HomeMy WebLinkAboutMinutes - August 1, 2006 SSCITY OF LODI
INFORMAL INFORMATIONAL MEETING
"SHIRTSLEEVE" SESSION
CARNEGIE FORUM, 305 WEST PINE STREET
TUESDAY, AUGUST 1, 2006
An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held Tuesday,
August 1, 2006, commencing at 7:01 a.m.
A. ROLL CALL
Present: Council Members — Beckman, Hansen, Johnson, and Mayor Hitchcock
Absent: Council Members — Mounce
Also Present: City Manager King, City Attorney Schwabauer, and Interim City Clerk Perrin
B. TOPIC(S)
B-1 "Presentation of developer responsibility for costs associated with electric line/service
extension and possible changes"
George Morrow, Electric Utility Director, reported that staff has been researching how other
electric utilities handle the cost sharing for line adensions, what the cost is for providing
the service, and whether the City should update its current cost sharing procedure to
provide for full cost recovery. Current City policy states that developers are responsible for
substructures, which includes pipes, conduits, vaults, transformer pads, and pedestals, and
the City is responsible for all other items, including wire, transformers, metering, extending
lines, and overhead facilities. A majority of electric utilities place the responsibility for
substructures on developers, including the physical work of installation; whereas, the City
of Lodi performs the actual work and then charges the developer. Most electric utilities
assign all other costs directly to new development or to those who require expansion of the
system, and in Lodi, those costs are not currently passed on to developers. In
comparison, Pacific Gas & Electric (PG&E), which is an investor-owned utility, rebates the
developer/customer over time if it follows through on what it intended to do; otherwise, the
rebate is not given and the developer/customer pays the costs. Generally, substation
costs are not being assigned to developers; however, the city of Roseville is considering
doing so, and the Sacramento Municipal Utility District and PG&E are currently assigning
the costs if there is a direct, identifiable substation transmission cost associated with the
development. In reviewing a four-year average, Lodi developers have been paying one third
(or 33%) of the total cost package, and the City has been paying two thirds (or 67%). On
average, this percentage represents $365,000 to $500,000 per year in expenses.
In response to Council Member Hansen, Mr. Morrow explained that historically electric
utilities incurred all costs because it was a wealthy industry, the costs of distribution were
small compared to the cost of new power plants, and the costs were eventually passed on
to ratepayers through rates. As time passed, the costs became more significant,
particularly with deregulation. Cities began growing dramatically, which prompted
municipalities to begin passing the costs on to the developers. Lodi is at that point now
where there is significant growth on the horizon, and this would help to realign some of the
costs. This trend started about ten years ago, and five years ago most utilities began
implementing full cost recovery methods.
In response to Mayor Pro Tempore Johnson, Mr. Morrow stated that there are presently four
substations in Lodi. He believed there was enough capacity to serve the existing
community, some future development within the current boundaries, and some new
development over the next five to ten years should the City choose to annex additional land.
At some point, however, new substations will be necessary for either capacity or for
reliability. Regarding Delta College, Mr. Morrow believed that the two substations on the
Continued August], 2006
east side of town would meet the increased needs. The concern would be growth in the
southern portion of the community, as these areas are further away from existing
substations, and it would be sensible to install another substation for better performance.
Some electric utilities directly assign costs that are readily identifiable; whereas, others
charge an assessment at the time of growth, which is what staff is recommending. Based
on staff calculations, a generic substation would cost approximately $7.5 million, with a
transmission cost of $400,000, and he believed the City would need another substation in
five or so years.
Council Member Hansen questioned if the City could show that a new substation would be
directly attributable to new development alone as opposed to both new development and
existing service. Mr. Morrow responded that it would be the latter as the substation would
be connected to the entire system, therefore, providing a benefit to the entire community.
Mayor Hitchcock questioned if a substation would be needed if the City had no further
growth, to which Mr. Morrow responded in the negative; however, he explained that it may
be needed in order to provide better reliability. Currently, there is a transmission line that
brings bulk power from the PG&E Lockeford substation from the east; Lodi is impacted
each time that substation experiences a problem, and it would be prudent to have another
line coming into Lodi.
Mr. Morrow reported that the proposal from staff is that the developer/customer be
responsible for all distribution system costs related to their expansion project and that there
be an assessment for future substation transmission. The revenue from this proposal would
be $500,000 that could be set aside for reserves and could eventually help to keep rates
low. For a typical 200 amp residential lot, developers currently pay $750 and the City pays
$1,050, and this proposal would move the City's cost to the developer. With the
recommended assessment fee of $819 for substation transmission, the additional cost to
the developer for a typical residential lot would be $1,869, for a total cost for electric
expansion of $2,619.
In response to Mayor Pro Tempore Johnson, Mr. Morrow stated that the proposal does not
change the type of equipment installed; the issue is who pays for it. During the recent heat
wave, the City lost only 6 out of 3,600 transformers, where some utilities lost 10%.
In response to Council Member Beckman, Mr. Morrow explained that many investor-owned
utilities manage their costs similar to PG&E, which may be due to their regulatory model
and because they operate in hundreds of communities. Investor-owned utilities pass all of
the costs through the rate base and make a profit on their investment. Mr. Beckman added
that, in order to increase their customer base, they offer programs that do not penalize
those who want to build in their area and he believed this put Lodi at a disadvantage to
attract new business. Mr. Beckman felt that the City's transfer to the general fund from
Electric Utility is considered a profit, as it is based on the number of customers.
Mr. Morrow clarified that the City no longer transfers based on a percent of revenue; it is a
flat rate. He stated that staff would check with the cities of Sacramento, Roseville, Turlock,
and Modesto to see if this has negatively affected their expansion.
Council Member Hansen added that the City may not reimburse costs as does the investor-
owned utilities; however, Lodi's industrial and commercial rates in certain categories have
historically been lower, which he believed offset the cost issue for those looking to locate in
Lodi.
With the aid of an overhead (filed), Deputy City Manager Krueger provided an overview of the
various impact fees (i.e. water, sewer, storm drainage, etc.) that developers pay for a
typical residential unit. With the proposed electric substation fee of $819 included, a
typical residential development would pay a total of $20,500 in impact fees.
2
Continued August], 2006
Council Member Hansen requested that staff provide a comparison of Lodi's impact fees
with other cities in San Joaquin County when this matter comes back before Council.
City Manager King confirmed that various elements of the impact fees would increase at
some point in the future and that the list did not include all of the impact fees (i.e. regional
transportation impact fee, habitat conservation impact fee, etc.).
PUBLIC COMMENTS:
oo Jeffrey Kirst stated that ten years ago the development community went from paying a
fairly low rate to suddenly paying all associated costs. The development community
had expressed to the City Manager at that time that it wanted to be on par with
PG&E's rates, and in order to do so, it was determined that developers would pay for
its portion of the wire and substructures for residential projects. He believed the reason
PG&E reimbursed the money for the hard wiring was due to the fact that the California
Public Utilities Commission ruled that the utility would be receiving a gift. He reiterated
that the development community would like to be on parity with PG&E.
C. COMMENTS BY THE PUBLIC ON NON -AGENDA ITEMS
None.
D. ADJOURNMENT
No action was taken by the City Council. The meeting was adjourned at 7:49 a.m.
ATTEST:
Jennifer M. Perrin
Interim City Clerk
MEMORANDUM I
#,ffice of George F. Morrow, Directo
. A
1%
ffl
Agenda Item B-01
EUD is responsible for furnishing and installi ng the 12kV (primary voltage) underground
main feeders, overhead distribution system (including transformers and conductors),
power substations and the transmission facilities for 60kV and above. EUD also furnishes
and installs electric service (1 20124OV) conductor (eI . wire).
PgySlopers provide trenching, excavation, backfill and compaction for 12kV and 120/240V
underground systems. The developer also installs all required substructures such as
vaults, conduits, transformer pads, pedestals, etc. (In the rare circumstance that a new
development is not contiguous to EUD's system, the developer may also be required to
pay to extend the electric system to the edge of the development.)
Staff reviewed the policies of other electric utilities in the region to ascertw%
.`
&Prima ry/Seconda ry Voltage) and No. 16
(Service Connections, etc).
Tables 1 and 2 below document the findings of EUD's review of other nearby utility service
policies related to how electric distribution system expansion costs are being charged to new
developments:
F I III I III
Wil III I III 1111=11111�=4= I
,:
July 27, 2006
Page 2
Tablesshow. that the majorityplace mostiallof the cost
providing ne . w/additional services on the requesting customer/developer. The
Sacramento Municipal
that have moved to a full cost recovery
integrateIt should be noted that the "generic" cost of providing additional substation capacity (and
associated transmission facilities to the substation
generally gdevelopers
$MUD and PG&E), however, will charge any direct substation costs if clearly incurred as the
result of a development, A brief survey of utilities nationally found
that a growing of
electric utilities of so charge for substation -related costs incurred.
What has been ELID's historical cost experience for expanding its electric s
Ystem
provide
Mr, Blair King
July 27, 2006
Page 3
W
Note: Gost-s of transmission and substation facilifles are not included.
Staff was also interested in knowing how electric extension costs have been shared between
EUD and developers for residential subdivisions only. Table 4 shows the cost of improving the
electric distribution system to serve various residential subdivisions in recent years. The
calculated total cost per residential lot is approximately $1,800 in which 58% was paid by EUD
(-$1050/lot) and 42% was incurred by developers (-$750/lot).
MCI lI Iff 11 1111 111! 1 111 FEET MEN
Note: Costs of transmission and substation facilities are not included.
It should be noted that in both expense tabulations above, the cost of commissioning: the
d eveloper-furnishedAnstal led streetlights by the City and the cost of improving the C�Y's
transmission and substation facilities were not included,
Table 5 on the next page illustrates the calculation of substation costs and of a "full cost"
developer assessment for a typical (200A) residential property.
. ....... . ....
Number of Lots for Residential Subdivision
Total
Cost per
11 74 171 27 2q 16 ..........
--$-3-,"
233
Lot
Percentage
Line ExtensionsfServims
$24,26 65,80� $625-8-4- ... .
563 1 7
-8 0�22$42,26.4
—$16,5687—$1 -462
$244,785
$1,051
—$756
50%
—4
Substructures
$22,115 $42,329 $61,&12
$176,661
21
Note: Costs of transmission and substation facilities are not included.
It should be noted that in both expense tabulations above, the cost of commissioning: the
d eveloper-furnishedAnstal led streetlights by the City and the cost of improving the C�Y's
transmission and substation facilities were not included,
Table 5 on the next page illustrates the calculation of substation costs and of a "full cost"
developer assessment for a typical (200A) residential property.
July 27, r
Page 4
Effective Capacity
48.00
MVA
No. of Distribution Feeders
8
Circuits
No. of Power Transformers
2
knits
Substation Lot Size m
40,000
sq ft
Distribution Substation Cast = $
7,444,500
It. 6GkV Transmission Line,
Typical Line Length to the Substation =
5.00
miles
6QkV Transmission Cast = $
420,000
lil, Typical Oistribution Substation Facility Cost,
Total (Substation + Transmission) Cost : $
7,854,500
Cost per WA �
188.84
2005$
Presently, developers/customers requiring expanded electric service in Lodi are generally responsible
only Foy° the cast of underground substructures (i.e, conduit and vaults). Many electric utilities have
moved to a "full cost recover„ model for expanding electric facilities.
Looking at: historical costs, SLID has been paying about 2/3 of the cost to extend new service while
developers/customers have been paying about one-third, For recent lamer -scale residential
developments, EUD has paid about 58% of costs with developers being responsible for the remainder.
Under a "full cost recovery" model, developers would pay all future costs for electric service extensions,
A developer's cosi to extend services to a typical residential lot (2000 under this approach would
increase; from $750Aot to abort $1800/lot. In addition, Staff` suggests that new development outside
current City boundaries (i.e. as of 811106) be assessed a charge for the addition of future substations and
associated transmission lines. In 2006 dollars, the cost of standard substation is calculated to be
$163.84 per K (kilovolt -ampere) which would add $1146.91 to the cast of a typical 200A residential
electric service.
Cost Summary for Typical Residential Unit (200A)
struei_ e osts —
$75Ei
Presently_._paid by Developer
Line Extension& Service Casts
$1,050
Presently aid b EUD
Substation/Transmission
1,147
Presently EUD Res onsibilit
# Coss
$2,947
Pr posed to be paid EiFy l er
Extension of Electric Facilities
.0
Trot
Shirtsleeve Session
August 1, 2006
Questions
• What is EUD's current policy for sharing the cost of
electric line/service extensions?
• What are the practices of other electric utilities in this
regard?
• What has been EUD's historical cost experience
related to system expansion?
• What are the "full costs" associated with electric
system extensions?
• Should EUD to update/modify its cost sharing policy
to provide for full cost recovery?
EUD Current Policy
• Developer responsible for cost of installing
substructures:
- Conduit, vaults, transformer pads, pedestals
• EUD responsible for all other costs:
- Conductor, transformers, metering, etc. for primary,
secondary and service lines (overhead or underground)
Note: Developer may also be responsible for costs to connect non-
contiguous development.
Utility Survey Results (1)
Is the Developer responsible for the cost
of primary secondary/ electric extensions?
Utility
Substructures
All Other
City of Roseville
Yes
Yes
Modesto Irrigation District
Yes
Yes
Turlock Irrigation District
Yes
Yes
Sacramento Municipal Utility District
Yes
Yes
Pacific Gas & Electric Company
Yes
Yes/No
Lodi Electric Utility - Current
Yes
No
Lodi Electric Utility- Proposed
Yes
Yes
Utility Survey Results (2)
Is the Developer responsible for the cost of
providing & installing service connections & facilities?
Utility
Substructures
All Other
City of Roseville
Yes
Yes
Modesto Irrigation District
Yes
Yes
Turlock Irrigation District
Yes
Yes
Sacramento Municipal Utility District
Yes
Yes
Pacific Gas & Electric Company
Yes
Yes/No
Lodi Electric Utility - Current
Yes
No
Lodi Electric Utility - Proposed
Yes
Yes
Utility Survey Results (3)
Is the Developer responsible for the cost
of SU StatlonS and associated transmission?
Utility
Substations &
Transmission
City of Roseville
Being Considered
Modesto Irrigation District
No
Turlock Irrigation District
No
Sacramento Municipal Utility District
Sometimes
Pacific Gas & Electric Company
Sometimes
Lodi Electric Utility - Current
No
Lodi Electric Utility- Proposed
Yes
Utility Surveys -- Summary
• Most electric utilities in the region have
adopted a "full cost" recovery model
• "Generic" substation/transmission cost
recovery is done in specific circumstances but
being considered on a broader basis
Historical EUD Costs
YEAR
Paid by City
Line Extensions & Services
Paid by Developers
Substructures
2002
$
300,484.00
$
141,453.00
2003
$
304795.00
$
186,614.00
2004
$
398, 753.00
$
190, 544.00
2005
$
458,925.00 Ir$
—i
204,715.00
Total
$
1,462,957.00
$
723,326.00
Average
$
365,739.25
$
180,831.50
Percentage
67%
33%
Residential Subdivision Cost
For actual residential subdivisions over the past couple
of years, EUD has paid 58% of costs with the developer
paying the remainder.
Number of Lots for Residential Subdivision
Total
Cost
per
%
11
74
77
27
28
16
233
Line Extensions/Services
$24,260
$65,802
$62,384
$32,053
$18,022
$42,264
$244,785
$1,051
58%
Substructures 11
$22,115
1 $42,329
1 $61,892
1 $19,295
1 $16,568
1 $141462
,LL758
42%
Substation Capacity
• EUD currently has four distribution substations.
• These 4 substations are believed sufficient for
existing and in -fill development in the city.
• In the short run, the new developments under
discussion can also be served from existing
substations.
• In the longer run (5 to 10 years), the
west/southwest and/or south/southeast areas are
possibilities for locating new substations.
Substation Cost Survey
• Ludlow, VT -- all cost of required
substation/transmission
• Mountain View Electric Association, CO — all
cost of required substation/transmission
• Fort Collins, CO — Electric Capacity Fee
• Longmont, CO — Electric Community Investment
Fee
• Burbank, CA — Off-site Facilities Fee
• SMUD, CA — 1 MW or larger, all costs
• PG&E — all cost of required
substation/transmission (Woodland, CA)
Substation Cost Comt)utatioi
1. 60kV to 12kV Distribution Substation:
Effective Capacity = 48.00 MVA
No. of Distribution Feeders =
8
Circuits
No. of Power Transformers =
2
Units
Substation Lot Size =
40,000
sq ft
Distribution Substation Cost =
II. 60kV Transmission Line:
Typical Line Length to the Substation =
$ 7,444,500
5.00
Imiies
60kV Transmission Cost =
III. Typical Distribution Substation Facility Cost:
Total (Substation + Transmission) Cost =
$ 420,000
$ 7,864,500
Cost per kVA = $ 163.84 2006LJI
Summary
• EUD is incurring the majority of costs for
expanding the electric distribution system for
growth
• Many utilities pass all such costs to
developers/customers
• EUD should consider adopting a "full cost"
recovery model for distribution expenses
Staff Proposal
• Adopt a "full cost" recovery model for distribution
expenses for system growth
- Developer/customer to be responsible for all electric system
costs related to their development or expansion project
- Development outside current City boundaries to pay a
substation/transmission assessment of -$164 per KVA.
• This would result in
fund (-$500K)
annual fiscal benefit to electric
Sample Cost -- Residential
Current Developer Costs
-- Substructure
$750
Additional Developer Costs
-- Line Extension & Services
$19050
-- Substation/Transmission (outside City limits only)
$819
Total Costs
$29619
Note: 1. Example is for typical 200A Residential Service
2. Substation Charge is lower than staff report
$1,869
Typical Residential Cost Comparison
Truckee
$1500
Roseville
$1300
Sacramento (SMUD)
$1050
Turlock (TID)
$1300
Lodi
$10501
Note: The above is the cost for line extension and
services. The "substructure" costs are identical for
each since it is developer physical responsibility.
Questions/Comments
Low Density Residential
($ per residential unit)
Service Category
I Existing Impact Fee 1
Water
$1,060
Sewer 2
$5,166
Storm Drainage
$2,078
Streets 3
$3,016
Police
$417
Fire
$407
Parks & Recreation
$5,854
General City
$1,683
Art In Public Places
included
Total
$19,681
Electric $819
Total with Electric $20,500
For purposes of this comparison, the acre -based fees of the
existing program are converted to unit -based fees using 4.5 units/acre.
This is comparable to the density built in the Century Meadows area.
Sewer fee assumes 2 -bedroom home.
3 Streets fees include the Lower Sacramento Road portion
but not the County -wide regional transportation impact fee.
C:\Documents and Settings\jperrin\Local Settings\Temporary Internet Files\OLKC4\Copy of Comparison by Land Use.xls