCES The Resources Agency
Attachment No. of
GENERAL OBLIGATION LOAN/GRANT Periodic Estimate No.
PARTIAL PAYMENT ESTIMATE
DWR Contract No.
Proposition
PART A
NAME OF CONTRACTOR:
NAME OF PUBLIC AGENCY!WATER CO. TELEPHONE NO.
DATE OF COMPLETION: AMOUNT OF CONTRACT: OATES OF ESTIMATE:
Original Original $ From
Revised Revised $ To
DESCRIPTION OF JOB:
PA^i 8
' Show Original Items and Change Orders Separately.
CONTRACT ITEMS THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE QUANTITY
AMOUNT
QUANTITY
AMOUNT
' Show Original Items and Change Orders Separately.
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
• C'ontracmn (Stgnamre of ufhorrzed RepraaerttattL' el
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Engmrert
Date:
3. Request for Payment by Public Agency or Water Company
t Regtatrahort .Vumberl
The construction oC the project is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
f� reu,ning Pernndie F,timate for Partial Payment are true and correct statements of actual costs incurred for work
perf-rmed, and i hereby request payment of funds under the Bond Law provisions of the ;Vater Code in the amount
-:E 3 — _ for reimbursement of eligible project costs estimated above.
• 1ut ^. �•:,:;f. il—gnatrd ,i.Knaturr/
GWR 4135C .Back) :New 6/871
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
$
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job
Completed
s
.c
Is Contractor's Construction Progress on Schedule? ❑ Yes a No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
• C'ontracmn (Stgnamre of ufhorrzed RepraaerttattL' el
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Engmrert
Date:
3. Request for Payment by Public Agency or Water Company
t Regtatrahort .Vumberl
The construction oC the project is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
f� reu,ning Pernndie F,timate for Partial Payment are true and correct statements of actual costs incurred for work
perf-rmed, and i hereby request payment of funds under the Bond Law provisions of the ;Vater Code in the amount
-:E 3 — _ for reimbursement of eligible project costs estimated above.
• 1ut ^. �•:,:;f. il—gnatrd ,i.Knaturr/
GWR 4135C .Back) :New 6/871
State of California PART,MENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
YAMF_ OF PUBLIC AGENCYIWATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original $ From
Revised Revised $ To
",E5(7RIPTION OF JOB:
PART U
*'Show Original Items and Change Orders Separately.
J's:.' 4135C ,N.-, 6.87
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
*'Show Original Items and Change Orders Separately.
J's:.' 4135C ,N.-, 6.87
PART C
C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
trnrtorl !Signature o! Authorised Rep--ral—)
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Sinned
,£agineen
Date:
3. Request for Pavment by Public Agency or Water Company
/Reg,atra hon .VumOer/
1'
he construction �ei ,he project is progressing satisfactorily, and to the bestofmy knowledge the amounts contained in the
Ior( ;;oinV Pervxiic E,uniate for Partial Payment are true and correct statements of actual costs incurred for wart
pe!•,iirmed, anci l hereby request payment of funds under the Bond Law provisions of the Nater Code in the amount
^d --- for reimbursement of eiigible project costa estimated above.
Ur gv ated S,g—turee
OWR 4135C 13act1 tNew 6/57,
THIS PERIOD
TOTAL TO DATE
Amount Earned
g
$
Amount Retained
5
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
g
$
Estimated Percentage of job Completed
T
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
trnrtorl !Signature o! Authorised Rep--ral—)
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Sinned
,£agineen
Date:
3. Request for Pavment by Public Agency or Water Company
/Reg,atra hon .VumOer/
1'
he construction �ei ,he project is progressing satisfactorily, and to the bestofmy knowledge the amounts contained in the
Ior( ;;oinV Pervxiic E,uniate for Partial Payment are true and correct statements of actual costs incurred for wart
pe!•,iirmed, anci l hereby request payment of funds under the Bond Law provisions of the Nater Code in the amount
^d --- for reimbursement of eiigible project costa estimated above.
Ur gv ated S,g—turee
OWR 4135C 13act1 tNew 6/57,
State of California --PARTMENT OF WATER RESOURCES 4 -
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
::AME OF PUBLIC AGENCY!WATER CO.
TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
UArE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original __ Original $ From
Revised Revised $ To
i)_ -Sr RIPTION OF JOB:
FART 3
"Show Original Items and Change Orders Separately.
DWR 4135C New 6/871
CONTRACT ITEMS THIS PERIOD
TOTAL TO DATE
IT`M
UNIT
QUANTITY UNIT PRICE QUANTITY
AMOUNT
QUANTITY
AMOUNT
1
"Show Original Items and Change Orders Separately.
DWR 4135C New 6/871
PART C
r
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of dater Resources.
X-11—tort By (Signature of Authorized Repreae wiuo
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
'Engineer)
Date:
3. Request for Payment by Public Agency or Water Company
)Rex<atra[,un Num6erl
rher-lratrcctiuiifthel)roject is progressing satisfactorily, and to the best of my k now ledge the am, Junts con tained ill the
rf" oin r Penodic Estirnate for Partial Payment are true and correct statements of cctual costs incurred for work
pert(irmeti. and I hereby request payment of funds under the Bond Law provisions of the Nater Code in the amount
ot, S --_ _ for reimbursement of eligible project costs estimated above.
{,thw—d. 0.-Ae—frd S�geaturel
DWR 41350 3acK) New 6/27)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
$
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job
Completed
a
Is Contractor's Construction Progress on Schedule? 11 Yes F-1 No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of dater Resources.
X-11—tort By (Signature of Authorized Repreae wiuo
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
'Engineer)
Date:
3. Request for Payment by Public Agency or Water Company
)Rex<atra[,un Num6erl
rher-lratrcctiuiifthel)roject is progressing satisfactorily, and to the best of my k now ledge the am, Junts con tained ill the
rf" oin r Penodic Estirnate for Partial Payment are true and correct statements of cctual costs incurred for work
pert(irmeti. and I hereby request payment of funds under the Bond Law provisions of the Nater Code in the amount
ot, S --_ _ for reimbursement of eligible project costs estimated above.
{,thw—d. 0.-Ae—frd S�geaturel
DWR 41350 3acK) New 6/27)
State of California
PART A
PARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
NAME OF CONTRACTOR:
:.AME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE!
Original Original $ From
Revised Revised $ To
,L-:; RIPTION OF JOB:
PART S
*Show Original Items and Change Orders Separately.
D A,'R 41.35C . - 6 ?T
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
IT`M�
UNIT
QUANTITY UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
I
I
I
*Show Original Items and Change Orders Separately.
D A,'R 41.35C . - 6 ?T
T
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
'Contractor) (Signature of Authorized Representative)
, 19 Title
2. Certification of Engineer
1 certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the beat of my
knowledge and belief it is a true and correct statement of work performed and/or material inciuded in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Engineer) (ReRmi'atton Number)
Date:
3. Request for Payment by Public Agency or Water Company
"rhe construction of the project is progressing satisfactorily, and to the bestofmy knowledge the amounts contained in the
ti)regoing Periodic Estimate for Partial Payment are true and correct statements of actual cots incurred for work
prr:.)rmed. and I hereby request payment of funds under the Bond Law provisions of the Water- 'ode in the amount
for reimbursement of eligible project costa estimated above.
.-1 u!hornted. Des)gnated S+Rnaturel
,Date)
CWR 4135C 9ccki !New 6/27)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
$
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job
Completed
o-
;c
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By
'Contractor) (Signature of Authorized Representative)
, 19 Title
2. Certification of Engineer
1 certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the beat of my
knowledge and belief it is a true and correct statement of work performed and/or material inciuded in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Engineer) (ReRmi'atton Number)
Date:
3. Request for Payment by Public Agency or Water Company
"rhe construction of the project is progressing satisfactorily, and to the bestofmy knowledge the amounts contained in the
ti)regoing Periodic Estimate for Partial Payment are true and correct statements of actual cots incurred for work
prr:.)rmed. and I hereby request payment of funds under the Bond Law provisions of the Water- 'ode in the amount
for reimbursement of eligible project costa estimated above.
.-1 u!hornted. Des)gnated S+Rnaturel
,Date)
CWR 4135C 9ccki !New 6/27)
State of California
PART A
NAME OF CONTRACTOR:
yAME OF PUaLIC AGENCY!WATER CO.
�ARTMENTOFWATER RESOURCES f
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original S From
Revised Revised S To
^ESCRIPTION OF JOB-.
PART B
`Show Original Items and Change Orders Separately.
—''VR 4135C .. w 6 .47'
CONTRACT ITEMS
THIS PERIOD TOTAL TO DATE
IT "-,V1*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT QUANTITY
AMOUNT
`Show Original Items and Change Orders Separately.
—''VR 4135C .. w 6 .47'
PART C
e�
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
Contrartort
2. Certification of Engineer
By
(Signature of Authonied Representative)
, 19 Title
I certifv that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly -authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
tEngtnean
Date:
3. Request for Payment by Public Agency or Water Company
rHeq<etr¢non Va.nber/
The construction 11f the project is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
furegming Periodic I -:;timate fur Partial Payment are true and correct statements of actual costs incurred for work
;)erformed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
""S — for reimbursement of eligible project costs estimated above.
:l utnr, r,,vd. Uv..rKnated .i�Kna[urri
DWR 41355C .;?ack) ;New 6187)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
S
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job Completed
c
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
Contrartort
2. Certification of Engineer
By
(Signature of Authonied Representative)
, 19 Title
I certifv that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly -authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
tEngtnean
Date:
3. Request for Payment by Public Agency or Water Company
rHeq<etr¢non Va.nber/
The construction 11f the project is progressing satisfactorily, and to the bestof my knowledge the amounts contained in the
furegming Periodic I -:;timate fur Partial Payment are true and correct statements of actual costs incurred for work
;)erformed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
""S — for reimbursement of eligible project costs estimated above.
:l utnr, r,,vd. Uv..rKnated .i�Kna[urri
DWR 41355C .;?ack) ;New 6187)
State of California
PART A
-PARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
NAME OF CONTRACTOR:
NAME_ OF PUBLIC AGENCY: WATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF- COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original $ From
Revised Revised $ To
r ._SCRIPTION OF JOB:
FART B
'Show Original Items and Change Orders Separately.
DWR 4135C "Jew 6.871
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT QUANTITY
UNIT PRICE
QUANTITY AMOUNT
QUANTITY
AMOUNT
1
I
'Show Original Items and Change Orders Separately.
DWR 4135C "Jew 6.871
.e -
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
1Cuntracton By /Jignature u/ Authorised Representglivel
19 Title
2. Certi kation of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract, and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
l Eaguteeo
Date:
3. Request for Payment by Public Agency or Water Company
trat,nn Number)
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
forf•,oing Purtodic F:,tirnate for Partial Payment are true and correct statements of actual costs incurred for work
pt -t 6trmrd, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
"t* •-s —. for reimbursement of eligible project costs estimated above.
trd S,Knatu o
Dater
DWR 4135C .Back; (New 6137)
THIS
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
$
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Cue
$
$
Estimated Percentage of Job Completed
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
a>
e
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
1Cuntracton By /Jignature u/ Authorised Representglivel
19 Title
2. Certi kation of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract, and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
l Eaguteeo
Date:
3. Request for Payment by Public Agency or Water Company
trat,nn Number)
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
forf•,oing Purtodic F:,tirnate for Partial Payment are true and correct statements of actual costs incurred for work
pt -t 6trmrd, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
"t* •-s —. for reimbursement of eligible project costs estimated above.
trd S,Knatu o
Dater
DWR 4135C .Back; (New 6137)
>r
State of California OARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
.:4MF_ OF PUBLIC AGENCY.'WATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
GATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original $ From
Revised _ Revised $ To
n ESCPIPTION OF JOB:
PA R 3
'Show Original Items and Change Orders Separately.
DwR 4135C Mew 5:'87`
CONTRACT ITEMS
THIS PERIOD TOTAL TO DATE
;TEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT QUANTITY AMOUNT
i
i
'Show Original Items and Change Orders Separately.
DwR 4135C Mew 5:'87`
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
By —
(Signature of Authorized Repreeentalicel
19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
tEngtnerrt
Date:
3. Request for Payment by Public Agency or Water Company
!Regtatratron Numb,»
The construction of the prniect is progressing satisfactorily, and to the bestof my knowiedge the amounts contained in the
Core<, going Periodic H:.timute 61r Partial Payment are true and correct statements of actual costs incurred for work
perC:)rmed, and I hereby request payment of funds under the Bond Law provisions of the Nater (.;ode in the amount
"r, 1� ---- for reimbursement of eligible project costs estimated above.
.a u N:on;.-d. Drs�gnatrd .i�Xna:urn
CWR 41_5C Back) (New 6/87)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
Amount Retained
$
$
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
$
Estimated Percentage of Job Completed
a
Is Contractor's Construction Progress on Schedule? ❑ Yes a No*
*Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Nater Resources.
By —
(Signature of Authorized Repreeentalicel
19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
tEngtnerrt
Date:
3. Request for Payment by Public Agency or Water Company
!Regtatratron Numb,»
The construction of the prniect is progressing satisfactorily, and to the bestof my knowiedge the amounts contained in the
Core<, going Periodic H:.timute 61r Partial Payment are true and correct statements of actual costs incurred for work
perC:)rmed, and I hereby request payment of funds under the Bond Law provisions of the Nater (.;ode in the amount
"r, 1� ---- for reimbursement of eligible project costs estimated above.
.a u N:on;.-d. Drs�gnatrd .i�Xna:urn
CWR 41_5C Back) (New 6/87)
State of California ARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
NAME OF PUBLIC AGENCY!WATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original S From
Revised Revised $ To
i =SCRIP TION OF JOB:
PART 8
"Show Original Items and Change Orders Separately.
NR 4'1 35C 1` _- 6 87.
CONTRACT ITEMS THIS PERIOD TOTAL TO DATE
IT
UNIT
QUANTITY
UNIT PRICE QUANTITY
AMOUNT QUANTITY
AMOUNT
I
"Show Original Items and Change Orders Separately.
NR 4'1 35C 1` _- 6 87.
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By !Signature of Authorised Repreaentativer
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
!Engineer)
Date:
3. Request for Payment by Public Agency or Water Company
(ReRatrathon Nurnher)
The construction -4 the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
,rt �nin� Periodic lEstimate for Partial Payment are true and correct statements of actual costs incurred for work
per(iirmed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
�d 7 for reimbursement of eligible project costs estimated above.
a�th��r, rva_ flv.r�gnatrd �i,tnatlrvt
DWR 4135C :Back) (New 6/871,
THIS PERIOD
TOTAL TO DATE
Amount Earned
j
$
Amount Retained
S
$
Previous Payments
S XXXXXXXXXXXXXXXXXXX
$
Amount Due
$
1 $
Estimated Percentage of Job
Completed
r
,c
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No
"Explain:
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By !Signature of Authorised Repreaentativer
, 19 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
!Engineer)
Date:
3. Request for Payment by Public Agency or Water Company
(ReRatrathon Nurnher)
The construction -4 the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
,rt �nin� Periodic lEstimate for Partial Payment are true and correct statements of actual costs incurred for work
per(iirmed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
�d 7 for reimbursement of eligible project costs estimated above.
a�th��r, rva_ flv.r�gnatrd �i,tnatlrvt
DWR 4135C :Back) (New 6/871,
State of California PARTMENT OF WATER RESOURCES
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
NAME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
The Resources Agency
Attachment No. of
Periodic Estimate No.
DWR Contract No.
Proposition
BATE OF COMPLETION: AMOUNT OF CONTRACT: OATES OF ESTIMATE:
Original Original $ From
Revised Revised $ To
,. E:Sr_'RIPTION OF JOB:
PART B
'Show Original Items and Change Orders Separately.
D'r/R 41350 New 6-$71
CONTRACT ITEMS
THIS PERIOD TOTAL TO DATE
!TEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT QUANTITY
AMOUNT
I
'Show Original Items and Change Orders Separately.
D'r/R 41350 New 6-$71
t
State of California
GENERAL OBLIGATION LOAN/GRANT
Proposition
Name of Public Agency/Water Co.:—
Contact Person: John Doe
DEPARTMENT OF WATER RESOURCES SAMPLE
BUDGET AND EXPENDITURE SUMMARY
XYZ WaLer Company
Periodic Estimate No.: 2 for Period January 1
19 86 to January 31
The Resource% Agency
Page 1 of 1
Date 2/1/86
E5XXXX
DWR Contract No.:
__Telephone: (415) 123-4567
r 19 86
LINE
ITEM
ALLOTMENT TITLE
ALLOTMENT
AMOUNT
TOTAL PRIOR
CLAIMS
CURRENT
CHARGES
TOTAL CHARGES
TO DATE
ALLOTMENT
BALANCE
1
En in ering
90,000.00
25,694.77
3,130.43
28,825.20
61,17'4.80
2
Legal Services
1(),000.00
315.00
160.00
475.00
9,525.00
3
Miscellaneous Materials:
100,000.00
3,284.23
96,715.77
Water Conservation Kits
428.00
Pump
2,856.23
4
Construction Work:
640,000.00
215,004.97
424,995.03
Pipeline
1.31,443.97
Reservoir
83,561.00
Administration
60,000.00
60,000.00
Retention to Date:
Pi.pelAne
14,604.89
( 14,604.89)
I'eservoi.r
8,356.10
(8,356.10)
SUB TOTAL THIS PAGE
900,000,00
109,570.77
1'38 018.63
270 550.39
629,449.61
SUB TOTAL PAGE
SUB TOTAL PAGE
TOTAL
900,000.00
109 570.77
138 018.63
270.5.50.39
629,44 .61
INITIAL SUBMISSION ONLY: Reviewed by Registered Civil Engineer
SUBMIT: One Copy to Deportment of Water Resources, Bond Financing and Administration
P. 0. Box 942836, Sacramento, CA 94236-0001
DWR 4135 (New 6/87)
RCE No. Date
r
INSTRUCTIONS FOR DWR 4135 B
(To be filled out by the Water Co. for periodic payment)
PART A:
Water Co.: The name should be identical to the name used in the contract with the Department of Water Resources.
Address and Telephone_ Number. Self-explanatory.
DWR Contract Number. The number is on the contract.
Periodic Estimate: Submit no more than one estimate per month.
PART B: Expenditure Summary
Budget Line Item Number: Corresponding to DWR 4135, Budget and Expenditure Summary.
Attachment Number. Numerically identify each attachment, corresponding to DWR 4135 C.
Description: Identify the material, labor or item being billed. Indicate vendor's name.
Project Expenditure: The total dollar amount of the partial payment being requested by the contractor or vendor.
State Funds Requested: The dollar amount of the project expenditure being requested this estimate.
PART C: Totals
1. Total expenditures and State funds requested from the columns in Part B.
2. Total all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item on previous estimate.)
3. Total of Items 1 and 2.
4. Total retention this estimate.
5. Total retention from all prior periodic estimates — DO NOT INCLUDE THIS ESTIMATE. (See Item 6 on previous estimate.)
6. Total of Items 4 and 5.
7. Loan amount from the contract NOT including the administrative fee.
8. Total of Items 3 and 6.
9. Funds still available — Item 7 minus Item 8. This amount MUST be equal to or greater than zero.
DO NOT WRITE IN THE BLOCKS MARKED "FOR DWR USE".
If additional space is required, use a second DWR 4135 B and identify it in the upper right hand corner. Total ONLY the last DWR 4135 B.
INSTRUCTIONS FOR PARTIAL PAYMENT ESTIMATE, DWR 4135 C
PART A: Self-explanatory.
PART B:
Contract Item:
Unit: Identifv each item by its basic description (each, square foot, linear foot, project, etc.).
Quantity: The number of units contracted.
Unit Price: The price per unit.
This Period:
Quantity: Number of contracted units this period.
Amount: Number of contracted units this period X Unit Price.
Total to Date:
Quantity: Total units billed including this partial payment.
Amount: Total quantity X Unit Price.
PART C:
1. Amount earned: Total of "This Period" and "Total to Date" columns in Part B.
2. Amount retained: Self-explanatory.
3. Previous payments: Self-explanatory.
4. Amount Due: 1 minus 2 and 3.
Estimated Percentage and Progress Schedule: Self-explanatory and required on all contractor items.
PART D:
Part D, 1, 2, and 3 must be signed.
Part D, 2 is always signed by a registered civil engineer unless otherwise approved in writing by DWR. Part D, 3 is always signed by
by the Water Co.
All signatures on origianl set of the estimate must be original signatures. Additional copies may be made from this set. Please
submit the original and four copies of the entire estimate package to the Department of Water Resources, Bond Financing and
Administration, P. O. Box 942836, Sacramento, CA 94236-0001.
DWR 41359 (Bock) (New 5187)
Stare of California
Total this
DEPARTMENT OE WATER RESOURCES
ST''LF
The Resources Agency
Proposition
PL JDIC ESTIMATE FOR PARTIAL PAYME:
Page 1 of 1
Total all prior
109,570.77
GENERAL OBLIGATION LOAN
Periodic estimates
PART A
(see Instructions on Reverse Side)
tures to date
247, 589.40
247,589.40
XYZ Water Company
(PRIVATE)
Name of Water Company:
Total retention this
14,604.89
14,604.89
periodic estimate
Special
j
Name of Bank:
Bank
of Unites! States Checking
Account No.:
567123-4
Address of Bank:
1234 Any Street, Anywhere, CA 95801
Total retention to date
22,960.89
22,960.89
DWR
Telephone No. of
Bank:
(415) 123-4567 Contract No.:
E5XXXX
8
Periodic Estimate No. 2 for Period January 1 19—.a6 to
.Tanttary 31
'19 qA
PART B — Expenditure
Summary
270,550.39
9
BUDGET
IN
ITEM NO_
ATTACH-
ENT NO
DESCRIPTION
PROJECT
EXPENDITURES
3,130.43
STATE
FUNDS REQUESTED
1
1
ABC Engineering Consultants
3,130.43
2
2
DEF
Law Office
160.00
160.00
3
3
GEH
Enterprises
428.00
428.00
3
+
JKL,
Inc.
2,856.23
2,856.23
4
5
LINO
Pipeline, Inc.
131,443.97
131,443.97
(FOR DWR USE ONLY)
Amount of this S
Partial Payment
PAYMENT APPROVED:
AUTHORIZED SIGNATURE
DEPARTMENT OF WATER RESOURCES
Work Order No.
Date Pa,d
[loim No.
POR :WR t1SE
SURNAMEI
DWR 41358 iNew 6/87)
PART C — Totals
SUBMIT: Original and four copies to the Department.of Water Resources.
Total this
138,018.63
138,018.63
1
Periodic estimate
2
Total all prior
109,570.77
109,570.77
Periodic estimates
3
tures to date
247, 589.40
247,589.40
1 . 2 above
4
Total retention this
14,604.89
14,604.89
periodic estimate
j
Total retention all prior
8,356.10
8,356.10
periodic estimates
6
Total retention to date
22,960.89
22,960.89
(4 . 5 above)
7
DWR Contract Amount
900.000.00
8
Total funds obligated
(3 + 6 above)
270,550.39
9
Funds still available
(7 - ft above)
629 449.61
SUBMIT: Original and four copies to the Department.of Water Resources.
PART C or
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
,Controctari By rSsgnct.,e of Authorized Representatn•ei
2/1 , 19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
�Eng�neen
2/1/86
Date:
3. Request for Payment by Public Agency or Water Company
' Regi I t ra t'...Ya m he r i
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 3,130.43 for reimbursement of eligible project costs estimated above.
•Authunred. Designated Sig—t—,
2/1/86
Mate,
DwR 4135C i8ack) jNew 6/87)
THIS PERIOD
TOTAL TO DATE
Amount Earned
S 3,130.43
S 28,825.20
Amount Retained
$ NA
S NA
Previous Payments
S XXXXXXXXXXXXXXXXXXX
$
25 694.77
Amount Due
$ 3 13;=.43
$ 130.43
Estimated Percentage of Job
Completed
Is Contractor's Construction Progress on Schedule? F-1 Yes F� No*
*Explain:
10
N/A
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
,Controctari By rSsgnct.,e of Authorized Representatn•ei
2/1 , 19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
�Eng�neen
2/1/86
Date:
3. Request for Payment by Public Agency or Water Company
' Regi I t ra t'...Ya m he r i
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 3,130.43 for reimbursement of eligible project costs estimated above.
•Authunred. Designated Sig—t—,
2/1/86
Mate,
DwR 4135C i8ack) jNew 6/87)
DLII LL
State of California DEPARTMENT OF WATER RESOURCES^
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
ABC Engineering Consultants
The Resources Agency
Attachment No. 1 of 5
Periodic Estimate No. 2
DWR Contract No.
Proposition
NAME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
,XYZ Water Company
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original S NSA From 1/1/86
Revised Revised S To 1/31/86
DESCRIPTION OF JOB:
Water System Improvement Design and Surveying preparatory to and during construction; Contra
Administration, Engineering Coordination and Supervision during construction; Preparation of
PART B Grade Sheets, Constructing Staking, etc.
*5how Original Items and Change Orders Separately.
DWR 4135C (New 6/87)
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
State
Loan
Design
Project
Our W.O.
106-35
See Attachel
Summary of
Invoices ani
Copy
of Invoices
$3,130.43
S28,825.20
*5how Original Items and Change Orders Separately.
DWR 4135C (New 6/87)
S A M P L E
ABC ENGINEERING CONSULTANTS
February 1, 1986
SUMMARY: STATE LOAN DESIGN PROJECT 106-35.1
Invoice
Date:
Invoice
Number:
Engineering
Fees:
Incidental
Expenses:
TOTAL:
1/10/86
3221
$ 2,090.00
$ 279.97
$ 2,369.97
1/10/86
3222
255.00
9.27
264.27
1/10/86
3223
278.00
.52
278.52
1/10/86
3224
209.00
8.67
217.67
TOTAL:
$ 2,832.00
$ 290.43
$ 3,130.43
ABC ENGINEERING CONSULTANTS
(714) 684-6900
S A M P L E
Invoice
NO. 3221
Date February 1, 1986
BILLING PERIOD:
From 1/1/86 to 1/31/86
Account 106-35.2
DDf1TWIM. _ _ STAIR T flnTL_.IIFSTC9d . DDCI7FCT. C_RAiF.D�i.... TTRMR . ('f1DRRCDf1NT1RNf`R .. - .
General Design; Specification
*
Preparation, and
Related Work.
Services - Office
--
*X Hours 3 $ Y;
-
*X Hours a $ Y **
374.00
*X Hours 3 $ Y **
672.00
$
2,090.00
$ 2,090.00
Incidental Expenses
Prints
$
159.15
Covers, Binders, Dividers
-
30.60
UPS
30.46
The Sun -Telegram
59.76
$
279.97
$ 279.97
TOTAL DUE
$ 2,369.97
X --number of hours _
** Y=hourly rate
ABC ENGINEERING -CONSULTANTS
(714) 684-6900
S A M P L E
Invoice
NO. 3222
Date February 1, 1986
BILLING PERIOD:
From 1/1/86 to 1/31/86
Account 106-35.3
PROJECT: PANORAMA TIE -LINE
Design and.Drafting;.Drafting Specification Exhibit for Project Sign.
Services - Office
*X Hours @ $ Y **
*X Hours @ $ Y **
Incidental Expenses
Telephone
Prints
TOTAL DUE
* X --number of hours
** Y=hourly rate
$ 46.00
209.00
$ -255.00
$ .60
8.67
$ 255.00
$ 9.27 $ 9.27
$ 264.27
ABC ENGINEERING CONSULTANTS
(714) 684-6900
S A M P L E
Invoice
NO. 3223
Date February 1, 1986
BILLING PERIOD:
From 1/1/86 to 1/31/86
Account 106-35.4
PROJECT: STATE LOAN DESIGN PROJECT - PANORAMA PRESSURE REDUCERS & HYDROPNEUMATIC TANK
Drafting and Design.
Services - Office
*X Hours @ $ Y ** $ 18.00
*X Hours a $ Y ** 253.00
*X Hours a $ Y ** 7.00
$ 278.00 $ 278.00
Incidental Expenses
Telephone $ _..12
Prints .40
$ .52 $ .52
TOTAL DUE $ 278.52
* X=number of hours _
** Y=hourly rate
ABC ENGINEERING CONSULTANTS
(714) 684-6900
S A M P L E
Invoice
NO. 3224
Date February 1, 1986
BILLING PERIOD:
From 1/1/86 to 1/31/86
Account 106-35.5
PROTECT: STATE LOAN PROJECT - TERRACE TIE -LINE
Drafting and Design.
Services - Office
*X Hours @ $ Y ** $ 209.00 $ 209.00
Incidental Expenses -
Prints 8.67 $ 8.67
TOTAL.DUE $ 217.67
* X --number of hours -
** Y=:hourly rate
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
'Cuntrar[oq By tStgnat.re of Authorized Reprexrtfatn't[
2/1 .19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
Date:
2/1/86
,Engineer) rRegat•atwn N—b,,,
3. Request for Payment by Public Agency or Water Company
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 1 fin - nn for reimbursement of eligible project costs estimated above.
.{.!hunted, hes,mrtoted Slpnat.,e,
2/1/86
,Dater
DWR 4135C ,Back; (New 6/87)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$
$
160.00
475.00
Amount Retained
S
$
Previous Payments
S XXXXXXXXXXXXXXXXXXX
S 315.00
Amount Due
$ 160.00
$ 160.00
Estimated Percentage of Job Completed
Is Contractor's Construction Progress on Schedule? ❑ Yes ❑ No*
*Explain:
N/A
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
'Cuntrar[oq By tStgnat.re of Authorized Reprexrtfatn't[
2/1 .19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
Date:
2/1/86
,Engineer) rRegat•atwn N—b,,,
3. Request for Payment by Public Agency or Water Company
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 1 fin - nn for reimbursement of eligible project costs estimated above.
.{.!hunted, hes,mrtoted Slpnat.,e,
2/1/86
,Dater
DWR 4135C ,Back; (New 6/87)
State of California DEPARTMENT OF 'NATER RESOURCES J t''lrl'L
GENERAL OBLIGATION LOAN/GRANT
PARTIAL PAYMENT ESTIMATE
PART A
NAME OF CONTRACTOR:
DEF Law Offices
NAME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
XYZ Water Company
The Resources Agency
Attachment No. 2 of 5
Periodic Estimate No. 2
DWR Contract No.
Proposition
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original $ NIA From 1/1 /RFi
Revised Revised $ To 1/31/86
DESCRIPTION OF JOB:
Legal Services
PART B
*Show Original Items and Change Orders Separately.
JWR A135C (New 6/87)
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
See Attach
ad Invoice
N/A
160.00
N/A
475.00
*Show Original Items and Change Orders Separately.
JWR A135C (New 6/87)
S A M P L E
DEF Law Offices
February 1, 1986
PROFESSIONAL SERVICES AS FOLLOWS:
1/10/86 Preparation of four letters (certified
mail) requesting Easement for new Domestic
Water Line. $80.00
1/29/86 Preparation of four letters (certified
mail) re proposed Right of Way Easement
in the vicinity of "S" Road. $80.00
PART C
TH15 PERIOD T T TO DATE
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct, that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
,Cantr6e1ar/ By (Signature of Authorized Representattrr,
2/1 , 19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Enginerrl ,Reg,stranon Number,
Date: 2/1/86
3. Request for Payment by Public Agency or Water Company
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
perfor" � I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of 5 for reimbursement of eligible project costs estimated above.
il-9—tea S,Rnarure,
2/1/86
Date,
DWR 4135C (Bock) (New 6%87)
0 Ai-
LAmount
AmountEarned
S 428.00
S 428.00
Amount Retained
$ None
$ None
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
$
Amount Due
$ 428.00
$ 428.00
Estimated Percentage of Job Completed
Is Contractor's Construction Progress on Schedule? ❑ Yes F� No*
*Explain:
°i
N/A
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct, that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
,Cantr6e1ar/ By (Signature of Authorized Representattrr,
2/1 , 19 86 Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
,Enginerrl ,Reg,stranon Number,
Date: 2/1/86
3. Request for Payment by Public Agency or Water Company
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
perfor" � I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of 5 for reimbursement of eligible project costs estimated above.
il-9—tea S,Rnarure,
2/1/86
Date,
DWR 4135C (Bock) (New 6%87)
State of California DEPARTMENT OF WATER RESOURCES SAMPLE The Resources Agency
Attachment No. _ 3 of 5_
GENERAL OBLIGATION LOAN/GRANT Periodic Estimate No. 2
PARTIAL PAYMENT ESTIMATE
DWR Contract No.
Proposition
PART A
NAME OF CONTRACTOR:
GHI Enterprises
NAME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
XYZ Water Company
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE=
Original Original $ N/A From 1/1/86
Revised Revised S To 1/31/86
DESCRIPTION OF JOB:
Water Conservation Kits
PART B
't Show Original Items and Change Orders Separately.
DWR 4135C INe- 6/87)
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
Kit - See
Each
200
2.14
200
$428.0
200
$428.00
Invoice
't Show Original Items and Change Orders Separately.
DWR 4135C INe- 6/87)
GHI Enterprises
PROJECT:
S A M P L E
Invoice
NO. 1287
Date February 1, 1986
BILLING PERIOD:
From To
Account
CUSTOMER PO NO ORDER DATE DATE SHIPPED SALESMAN ROUTING
per verbal 3 Jan 86 7 Jan 86 SS Shipped UPS
Quantity Quantity Remaining Unit
Ordered Shipped on Order Price Unit Amount
COMPLETE WATER GUARD
CONSERVATION KIT
(2 Toilet Tank Inserts,
2 Shower Flow Restrictors,
2 Leak Detectors)
TER,"!S : 30 days NET
200 ea 200 ea
-0- $2.14 each $428.00
INVOICE TOTAL -
$428.00
PART C
Tulc oC DI(1r1
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By (Signature of Authorized Repeesentatu e.
2/1 , 19 _ 86.— Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
•Entnneeo
Date: 21/11/86
3. Request for Payment by Public Agency or Water Company
tReglateauon Numhen
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of j 2,956.23 for reimbursement of eligible project costs estimated above.
D-im—ted S,gnatmw
2/1/86
DwR 4135C j8cc'lm "New 6;87)
I VIMI I V V..�
Amount Earned
5 2,856.23
$ 2,856.23
Amount Retained
$ Kone
$ None
Previous Payments
5 XXXXXXXXXXXXXXXXXXX
S
Amount DueS
2,856.23
5 2,856.23
Estimated Percentage of Job
Completed
Is Contractor's Construction Progress on Schedule? ® Yes No*
*Explain:
100
a
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the "Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
By (Signature of Authorized Repeesentatu e.
2/1 , 19 _ 86.— Title
2. Certification of Engineer
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
•Entnneeo
Date: 21/11/86
3. Request for Payment by Public Agency or Water Company
tReglateauon Numhen
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed, and I hereby request payment of funds under the Bond Law provisions of the Water Code in the amount
of j 2,956.23 for reimbursement of eligible project costs estimated above.
D-im—ted S,gnatmw
2/1/86
DwR 4135C j8cc'lm "New 6;87)
State of California _DEPARTMENT OF WATER RESOURCES J L'tYLG The Resources Agency
Attachment No. 4 of 5
GENERAL OBLIGATION LOAN/GRANT Periodic Estimate No. 2
PARTIAL PAYMENT ESTIMATE
DWR Contract No.
Proposition
PART A
NAME OF CONTRACTOR:
JKL, Inc.
NAME OF PUBLIC AGENCY/WATER CO. TELEPHONE NO.
XYZ Water Company
DATE OF COMPLETION= AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original $ 2,856_21 From 1/1/86
Revised Revised $ To 1/31/86
DESCRIPTION OF JOB:
Material only, purchase of 20 H.P. Submersible Pumping Unit for Panorama Heights Well
PART B
*Show Original items and Change Orders Separately.
DWR AI35C (New 6/87)
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
OUANTITY
AMOUNT
Pump
1 each
1 each
L.S.
Complete
$2,856.23
Complete
$2,856.23
(See attached
quotati
n sheet)
*Show Original items and Change Orders Separately.
DWR AI35C (New 6/87)
S A M P L E
JILL, INC.
PQR Pumps
December 1, 1985
ABC Engineering Consultants
123 MainStreet
Any Town, CA
Attention:
RE: Quotation on 20 HP Submersible Pump
Gentlemen:
Per your request we are pleased to submit for your consideration the
following quotation. Accordingly, we offer:
1 Model 20 HP Submersible Pump and Motor
100 GPM at 485' TDH $2,354.40
250' #8-3 Cable 165.00
1 12" x 3" x 4" Well Seal 104.40
$2,623.80
6% Sales Tax 157.43
Freight 75.00
TOTAL $2,856.23
Labor to install assuming we have to use the existing pump is $650.00.
Delivery can be made within 15 working days.
The bowl assembly quoted is a 10 stage with bronze impellers, stainless
steel shaft and cast iron bowls.
Thank you for the opportunity of submitting this quotation.
Very truly yours,
JKL, INC.
By
JKL, INC.
PQR Pumps
PROJECT:
S A M P L E
Invoice
NO. 4505
Date February lr 1986
BILLING PERIOD:
From To
Account
Customer Order No. Order Date Shipped Via Date Shipped Terms
2249 1/6/86 System 99 1/15/86 Net 30 Days
1 Submersible Pump and Motor
250 #8-3 Cable
1 12" Well Seal
1 Delivery
1 Sales Tax TOTAL $2,856.23
THANK YOU
Job # 78-274
PART C
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
ivIN0 Pipelines, Inc. B
(Contractor' y 'Signature of Authort:ed Representaheet
2/1
2. Certification of Engineer
19 86 Title President
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly,authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
'Engineer
Date: 2/1/86
3. Request for Payment by Public Agency or Water Company
1Regv1ra1,an N -6f"
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed anc� I he �,by request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 131 X43 �� for reimbursement of eligible project costs estimated above.
Author' -a. Designated Signature,
2/1/86
'Date,
OWR 4135C i8ack) (New 6/87)
THIS PERIOD
TOTAL TO DATE
Amount Earned
$ 146,048.86
$ 146,048,86
Amount Retained
S 14,604.89
$ 14,604.89
Previous Payments
$ XXXXXXXXXXXXXXXXXXX
S —0—
Amount Due
$ 131,443.97
S 131,443.97
Estimated Percentage of Job
Completed
Is Contractor's Construction Progress on Schedule? El Yes a No*
*Explain:
87
ar
�c
PART D
1. Certification of Contractor
According to the best of my knowledge and belief, I certify that all items and amounts shown on the foregoing Periodic
Estimate for Partial Payment are correct; that all work has been performed and/or material supplied in full accordance
with the requirements of the referenced Contract, and/or duly authorized deviations, substitutions, alterations, and/or
additions; that the foregoing is a true and correct statement of the contract account up to and including the last day of the
period covered by this Periodic Estimate; that no part of the"Balance Due this Payment" has been received, and that the
undersigned and his subcontractors have complied with the nondiscrimination provisions of the Loan/Grant Contract
with the Department of Water Resources.
ivIN0 Pipelines, Inc. B
(Contractor' y 'Signature of Authort:ed Representaheet
2/1
2. Certification of Engineer
19 86 Title President
I certify that I have checked and verified the foregoing Periodic Estimate for Partial Payment; that to the best of my
knowledge and belief it is a true and correct statement of work performed and/or material included in this Periodic
Estimate has been inspected by me and/or by my duly,authorized representative or assistants and that it has been
performed and/or supplied in full accordance with requirements of the referenced contract; and that partial payment
claimed and requested by the contractor is correctly computed on the basis of work performed and/or material supplied
to date.
Signed
'Engineer
Date: 2/1/86
3. Request for Payment by Public Agency or Water Company
1Regv1ra1,an N -6f"
The construction of the project is progressing satisfactorily, and to the best of my knowledge the amounts contained in the
foregoing Periodic Estimate for Partial Payment are true and correct statements of actual costs incurred for work
performed anc� I he �,by request payment of funds under the Bond Law provisions of the Water Code in the amount
of S 131 X43 �� for reimbursement of eligible project costs estimated above.
Author' -a. Designated Signature,
2/1/86
'Date,
OWR 4135C i8ack) (New 6/87)
State at California nEPARTMENT OF WATER RESOURCES `'AMPLE The Resources Agency
Attachment No. 5 of 5
GENERAL OBLIGATION LOAN/GRANT Periodic Estimate No. 2
PARTIAL PAYMENT ESTIMATE
DWR Contract No.
Proposition
PART A
NAME OF CONTRACTOR:
MNO Pipeline Incorporated
NAME OF PUBLIC AGENCY/WATER CO• TELEPHONE NO.
XYZ Water Company
DATE OF COMPLETION: AMOUNT OF CONTRACT: DATES OF ESTIMATE:
Original Original S 166.990.40 From 1 /1 186
Revised Revised $ To �f�6
DESCRIPTION OF JOB:
Construction Contract
PART B
'Show Original Items and Change Orders Separately.
DWR 4135C .;Ne- 6/87)
CONTRACT ITEMS
THIS PERIOD
TOTAL TO DATE
ITEM*
UNIT
QUANTITY
UNIT PRICE
QUANTITY
AMOUNT
QUANTITY
AMOUNT
See Attachel
Contract
Partial Payment
Request
$131,443.97
$131,443.97
'Show Original Items and Change Orders Separately.
DWR 4135C .;Ne- 6/87)
0
S A M P L L•'
DATE 2/1/86
Page 1 of 3
CONTRACT DOCUMENTS FOR
FURNISH AND CONSTRUCT TERRACE
TIE LINE & APPURTENANCES AND
PANORAMA
MNO Pipeline Inc.
HEIGHTS TIE LINE,
PRESSURE
TANK &
PRESSURE REDUCER INSTALLATIONS
WITH FENCING &
APPURTENANCES
PARTIAL PAYMENT
REQUEST NO. 1
Bid Item
No.
or
Sub -Item
Contract
Percent Amount
Bid Item or Change
Change Order No.
No.
Description
Amount
Completed Completed
Order Total
101
101.1
6" AC Pipe
36,889.66
95%
35,045.17
101
101.2
6" Gate Valve
1,680.00
95%
1,596.00
101
101.3
6" Fire Hydrant
950.00
100%
950.00
101
101.4
Conn. to exist
200.00
100%
200.00
101
101.5
Conn. to exist
200.00
100%
200.00
101
101.6
Slope Trench
100.00
100%
100.00
202
202.1
12" A.C. Pipe
10,222.60
95%
9,711.47
202
202.2
8" A.C. Pipe
80,567.50
95%
76,539.12
202
202.3
6" A.C. Pipe
4,719.12
95%
4,483.16
7btal Completed =
128,824.92
Engineer's Statement
We have
examined this Payment
Request
and approve
it for payment
Less 10% Retention =
subject
to the noted
changes and/or
corrections.
Balance =
By
Less Previous Payments =
DATE
2/1/86
Page
2 of 3
CONTRACT DOCUMENTS FOR
FURNISH AND CONSTRUCT TERRACE
TIE LINE & APPURTENANCES AND
PANORAMA
MNO Pipeline Inc.
HEIGHTS TIE LINE,'PRESSURE:TANK &
PRESSURE REDUCER INSTALLATIONS
WITH FENCING &
APPURTENANCES
PARTIAL PAYMENT
REQUEST NO.•
1
Bid Item
No.
or
Sub -Item
Contract
Percent Amount
Bid Item or Change
Change Order No.
No.
Description
Amount
Completed Completed
Order Total
202
202.4
6" AC Pipe
6,351.52
95%
6,033.94.
202
202.5
6" Gate Valve
2,040.00
100%
2,040.00
202
202.6
6" Gate Valve
1,200.00
100%
1,200.00
202
202.7
6" Fire Hydrant
4,750.00
100%
4,750.00
202
202.8
6" Fire Hydrant
1,000.00
100%
11000.00
202
202.9
Conn. to exist
200.00
100%
200.00
202
202.10
Conn. to exist
200.00
0
a 202
202.11
1" Air Valve
200.UO
0
Total Completed =
Engineer's Statement
We have
examined this
Payment
Request
and approve it
for payment
Less 10% Retention =
subject
to the noted
changes and/or
corrections.
Balance =
By
Less Previous Payments =
TOTAL DUE
SAMPIX
MNO Pipeline Inc.
Bid Item No.
or
Change Order No.
Sch II 201
Sch
II
202
Sch
II
203
Sch
II
203
Sch
II
209
Sch
II
204
Sch
II
204
Sch
II
204
i
CONTRACT DOCUMENTS FOR.
FURNISH AND CONSTRUCT TERRACE
TIE .LINE & APPURTENANCES.AND PANORAMA
HEIGHTS TIE LINE, PRESSURE TANK &
PRESSURE REDUCER INSTALLATIONS
WITH FENCING & APPURTENANCES
PARTIAL PAYMENT REQUEST NO. 1
Sub --Item
Contract
Percent
No.
Description
Amount
Completed
Pressure Red Sta.
5,000.00
0
Pressure Tank
5,000.00
408
203.1
Fencing
1,290.00
0
203.2
12" Gates
400.00
0
203.3
30" Gates
170.00
0
204.1
Fencing
1,830.00
0
204.2
16" Gate
500.00
0
204.3
30" Gate
170.00
0
Engineer's Statement
We have examined this Payment
Request and approve it for payment
subject to the noted changes and/or
corrections.
By
DATE 2/1/86
Page 3 of 3
Amount
Completed
Total Completed =
Less 10% Retention
Balance =
Less Previous Payments =
TOTAL DUE
Bid Item'.or Change
Order Total
2,000.00
146,048.86
14,604.89
131,443.97