HomeMy WebLinkAboutAgenda Report - January 15, 1997 (66)' CITY OF LODI I COUNCIL COMMUNICATION
i
AGENDA TITLE: Acceptance of Improvements Under Henning Substation Control Building Contract
MEETING DATE: January 15, 1997
SUBMITTED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council accept the improvements under the Henning Substation
Control Building contract and direct the Electric Utility Director to file a Notice
of Completion with the County Recorder's Office.
BACKGROUND: The project was awarded to Diede Construction, Inc., Woodbridge, on August
7, 1996, in the amount of $30,031.00. The contract has been completed in
substantial conformance with the plans and specifications approved by the
City Council. The final contract price was $30,031.00, the same amount as
i the contract award.
FUNDING: 1995-97 Utility Outlay Budget
Alan N. Vallow
Electric Utility Director
Prepared by Hans Hansen, Assistant Electric Utility Director
cc: City Attorney
Purchasing Officer
Public Works Director
i
APPROVED
H. Dixon Flynn
CITY MANAGER
H:IUSERIADMlMCTYCNCLI01-15-97.CC1
January 6, 1997