HomeMy WebLinkAboutAgenda Report - March 4, 1998COUNCIL COMMUNICATION
AGENDA TITLE: Agreement for the Provision of Engineering and Construction Services
MEETING DATE: March 4, 1998
SUBMITTED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution authorizing the City Manager
to enter into a contract for the Electric Utility Department to provide engineering
and construction services to Woodbridge Irrigation District.
BACKGROUND: The City Council was briefed at their January 13, 1998 Shirtsleeve Session on
the status of Woodbridge Irrigation District's efforts to become an electric power
provider. At that time it was reported that Electric Utility Department staff had
been providing professional assistance in examining
the feasibility of this endeavor. The Council was clear in its direction that the Electric Utility Department should
aggressively pursue wholesale sales opportunities and regional economic benefits. The proposed Agreement with
Woodbridge Irrigation District provides Lodi with an opportunity to market surplus wholesale generation and
improves the Electric Utility's economy of scale with respect to provision of electric services.
Since the January 13, 1998 meeting, Woodbridge has taken several steps to prepare to serve Sebastiani Wineries
and is now ready to begin construction of a 12kV line to provide service to Sebastiani facilities in the Woodbridge
area. The Electric Utility Department is requesting authorization to enter into a contract to act as Woodbridge's
contractor for the construction of this line. The Electric Utility Department will provide labor and materials for
construction of the line; Woodbridge Irrigation District will reimburse the Electric Utility Department over a period
not to exceed eighty-four months. Interest will be paid by Woodbridge at a rate equal to that obtained by the Local
Area Investment Fund. Sebastiani Wineries will become a customer of Woodbridge Irrigation District; the Electric
Utility Department is not proposing to provide retail services outside its current service area. Operation and
maintenance services, interconnection rights, and access to market priced power will be negotiated in the future
under separate agreement.
A. Woodbridge Irrigation District has approved a Negative Declaration of Environmental Impact for the project
to serve Sebastiani Wineries.
B. Woodbridge Irrigation District has obtained the approval of the Local Area Formation Commission to serve
the Sebastiani facility that is not currently within its legal borders.
C. Woodbridge Irrigation District has applied for membership in the Northern California Joint Pole Association.
D. The Board of Directors of the Woodbridge Irrigation District is scheduled to consider this contract at their
March 10, 1998 meeting.
E. The contracting of services between the Electric Utility Department and the Woodbridge Irrigation District
would result in the optimal allocation of personnel resources and improved economies of scale with respect
to the provision of electric service.
Approved
'T-111. Dixon Flynn
City Manager I
lectric Utility Department Council Communication
Date of Meeting: March 4, 1998 Page 212
F. The availability of low cost power and improved reliability of distribution service in the Woodbridge area
bordering the City of Lodi would be a benefit to the area's economy.
G. Woodbridge Irrigation District would become a potential new wholesale customer for surplus Lodi electric
power, achieving the Council's stated goal.
City staff has been meeting with PG&E's engineering staff with respect to design aspects of the proposed project.
FUNDING: Electric Utility Department Operating Fund
Initial Cost: $311,000. These costs will be repaid with interest by the Woodbridge Irrigation
District.
Prepared by: Nancy Bougher, Senior Electric Utility Rate Analyst
Funding Approval:
Vicky McAthie, Finance Director
ANVINB/Ist
c: City Attorney
wpd
Alan N. Vallow
Electric Utility Director
AGREEMENT FOR THE PROVISION OF
ENGINEERING AND CONSTRUCTION SERVICES
This Agreement is entered into by Woodbridge Irrigation District, a California irrigation
district (Woodbridge) and the City of Lodi, a California municipal corporation (Lodi). The
purpose of this Agreement is to provide for the design and construction of distribution
facilities by Lodi on behalf of Woodbridge to allow Woodbridge to provide electric
distribution service to Sebastiani Wineries. The Project consists of the design and
construction of a 12kV line interconnected with the Lodi Electric Utility at Sargent and
Lower Sacramento Roads and serving Sebastiani Winery's Vengange and Nathanson
Creek facilities in Woodbridge. Lodi will provide design, construction and related services
necessary to ensure the timely completion of the Project. Woodbridge will compensate
Lodi as outlined below.
PROJECT SERVICES
The Project entails the design and construction of an overhead 12kV distribution line to
provide electric services to Sebastiani Wineries. The line will interconnect with the Lodi
electric system at Sargent and Lower Sacramento Roads. The line will run along Sargent
Road to Ray Road as joint pole use with existing Pacific Gas and Electric (PG&E)
distribution facilities. The line will then continue northerly as underbuild on an existing
PG&E 60kV wood pole transmission line to the Woodbridge Irrigation District canal
(approximately one-half mile). At this point the line will divide. One branch will continue
northerly crossing the Union Pacific Railroad line and along the easterly fence line of
Sebastiani Vendange Winery to Turner Road, then westerly on Turner Road as joint pole
use on existing PG&E distribution line to the service entrance pole (approximately 350 feet
westerly) at Service A. The other branch will be underbuild on the existing 60kV PG&E
transmission line westerly to the Sebastiani Nathanson Creek Winery (approximately one-
half mile) and then northerly one span to the service entrance pole at Service B. The line
will include a recloser and metering facilities at the point of interconnection with the City
of Lodi system at Sargent Road west of Lodi Avenue. A capacitor bank (600kVar) will be
installed on Sargent Road in the vicinity of DeVries Road. Primary metering facilities will
be installed at service points A and B. The line will be connected to the customer's service
entrance equipment at the existing riser and padmount disconnect switch at Sebastiani
Vendange Winery and at the customer installed disconnect switch and recloser at
Sebastiani Nathanson Creek Winery.
Lodi shall, on behalf of Woodbridge, (1) prepare all engineering and design documents
and shall obtain all materials necessary for construction of the Project. At the completion
of the Project Lodi shall also prepare and deliver to Woodbridge copies of all engineering
19981cou no! Rcomm u nications1030498cc4A
documents, drawings and specifications prepared by Lodi as part of the Project; (2) obtain
necessary easements, encroachment permits and right-of-ways. Woodbridge shall provide
their full cooperation in obtaining these easements; and (3) prepare and submit required
documentation for review and approval by PG&E and the Northern California Joint Pole
Association (NCJPA).
Woodbridge agrees: (1) To obtain membership in the Northern California Joint Pole
Association by March 15, 1998. Woodbridge recognizes that failure to obtain membership
by this date could result in significant delays in obtaining approvals necessary to
commence construction. If Woodbridge is not able to obtain NCJPA membership by this
date, Woodbridge will promptly notify Lodi of the delay and any projected date for
obtaining membership. Woodbridge agrees to hold Lodi harmless for damages caused
by delays in obtaining NCJPA membership. (2) Obtain final regulatory and legal approvals
from the San Joaquin Local Area Formation Commission (LAFCO) prior to the scheduled
start of construction, May 1, 1998. Woodbridge recognizes that failure to obtain final
LAFCO approval by this date may result in delays in the agreed upon Project schedule.
Woodbridge agrees to hold Lodi harmless for damages caused by delays in obtaining final
LAFCO approval prior to start of construction. (3) Obtain final California Environmental
Quality Act (CEQA) clearance for all activities related to the construction and operation of
the Project.
PROJECT SCHEDULE
March 15, 1998 Engineering design work completed, sent to NCJPA/PG&E for review
and approval
March 18, 1998 Material bids returned, evaluated, ready for Council. Council to
award material bids.
April 15, 1998 Design review completed by PG&E
May 1, 1998 Begin Line Construction
June 1, 1998 Energize 12kV Line
COMPENSATION AND PAYMENT TERMS
Total compensation, excluding interest, for Project Services described in this Agreement
shall be $311,000. This shall include all design, construction and related services
described in this Agreement. Woodbridge shall make monthly payments. Payments will
be calculated at $0.00526 multiplied by Woodbridge KWH usage as metered at the Lodi-
19981counciRcommunications1090498cc4A 2
Woodbridge interconnection point. The actual portion of the payment applied to principal
and interest shall be calculated monthly and interest shall be charged equal to the rate
obtained by the Local Area Investment Fund on the first day of each billing period. Lodi
shall issue an invoice by the fifteenth day of each month after completion of the Project
based on usage for the previous calendar month. Invoices shall be payable within thirty
(30) days after the invoice date. Payments will cease when the principal amount and all
applicable interest has been paid in full. Any principal balance outstanding at the end of
eighty-four (84) months shall be invoiced in full to Woodbridge and shall be due and
payable within thirty (30) days after the invoice date. Woodbridge may elect at any time
to prepay all or any portion of the principal balance.
LATE PAYMENTS
If Woodbridge objects to all or any portion of an invoice, Woodbridge shall notify Lodi
within seven (7) calendar days of invoice date, identify cause of disagreement, and pay
when due, that portion of the invoice not in dispute. All outstanding balances will accrue
a finance charge of one and one-half percent (1.5%) per month for each month the invoice
is outstanding.
ADDITIONAL SERVICES
Lodi agrees to provide to Woodbridge operations and maintenance services,
interconnection rights and access to market priced power. Negotiations for these services
shall commence immediately upon signing of this Agreement and shall be concluded at
the earliest possible date. Payment for these services shall be separate from payment for
the Services described in Project Services above.
STANDARD OF CARE
All design and construction work will be performed in accordance with the standards,
regulations and procedures set forth in General Order #95 (G.O. 95) from the State of
California Public Utilities Commission. The City of Lodi Electric Utility Department shall
provide tree trimming necessary for the proper clearances mandated by G.O. 95. Any
required trimming of trees will be trimming that would normally occur for proper
maintenance of power line easements. All trimming of oak trees shall be in compliance
with applicable governmental regulations and ordinances. New wood poles installed as
part of the Project will be taller than existing poles and may result in less trimming.
OWNERSHIP AND REUSE OF DOCUMENTS
1998\council\communicatons\03D498cc4A 3
Except as otherwise provided herein, engineering documents, drawings and specifications
prepared by Lodi as part of this Agreement shall become the property of Woodbridge upon
completion of work and payment in full of all monies due to Lodi; provided, however, that
Lodi shall retain the unrestricted rights to their use and shall retain all common law,
statutory, copyright, and other reserved rights.
Woodbridge shall not reuse or make any modification to any and all documents prepared
by Lodi, including, but not limited to, engineering documents, drawings and specifications
(the "documents") without the prior written authorization of Lodi. Woodbridge agrees, to
the fullest extent permitted by law, to indemnify and hold Lodi harmless from any claim,
liability or cost (including reasonable attorneys' fees and defense costs) arising or
allegedly arising out of any unauthorized reuse or modification of the documents by
Woodbridge or any person or entity that acquires or obtains the documents from or
through Woodbridge without the written authorization of Lodi.
Submission or distribution of documents to meet official regulatory requirements or for
similar purposes in connection with the Project is not to be construed as publication in
derogation of Lodi's reserved rights.
INDEMNIFICATION
Lodi agrees, to the fullest extent permitted by law, to indemnify and hold Woodbridge
harmless from any damage, liability or cost (including reasonable attorneys' fees and costs
of defense) to the extent caused by Lodi's negligent acts, errors or omissions in the
performance of professional services under this Agreement and those of Lodi's employees,
subcontractors, consultants or anyone for whom Lodi is legally liable and arising from the
Project that is the subject of this Agreement. Lodi is not obligated to indemnify
Woodbridge in any manner whatsoever for Woodbridge's own negligence.
Woodbridge agrees, to the fullest extent permitted by law, to indemnify and hold Lodi
harmless from any damage, liability or cost (including reasonable attorneys' fees and costs
of defense) to the extent caused by Woodbridge's negligent acts, errors or omissions and
those of Woodbridge's employees, contractors, subcontractors or consultants or anyone
for whom Woodbridge is legally liable, and arising from the Project that is the subject of
this Agreement.
NON-PERFORMANCE
Should Lodi fail to perform its obligations as described in this Agreement for reasons other
than those detailed below, Lodi agrees to pay Woodbridge liquidated damages equal to
Woodbridge's actual damages for failure to provide service to Sebastiani.
19981council%communications\030498cc4A 4
Lodi shall not be liable for unforeseeable actions or for acts beyond its control such as acts
of God, sudden actions of the elements, actions or inactions by federal, state or municipal
agencies, and actions or inactions of legislative, judicial, or regulatory agencies.
Lodi shall not be liable for any failure of Woodbridge perform any of its responsibilities as
described in Project Services.
Lodi shall make all reasonable efforts to ensure that the engineering design review
process is concluded as scheduled. However, Woodbridge shall not hold Lodi liable the
failure of PG&E/NCJPA to provide essential data or complete their engineering design
review in a timely manner.
TERMINATION OF SERVICES
This Agreement may be terminated by Woodbridge with five (5) days written notice. In the
event of such termination Woodbridge shall pay Lodi for all services rendered from the
date of the Agreement to date of termination, all related expenses, and all termination
expenses.
SUCCESSORS AND ASSIGNS
Woodbridge and Lodi each binds itself and its partners, successors, executors,
administrators, assigns and legal representatives to the other party to this Agreement and
to the partners, successors, executors, administrators, assigns, and legal representatives
of such other party, in respect to all covenants, agreements, and obligations of this
Agreement. This Agreement shall not be assigned by either party without the other party's
express written consent. However, Lodi shall be entitled to subcontract portions of its work
to other companies without first obtaining the written consent provided for under this
Article.
EEO COMPLIANCE
Lodi and Woodbridge expressly agree not to discriminate against any employee or
applicant for employment because of race, color, religion, gender, sexual orientation.
national origin, or disability and shall during the performance of this Agreement comply
with all applicable Executive Orders and federal regulations.
MEDIATION
1998+,coundhcommunications%030498=4A 5
All claims, disputes or controversies arising out of, or in relation to the interpretation,
application or enforcement of this Agreement, which cannot be first settled through direct
discussions, shall be submitted to mediation under the Commercial Mediation Rules of the
American Arbitration Association. Woodbridge and Lodi agree to share the costs for such
mediation services on an equal basis. Nothing contained in this paragraph shall preclude
the parties to this Agreement from pursuing other means of dispute resolution either
concurrently or subsequent to the mediation process. In the event any dispute is resolved
by court order, then the prevailing party shall be entitled to its attorney's fees and all
related costs, as ordered by the court, including costs and attorney's fees incurred on
appeal.
APPLICABLE LAWS
This Agreement shall be governed by the laws of the State of California.
By: By:
Anders Christensen H. Dixon Flynn
Woodbridge Irrigation District City Manager
Date: Date:
APPROVED AS TO FORM:
Al az._
Wall A. Ha
City Attorney
1998�councillcommunications\A30498ce4A 6
ATTEST:
Alice M. Reimche
City Clerk
RESOLUTION NO. 98.39
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
THE CITY MANAGER TO ENTER AN ENGINEERING AND
CONSTRUCTION SERVICES AGREEMENT BETWEEN THE CITY
OF LODI AND THE WOODBRIDGE IRRIGATION DISTRICT (WID)
BE IT RESOLVED, by the City Council of the City of Lodi that the City Manager
is hereby authorized and directed to execute an Engineering and Construction Services
Agreement with the Woodbridge Irrigation District (WID) on behalf of the City of Lodi.
Dated: March 4, 1998
I hereby certify that Resolution No. 98-39 was passed and adopted by the Lodi
City Council in a regular meeting held March 4, 1998 by the following vote:
AYES:
Council Members - Johnson, Land, Mann and Sieglock (Mayor)
NOES:
Council Members - None
ABSENT:
Council Members - None
ABSTAIN:
Council Members - Pennino
OLICZEWMAEMICHE
City Clerk
4-111c o