HomeMy WebLinkAboutMinutes - February 5, 2008 SSCITY OF LODI
INFORMAL INFORMATIONAL MEETING
"SHIRTSLEEVE" SESSION
CARNEGIE FORUM, 305 WEST PINE STREET
TUESDAY, FEBRUARY 5, 2008
An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held Tuesday,
February 5, 2008, commencing at 7:00 a.m.
A. ROLL CALL
Present: Council Members — Hansen, Hitchcock (arrived at 7:01 a.m.), Johnson, Katzakian,
and Mayor Mounce
Absent: Council Members — None
Also Present: City Manager King, City Attorney Schwabauer, and Deputy City Clerk Perrin
B. TOPIC(S)
B-1 "Proposed West Side 60kV Transmission Project"
City Manager King briefly introduced the subject matter of the proposed west side 60kV
transmission project.
With the aid of a PowerPoint presentation (filed), Electric Utility Director George Morrow
explained that Lodi currently imports its power through a single pipe from PG&E's
Lockeford Substation to the east. The City's liability is contingent on the Lockeford
Substation, and over the years outages at this substation have resulted in power failures in
Lodi. The solution is to construct new transmission facilities to the west to diversify source
and location of power imports. Additionally, Mr. Morrow explained that Lodi's current import
capacity is 130 megawatts (mw), which is not enough capacity on a long-term basis, and
the combustion turbine is often utilized to reliably meet electric loads over that amount.
PG&E could upgrade its 60kV transmission circuits in the area; however, it has not
committed to a specific timetable to address the needed improvements. In lieu of the
upgrade, construction of new transmission facilities would increase import capacity.
Council Member Johnson questioned if PG&E is mandated to upgrade its facility, to which
Mr. Morrow responded that it has a statutory requirement to provide reliable, firm
transmission capacity; however, PG&E must work through the California Independent
System Operator (CaIISO), which is a very involved process.
Mayor Pro Tempore Hansen questioned what the consequences would be if the capacity
issues were not addressed, to which Mr. Morrow stated that the Utility would need to curtail
the load, by switching off circuits and implementing rotating blackouts, or import more
power.
Mr. Morrow stated that a new transmission line to the west is an excellent solution to the
reliability and capacity issues due to the fact that it would aid in the performance of the
electrical network, that strong electrical systems exist in the vicinity of 1-5, and there is an
opportunity for direct connection to the Northern California Power Agency (NCPA) power
projects. This would enable the City to bypass paying transmission costs to other
agencies, and the savings could potentially cover the circuit costs. Previous attempts were
made in 1988, 1998, and 2001 to build new transmission into Lodi, and, although progress
was made, no final actions were taken to complete the effort, due largely to concerns
expressed by the agricultural community. Funding to cover the project was allocated from
the NCPA bond issue; however, those funds remained unused for quite some time and were
eventually utilized for other purposes. City Council recently authorized retaining Auriga
Corporation to review the project, and the consultant has identified seven possible routes
and more closely reviewed three, taking into consideration the concerns of the agricultural
community.
Continued February 5, 2008
In response to Mayor Pro Tempore Hansen, Mr. Morrow stated that one of the benefits of
the western line is "behind the meter" generation (i.e. using Lodi's own circuits), which
could save $5 to $10 per mw hour. Additionally, the Lodi Energy Center could reduce
transmission charges for the project. All of these reductions in cost would be passed onto
the rate payers.
Mr. Morrow briefly reviewed the seven alternatives, using a detailed diagram and an aerial
view, and explained some of the pros and cons. Some of the concerns on the various
options include running the line straight along Highway 12 as previously discussed, lack of
frontages cn Highway 12, slicing up properties if run diagonally, and interference with the
airport that may require costly underground work.
In response to Mayor Pro Tempore Hansen, Mr. Morrow stated that the City would most
likely work with PG&E to upgrade the existing utility poles, rather than build new ones on
the opposite side of the street. Where the PG&E poles end, the line could veer south,
thereby missing the wineries. Mr. Morrow added that the new poles would be higher.
Council Member Johnson questioned what would happen with the existing poles near the
proposed substation, to which Mr. Morrow replied that those are stub poles and they would
be cleaned up and integrated. Mr. Johnson questioned how much more it would cost if a
new substation was built in the vicinity of Davis Road and Harney Lane. Mr. Morrow
explained that the substation is proposed to be located on Highway 12 near Chili's
restaurant; the other site is not being recommended. The consultant only identified that
location on the off chance the substation could not be built on Highway 12.
In response to Council Member Hitchcock, Mr. Morrow stated that, as long as the utilities
are built overhead, it is anticipated that the cost of the project would be less than running
the line straight cbwn Highway 12 as originally proposed because the cost is based on a
linear foot calculation. Furthermore, overhead is more reliable and is easier to maintain and
repair. A complete underground project would significantly increase the cost of the project;
therefore, the objective is to select a route that does not go underground. The project cost
would be in the range of $8 million to $10 million, with an annual fixed cost of $800,000 to
$1 million; however, savings from the behind the meter generation could equal or exceed
the costs of the project.
In response to Council Member Johnson, Mr. Morrow stated that the savings and
opportunity to offset costs would be pointed out to the rating agencies. It may be possible
to bundle the debt service with the Lodi Energy Center or to join the Transmission Agency
of Northern California bond that it will be taking out to upgrade and build circuits. It is not
anticipated that this project would increase rates.
Mayor Pro Tempore Hansen stated that, because of the volatility in the rate market and
issues associated with CallSO, the rates will continue to increase; however, this project
could slow down the need for rate increases or, better yet, reduce them.
In response to Council Member Katzakian, Mr. Morrow stated that the new power plant
operates 85% to 90% of the time and is down only for regular maintenance purposes.
Mr. Morrow summarized that staff is intending to move forward with this project, will work
with area residents and impacted parties to gain support for the preferred route, and will
return to Council with a final report. Once the route is identified, the required environmental
impact work will take place, with an anticipated operational date no later than 2011 to 2012.
Mr. King added that no formal actions would be taken outside of the Council.
PUBLIC COMMENTS:
co Terry Quashnick, representing a local plastics company, expressed support for the
project, stating that outages have a serious negative affect on its industry, particularly
when the system shuts down in the middle of a production run. He hoped that all
involved parties can work together to see this project through.
W
Continued February 5, 2008
Mayor Pro Tempore Hansen expressed support for this project as it would address
reliability, capacity, and controlling costs, which would have a positive affect on rate payers.
In response to Council Member Hitchcock, Mr. Morrow stated that there is some flexibility
in connecting with the western system and staff will monitor how the CallSO marketing
strategy affects the City. In further response, Mr. Morrow stated that the cost to install
underground lines at the airport doubles the cost of the transmission; however, he believed
there may be other alternatives, and staff will continue to look into the matter and work with
airport staff. Council Member Hitchcock expressed support for constructing this project as
inexpensively as possible and believed that, if it is more costly to build underground due to
the airport, other alternatives should be explored.
Council Member Johnson agreed with Ms. Hitchcock and pointed to page 75 of the
Transmission Line Study Final Report, stating that the City legally has the right to take
whatever steps necessary to accomplish this goal.
In response to Council Member Katzakian, Mr. Morrow stated that the route straight down
Highway 12 will not initially be considered, due to the concerns of property owners as well
as the higher cost; however, the possibility will not be rejected entirely in case there is no
better approach.
C. COMMENTS BY THE PUBLIC ON NON -AGENDA ITEMS
None.
D. ADJOURNMENT
No action was taken by the City Council. The meeting was adjourned at 7:47 a.m.
ATTEST:
Jennifer M. Perrin
Deputy City Clerk
AGENDA ITEM 6-1
(0 CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Proposed West -side 60 KV Transmission Project(EUD)
MEETING DATE: Februarys, 2408
PREPARED BY Electric LIM ity Director
RECOMMENDEDACTION: Presentation only.
BACKGROUND INFORMATION: Currently, the Lodi Electric Utility Department (EUD) is investigating
the construction of a new power transmission project. This five to
seven mile project is expected to stretch from the vicinity of Lower
Sacramento Road and Highway 12 out to the Lodi White Slough Wastewater Treatment Control Facility.
Lodi would like to construct this project for operation by 2012 (i.e. three to four years).
At the present time, EUD receives bulk electricity through three 60 KV power lines but they all emanate
from one source — PG&E's Lockeford Substation located east of Lodi. Should weather conditions,
mechanical failure or human error impactthis substation, the City of Lodi is in peril of losing electric
service on a City-wide scale. This very scenario has in fact occurred several times since the year 2005
and a number of times previously.
In order to enhance service reliability and reduce the potential for city-wide electric interruptions, EUD is
proposing to construct new power lines to interconnectwith high capacity transmission circuits located to
the west of Lodi near Interstate 5. This project, expected to be composed of two new 60 KV transmission
lines, would provide Lodi a much-needed second source of electricity to meet customers' energy needs
reliably.
Although the exact mutefor this newtransmission line has yet to be determined, EUD is considering as
many as seven (7) alternatives. The utility's goal is to constructtwo overhead transmission lines (both
located on one pole) in a mannerthat cost-effectively minimizesthe impacton adjacent property Owners
and the environment.
Ultimately, this second transmission linewill improve overall electric utility grid reliabilityfor Lodi residents
and businesses, aid in meeting Lodi's future energy needs and reduce transmission delivery charges.
FISCAL IMPACT: Not at this time.
FUNDING: Not applicable. 0
.0'Ir •
George F. Mbnow
Electric Utility Director
GFhM
Attachments
APPROVED:
Blair rng, City Manager
Electric Utility Department
West 60KV
Transmission Project
City Council Shirtsleeve Session
February 5, 2008
Problem 1
• Lodi presently imports its power through a
single " pipe" composed of three circuits
• "Pipe" emanates from PG&E's Lockeford
Substation
• Over the years, outages at Lockeford Sub
have resulted in total blackout of power in
Lodi
• Radial electric service is not accepted
industry practice as to reliability
2
Recent City -Wide
Power Outages
Interruption Date
Duration
Remarks
1/25/2005
12 minutes
Contractor working on 60 KV line
caused flashover
11/4/2005
Momentary
Line relay from PG&E Bellota
(less than 2 minutes)
Substation.
Incoming 60 KV de -energized by
3/6/2006
2 hours, 23 minutes
PG&E 230 KV breaker trip.
10/29/07
Momentary
Lightning tripped off two 230KV
circuits at Lockeford Substation
K
OF
0
Lockeford to Lodi
4
mckw"Ummm-
P"
MK ��7
C:10
11
�,
42
1
�rw��rr■
�R1r 1.�1 P_n■_-r bml Mc
LOQ
mw
M ML -T bmflmc
1�
3t
MP
DIY
I�IY. �1i11�
lM11F
! 1.
m
t3
12 9P
Lw ci
zfm- -i mww �YMI�
1�
+a fir• -M-Om1 w
IT B
4
F <0
00
0
Solution 1
• Construct new transmission facilities to
diversify source/location of power imports
• Existing circuits are located to east of Lodi
• New transmission to the West is obvious
solution
6i
F <0
00
0
Problem 2
• Import capacity into Lodi today is only 130
MW
• Must run Lodi CT (25 MW) to reliably meet
electric loads over 130 MW
• 2008 Peak Load is projected at -- 152 MW.
C.1
00
0
Import Capacity
Lodi Peak Load
✓2008 Projected Summer Load
✓August 30, 2007
✓July 25, 2006
152 MW
134 MW
145 MW
Transmission Import Ratings
✓Summer Rating (w/ CT)
✓Summer Rating (w/o CT)
155 MW
130 MW
7
F <0
00
0
Solution 2
• PG&E can "reconductor" (upgrade) 60KV
transmission circuits in the area.
— PG&E has identified problem but no timetable
yet for needed improvements
• Lodi can construct new transmission
facilities to increase import capacity
E:1
F <0
00
q<,F0
Western Line
• New transmission to the west is an
excellent solution to reliability and capacity
problem
— New "feed" from west helps the performance
of the electrical network
— Strong electrical systems exist in vicinity of I-5
— Opportunity to direct connect to vicinity of
NCPA power projects
F <0
00
0
Previous Work
• There have been a number of studies and
attempts to gain approvals to build new
transmission into Lodi over past 20 years
-1988
-1998
-2001
• Generally siting concerns by the
agricultural community led to no action on
transmission project
10
1/6/88
Public Hearing
introducing the
230kV Line
Project DER
History of West
Transmission Project
2/18/98
Distribution of
Neg Dec 97-03
for Public
comment
5/25/88
Public
Hearing on
approval of
Final EIR.
No Action
Taken.
3/21/98
Council directs
Staff to further
research on
impacts and
gather more
input from
Community
6/98
Chamber of
Commerce
establishes
Alternative
Power
Commission
8/1/00
Council directs
Staff to
proceed with
environmental
process to
design &
construct 60kV
Line
7/01
Negative
Dec
drafted, no
record of
circulation.
n �Q
New Conceptual •
9��FOR�
• Auriga Corporation was retained to
performed to review Lodi transmission
• Requested to look at past work and to look
at routing options
• Auriga identified seven (7) possible routes
and looked at three (3) in more detail
uria
corpora ion
12
Auriga Study Objectives
0,
• Research the routes, impacts, and mitigation needed to
permit and construct a 60kV transmission line from
White Slough to Westside Sub.
— Cost effective, environmentally sensitive design
— Minimize impact upon
• Environment
• Public
• Property Owners
— Meet electric capacity needs of the City of Lodi
— Improve reliability for Lodi customers and the region.
— Reduce transmission charges.
13
Lodi Tnsmission Alternatives 24
xooft
0
•
��
NCPA
STIG #
Saraent
2❑
m
0
City of Ltdi Waste
Water Ealsement
Westsi
Substa
•
r-
0
cn
3
c�
rt
0
a
0 2OW NAYTEQ
OF
Ah
0
2
LIP
6mm
40
Ah
a
Ah
6 Highway 12
Westside
Substation
DbfoggiRd. t
West Kingdon Rd.
Ray
Road
Qr
V
z
weir K110(kn Hu:ld
113
0 LL
Ll
T FOUlf-V L -kjkP
Tredway Rd.
HameyLn.
A
Aht44wa or Ah
:arK*I@111:4"110
�a 1
MIT
4
* �k
230 kv Hus
TX
50 kv Hua
Fufure'60kv CiiL-uits to 60 kv Cirt�aits
TAMC, Western or New Lodi to Westside Sub
Generation
Westside Substation
Location
• Corner of Westgate Drive & HWY 12
CITY OF LODI SACRAMEKTO
TURNER RD. TURN R. RD. TURNER RD.
T
Ti LOOKEFORO - EFORO ST.
17
ST
E
o
_
`
OCUST
L ELM
ST
ST.
ELM ST
VICTC
WESTSIOE
�
PINE
ST
—
PROJECT
TOKAY ST. �
Y ST.
VINI 51
�NE
WESTSIOEffi
HENNING
SUBSTATION
—
SUBSTATION
0
J KETTLEMAN LN..
KETTLEMAN
LN.
SOUTHWEST='-`�"=:=n
GATEWAY
PROJECT
CENTURY
vo.l
—__
cENruRY e
H
OTHER
STOCK -MN
ANNEXATION
AREAS
17
00
0
Alternative 7
TMol OH LenpthmMwrW
Scope
5.75 Miles, Single Circuit 60kV
• 90% Wood Poles, 55' Height
-10% Wood and/or Steel Poles,
65'— 90' Height.
Benefits
• Short route
•Avoids past issues on Hwy 12
Risks
•Airstrip Mitigation
•Southwest Gateway
18
Alternative 6
TO -W L13 Lrerg#h-?,VEZ
TO -W Di Deng#h-2l,17L'
Scope
5.55 Miles, Single Circuit 60kV
-90% Wood Poles, 55' Height
-10% Wood and/or Steel Poles,
65'— 90' Height.
Benefits
Avoids Southwest Gateway
Risks
Air Strip Mitigation
Visual Impact
19
hoEtIL
as M
ew
Ile
in
ML
Oam FM
Alternative 1
ewer a
I
TctLL lM Lrrgth-OAM1
TtALk W LrnS*P-W.A4Y
L Scope
7.4 Miles, single circuit 60kV
-90% Wood Poles, 55' Height
-10% Wood and/or Steel Poles,
Owl
65'— 90 Height.
Benefits
• Constructability
Risks
• Visual Impacts
all
Wood Pole,
t� �P60kV Double Circuit
� 55 to 90 feet
fi�8
fl1�1
3G�-9
•
Y.t.*`'r'.V.'.**rrYh'.'.*'r'rY.'.*`:'rY.'.
��*`'`'
r'r r'� �yr�r
..�
CITY or LODI su�v P= T�YP VEMrA4
L14'IW! Umm wren EM!ACN BR)T
P6AF8P TF na
1 -i
w y
is wN w � wry
� 55 to 90 feet
F <0
00
0
Municipal Land
Acquisition Rights
Staff's goal is develop a project route and
acquire siting rights in an affirmative,
mutually agreeable manner.
• State law provides for electric utilities to
acquire property outside its corporate
limits for public purpose
22
Costs
• Routes range from about 5 to 7 miles
• Double circuit transmission line costs
range from $1.5M (OH) to $20M (UG)
— Overhead assumed at $50 per foot
— Underground estimated at $600 per foot
• Additional 230KV/60KV interconnection
costs estimated at about $5M
• Rough project cost estimate is $10 million
23
OF
0
Savings
• Line to west gives utility opportunity to put
generation "behind the meter"
• Savings of $1-2 million per year is very
possible in reduced CAISO transmission
wheeling charges
• Although project needed for reliab
possible for wheeling savings t
offset cost.
ility, it is
o more than
24
Ca �Q
Summary of Ben
e
its
'9- 01
• Improve system reliability
• Reduce probability of City-wide outages
• Enhance electrical performance of local
network
• Reduce transmission charges and losses
• Gain flexibility to change control areas if
appropriate
• Increase import capacity into Lodi
W
Next Steps
Obtain outside assistance to facilitate
communications with impacted parties
• Work with property owners to identify a
project routing that has the most
acceptance and support
• Once route is identified, undertake needed
design and environmental impact work
• Build project with an operational date not
later than 2011-2012.
M