HomeMy WebLinkAboutResolutions - No. 95-72RESOLUTION NO. 95-72
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE CONTRACT FOR ASPHALT MATERIALS
FOR FISCAL YEAR 1995-96
WHEREAS, in answer to notice duly published in accordance with law and the order of this City
Council sealed bids were received and publicly opened on May 18, 1995 at 11:00 a.m. for the bid for Asphalt
Materials for Fiscal Year 1995-96, described in the specifications therefore approved by the City Council on
May 3, 1995; and
WHEREAS, said bids have been compared, checked, and tabulated and a report thereof filed with
the City Manager as shown on Exhibit A attached hereto and made a part hereof.
WHEREAS, the City Manager recommends award of the Bid for Asphalt Materials for Fiscal Year
1995-96, be made as follows:
Item A. to Granite Construction, Stockton, CA
Item B to American River Asphalt, Folsom, CA, and
Item C to F.T.G. Construction, Lodi, CA
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of the Bid for
Asphalt Materials for Fiscal Year 1995-96 in the amount of $100,290.00, be and the same is hereby awarded
as follows:
Item A. to Granite Construction, Stockton, CA
Item B to American River Asphalt, Folsom, CA, and
Item C to F.T.G. Construction, Lodi, CA
Dated: June 7, 1995
I hereby certify that Resolution No. 95-72 was passed and adopted by the City Council of the City of
Lodi in a regular meeting held June 7, 1995, by the following vote:
AYES:
COUNCIL MEMBERS -
Davenport, Pennino, Sieglock, Warner and
Mann (Mayor)
NOES:
COUNCIL MEMBERS -
None
ABSENT:
COUNCIL MEMBERS -
None
ABSTAIN:
COUNCIL MEMBERS -
None
95
MIBIT "A"
1995-96
ASPHALT MATERIALS
Bid Results
Bid Opening 5/18/95, 11:00 am
Item A.
Granite
F.O.B. Plant
(1.550 Tons)
Teichert
Granite
F.T.G.
American River
Teichert
Construction,
Construction, Lodi
F.T.G.
American River
Sacramento
Aggregate,
$
27.89
Stockton
Construction, Lodi
Asphalt, Folsom
$
Sacramento
$/Ton
$
23.50
$
25.00
$ 20.75
$
20.50
Tax:
$
1.82
$
1.94
$ 1.61
$
1.59
Total $/Ton
$
25.32
$
26.94
$ 22.36
$
22.09
Mileage
Granite
47
F.T.G.
34
81
Teichert
80
Hauling $
$
52.17
$
37.74
$ 89.91
$
88.80
Final $/Ton
$
77.49
$
64.68
$ 112.27
$
110.89
Item B.
Stockpile City Limits (150 Tons)
Low Bid 1995-96
Tons Unit Price Total
Item A. 1550 $ 25.32 $ 39,246.00
Item B. 150 $ 28.75 $ 4,312.50
Item C. 1950 $ 29.09 $ 56,725.50
$ 100,284.00 Total cost based on bid
Contract 1994-95
Tons Unit Price Total
Item A. 1350 $ 25.32 $ 34,182.00
Item B. 150 $ 28.12 $ 4,218.00
Item C. 1100 $ 28.95 $ 31,845.00
$ 70,245.00 Previous Contract Price
Percentage of Chance from crevious Year
Item A. 0.00%
Item B. 2.24%
Item C. 0.48%
0.91%
Average one percent increase from previous year
Str"Wasphalt'SIDRSLTSALS Page 1
Granite
Teichert
Construction,
F.T.G.
American River
Aggregate,
Stockton
Construction, Lodi
Asphalt, Folsom
Sacramento
$/Ton
$
27.89
$
27.00
$ 26.68
$
29.50
Tax:
$
2.16
$
2.09
$ 2.07
$
2.29
Total $/Ton
$
30.05
$
29.09
$ 28.75
$
31.79
Item C.
Hower
of Paver (1, 950 Tons)
Granite
F.T.G.
Teichert
Construction,
Construction,
American River
Aggregate,
Stockton
Lodi
Asphalt, Folsom
Sacramento
$/Ton
$
28.33
$
27.00
$ 28.35
$
34.50
Tax:
$
2.20
$
2.09
$ 2.20
$
2.67
Total $/Ton
$
30.53
$
29.09
$ 30.55
$
37.17
Standby/Hr
$
56.00
$
56.50
$ 58.50
$
58.00
Low Bid 1995-96
Tons Unit Price Total
Item A. 1550 $ 25.32 $ 39,246.00
Item B. 150 $ 28.75 $ 4,312.50
Item C. 1950 $ 29.09 $ 56,725.50
$ 100,284.00 Total cost based on bid
Contract 1994-95
Tons Unit Price Total
Item A. 1350 $ 25.32 $ 34,182.00
Item B. 150 $ 28.12 $ 4,218.00
Item C. 1100 $ 28.95 $ 31,845.00
$ 70,245.00 Previous Contract Price
Percentage of Chance from crevious Year
Item A. 0.00%
Item B. 2.24%
Item C. 0.48%
0.91%
Average one percent increase from previous year
Str"Wasphalt'SIDRSLTSALS Page 1