HomeMy WebLinkAboutMinutes - June 4, 2013 SSLODI CITY COUNCIL
SHIRTSLEEVE SESSION
CARNEGIE FORUM, 305 WEST PINE STREET
TUESDAY, JUNE 4, 2013
A. Roll Call by City Clerk
An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held
Tuesday, June 4, 2013, commencing at 7:00 a.m.
Present: Council Member Hansen, Council Member Johnson, Mayor Pro Tempore Katzakian,
and Mayor Nakanishi
Absent: Council Member Mounce
Also Present: City Manager Bartlam, City Attorney Schwabauer, and City Clerk Johl
B. Topic(s)
B-1 Receive Status Report on 230kV Interconnection Project (EUD)
City Manager Bartlam briefly introduced the subject matter of the proposed 230kV interconnection
project.
Electric Utility Director Elizabeth Kirkley provided a PowerPoint presentation regarding the 230kV
Interconnection Project. Specific topics of discussion included the existing 60kV grid inter -tie
reliability and capacity, CAISO (California Independent System Operator) TAC (Transmission
Access Charges) forecast, PG&E area study, CAISO Board approval of Lodi project and reliability
projects, 230kV development project, industrial substation expansion, project time line and team,
and the next steps for the project.
In response to Council Member Johnson, Ms. Kirkley stated staff asked not to include the CT
(combustion turbine) in Lodi in the study so that additional considerations to bring service into
town would not be included.
In response to Council Member Hansen, Ms. Kirkley stated both STIG (steam injected gas
turbine) plants are included in the study.
In response to Mayor Pro Tempore Katzakian, Ms. Kirkley stated the utility pays both TAC
charges because it is using both the high and low grids.
In response to Mayor Nakanishi, Ms. Kirkley stated PG&E should use the 130MW figure instead
of 152MW in the study so that it can see the need for capacity.
In response to Mayor Nakanishi, Ms. Kirkley stated without renewables the light and dark green
portions of the graph on the forecast slide would be eliminated.
In response to Council Member Hansen, Consultant Mike Keller stated 85% of the load shown on
the Lockeford-Lodi Area Study map is service for the City.
In response to Council Member Hansen, Mr. Keller stated PG&E is no longer fighting building the
project that was mandated upon it although various decisions pertaining to the actual route,
environmental studies, and right-of-way access have yet to be made.
In response to Council Member Hansen, Ms. Kirkley stated the PG&E project increases reliability
but other than that it is a separate issue with respect to the proposed line from the west, which
Continued June 4, 2013
may still have some benefit and will be explored in the future.
In response to Council Member Hansen, Mr. Bartlam confirmed that PG&E may need to pay the
City for use of the land shown on the industrial substation expansion slide.
In response to Council Member Johnson, Mr. Bartlam stated approximately half of the property
would still be available after 230kV service completion.
In response to Council Member Hansen, Mr. Keller stated two transformers will need to be
procured and there is approximately a one-year lead time on them.
In response to Council Member Hansen and Mayor Pro Tempore Katzakian, Mr. Bartlam
confirmed that the City will need to upgrade its portion of the substation, which includes the two
new transformers, prior to PG&E upgrading its portion, which includes the switching station.
In response to Council Member Hansen, Mr. Bartlam stated the City will need to manage and
oversee the PG&E project with PG&E and through CAISO to ensure scheduling and consistency
as it pertains to geography, property owner consultation, and environmental studies.
In response to Council Member Johnson, Ms. Kirkley and Mr. Bartlam confirmed that the
$20 million cost should see the project through completion in 2017, the approximate estimated
cost of a line to the west is $40 million, and PG&E's project includes both a double line and a
230kV connection instead of a 60kV connection. Mr. Bartlam stated a line to the west in the future
may be beneficial because the City may pay less voltage charges but the proposed 230kV project
before the Council currently remains the priority project because it provides both reliability and
capacity at a shared cost.
In response to Mayor Pro Tempore Katzakian, Mr. Bartlam confirmed that the substation with the
transformers is approximately $15 million of the $20 million total project cost.
In response to Mayor Pro Tempore Katzakian, Mr. Bartlam stated for comparable purposes
General Mills uses 3MW.
In response to Mayor Nakanishi, Mr. Keller stated the CAISO operates PG&E -owned
transmission lines throughout the State. Mr. Keller stated PG&E is the largest owner and he will
provide the relevant information as to who owns the transmission lines percentage wise
throughout the State.
In response to Ed Miller, Mr. Bartlam stated the substation is located at Thurman Street and Guild
Avenue east of Highway 99 and payback on the proposed project with cost and finance charges
is approximately ten years.
C. Comments by Public on Non-Aaenda Items - None
D. Adjournment
No action was taken by the City Council. The meeting was adjourned at 8:00 a.m.
ATTEST:
Randi Johl
City Clerk
N
AGENDA ITEM F) I
CITY OF LODI
,. COUNCIL COMMUNICATION
TM
AGENDA TITLE: Receive Status Report on 230 kV Interconnection Project
MEETING DATE:
PREPARED BY:
June 4, 2013
Electric Utility Director
RECOMMENDED ACTION: Receive presentation of the status report on the 230 kV
Interconnection Project.
BACKGROUND INFORMATION: At a City Council Shirtsleeve Session held on December 6, 2011 the
Electric Utility staff provided a status report regarding the City's
electric transmission grid intertie. The presentation also included
proposals staff had received from Pacific Gas and Electric Company and the California Independent
System Operator (CAISO).
A number of meetings have been held since that time as part of the CAISO's 2012-2013 transmission
planning process. This presentation will apprise the Council of the outcome of this process as well as
outline the next steps the Electric Utility will be taking regarding the City's transmission grid intertie.
FISCAL IMPACT: Not applicable.
FUNDING AVAILABLE: Not applicable.
za eth A. irkley
Electric Utility Director
EAK/Ist
FAIaa:Z9lTA:I a
Bartlam, City Manager
230 kV Interconnection
Project
230 kV Interconnection
o Existing 60 kV Grid Intertie
o Transmission Access Charges (TAC)
o PG&E Lockeford-Lodi Area Study
o CAISO Board Approved Projects
0 230 kV Project Timeline
0 230 kV Project Team
o Next Steps — FY 2013/14
Existing 60 kV Grid Intertie
o Reliability
• 4 reported "city-wide" outages in past 7
years, the longest ~2.4 hours
o Capacity
• ~130
MW
w/o
NCPA's
Lodi
CT
• ~152
MW
with
CT running
o Transmission Access Charges (TAC)
• Low Voltage TAC $2.5 M annually
• High Voltage TAC $3 M annually
Wel
M111
130
120
110
f n
A�* 0 Le
Lodi Summer Peak
rl IrT 1 r1
Insufficient capacity: 130 MW w/o NCPA Lodi 25 MW CT
"003 X004 2005 2006 2007 -"008 2009 20201
Calendar Year
A I
RISE Film WOTH
$18.00
$16.00
$14.00
$12.00
s
$1o.ao
V
Q $g-00
x
$6.00
S4.M
$2-00
$0.00
Historical PG&E Area HV TAC ($/MWh) During 2001-2011 and Projected CAISO-
Wide HV TAC ($/MWh) During 2012-2020 Based on the CPUC/E3 LTPP Evaluation
Metric Calculator
Reliability Projects (CAISO 2010-11 Transmission Plan)
■ Renewable w/o Permit
a Renewable w/ Permit
M Existing/Base (IOU Tran
SEN1111
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
Year
7G&E Lockeford-Lod
230 kV System
Rio Oso
New Line 18 miles 230 kV
(CAISO �)r•------- 77
Approved) Tmiles
miles
Atlantic
18 miles
65
11 miles 29 miles
Gold Hill Lockeford
47 miles Lodi Stig
49 miles Lockeford
2 miles Area
Eight Mile r�
NO
7 miles
27 miles Stagg Area Mosher
24 miles ■ <
Stagg
38 miles
r z z 24 miles 14 miles
Tesla Weber
fX ra
12 miles
Bellota
Brighton
42 miles
%&a
66 kV System
Stagg 191 0] k Line
Lodi
•
Ketora-LOCII
•
LodeI190 - Lodi
W kV Line t�Colony
Rio Oso
H.O.
n, U.
Wi r ery
SYS147
SqY i g—i
Lockeford
H.O.
LD -VON - LMI 4�4 W Lir* NO.2
Victor
U,dw W - IrdmhlN 101,V Lint
Sw 97
N.Q.
Industrial,
Lodi Load ".a
L2:k4 gyp- 001 60 kV Lrt,e Na 3
Brighton
�+ Mettler $$ o
Stagg Nb Uri (CA SC APP�d)
N.O �
C _ _ y i SW 75la§ - 0 Be l lota�
1 -
� SW �} SV167
1 Waterloo 7
0-0
�n
SI 111 9a kV Line Mosher
Hammer
West
57 L e
IJ
W.QCherokee
Co-Uretry UOP Surniden
Club Oak Wire
Park 61
Weber
ml 6" ism morel Fa we Fire
Protect for Lod
2D72 -2D73 ISO Transmission Plan
SIT'Nae,
March 20, 2373
Figure 62A-3: Proposed Loaeford-Lodi Area 230 kV Development
mrrrr.r..�
r dDw i.rr
.c .c
ry 07 1-7
LmuF II Lwcbbry
Lbd vie
Irld�tritl �*'+r
.c
EW
mile Lodi Load
R'1
mbrwm
yr--I�nM'li`IlaS i�iF
n4
r.t
r
� Nirvrrl'�r �
Went
w
Cam UOF *�,rrrid�err
Club Oa1k
E oinrl
"k"
21E.`ism :rON, we
gnnrovec
Rel-labill-tv Prole
Table 2 — S umm urs} cf Needed Rel iability Driven Tran smission Projects i n th e ISO 2D 12-2013
Transmission Plan
Srviae Tentkwy
Number of Projects
Cod
Pacific Gas & Electric (PG&E)
31
$1,168 M
Southern California Edison Co_
1
$75 M
(SCE)
Sart' Diego Gas & Elegy Co-
4
100 M
(SDG&E)
Valley Electric Association
0
0
(VEA)
TOM
36
$1,343 M
Lockeford-Lodi Area 230 kV
Development Project
o Mitigate
• NERC Category B & C overloads
• NERC Category B voltage deviations
• NERC Category C low voltages
o $80-105 M
o In-service 5/31/2017
o Solve Lodi's capacity (200 MW) &
reliability constraints
o Lodi cost -$20 M
Industrial Substation Expansion
• . i - _ . s.. 1•
Street
Ac
j
+•,—
sir r.r{
-W12.1'.'-: 15'5 76."
4_
D kV Project Timeline
Su"w,Mard117,2013 I 1 New Industrial 230f6OkV Substation
O
ice[ h me
Mwl
FMM
]dli ipls
U%F@M
Qi A} 4i 41 pi �# 4i OI
ipVd ipft iptF
At fp #� 4� At �# 4i W Ot fG pi q/
1
PmfedDM&PNEIA S CWWrLA.'n
0=13
IZOUM14
*MW
2
Fie DOOp Mx"W
119r;g15
WMM15
B"
3
qM & BM POWff T1a116fb11 M
+1"M15
930M15
laid
4
F WndaSk eF4uaTea5rMMM
10t M5
12f3WM16
3Ud
5
6L6kffl IF W M 1b5
80=15
1FF121716
1284
6
Bid 8,WWd PMID MkMt&OWdad
2=16
Ar2VD16
B"
7
Cadet Now 230EUV SubsbOm
5=16
12MM15
17Sd
F7
Test 8 SUS
tldr11717
341121717
65tl
9
Omgtm New 23NOWSUbMabin
W3=17
40 017
IM
10 Caiad Close -M
4=17
540r1017
65tl LIM
fi JWW
CPM EW NA9CM kL29G-GIW V-9M5Ti1TXWVW Page 1
D kV Project Te
Tuesdzv, April 23, 2013
Lodi 2 DkV - Project Team
------------------ No Cr1YCOUNCIL------------------;
r +
I
I RISK OVERSWHT I
COSHSTTFf I
I �
I I
1
I I
I CITY HAFi4GER �
Rad Baum I
1 I
I �
I
iPROJEL—r SPONSOR
I COIHHINCATIOfIS
� o�em brdeY I
I l
I
I �
l MRANCIAL ENWOMMHERTAL 1
ENGIHEEFM*G LEGAL Juctm Ars
JM MMUMEEBMA S6em sdrraba ff RSR tilaagW Mae schwaLaff I
I � l
5 �
-------------- _____rte
EIMMEHUMB CLMIOE MRAN CULL EMM"NERTAL
CMSULTAMI LEGAL AOVIS R I I OMSULTAMI
orw�µ oyeRVA" I
rd f�r�eMy Enrtrrnrti.l
eenam�peK seas
+tea + F+oae
PIU}JECT SHE
M 4W-same—M
lie Ifs
ewia
Cutrrri ke
Cui�dkn swYrt EPPInrtrrnrnd
R Crloereer �I yr d `
rurnaawwr�, Reeurnrti
inrruenie opa
orar RaaeYuu`
Page 1
Next Steps - FY 2013/14
o Lodi Project Team Kick-off Meeting
o City Council approval PSAs
• Project Subject Matter Expert
• Engineering Consultant
• Outside Legal Counsel
• Financial Advisor
• Environmental Consultant