HomeMy WebLinkAboutMinutes - July 16, 2002 SSCITY OF LODI
INFORMAL INFORMATIONAL MEETING
"SHIRTSLEEVE" SESSION
CARNEGIE FORUM, 305 WEST PINE STREET
TUESDAY, JULY 16, 2002
An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held Tuesday,
July 16, 2002 commencing at 7:01 a.m.
A. ROLL CALL
Present: Council Members — Hitchcock, Howard, Land, Nakanishi (arrived at 7:05 a.m.),
and Mayor Pennino
Absent: Council Members — None
Also Present: City Manager Flynn, City Attorney Hays, and Deputy City Clerk Perrin
Announcements
Mayor Pennino wished a speedy recovery to Council candidate, Don Lindsay, who will be
undergoing heart surgery later this week.
B. CITY COUNCIL CALENDAR UPDATE
Deputy City Clerk Perrin reviewed the weekly calendar (filed).
C. TOPIC(S)
C-1 "Central City Railroad Safety Improvement Project Update"
NOTE: Council Member Nakanishi arrived at 7:05 a.m.
Public Works Director Prima directed Council's attention to the revised background
material (filed) regarding this morning's subject. The Central City Railroad Safety
Improvement Project has been on-going for quite some time, but recent negotiations have
brought the City much closer to arriving at a plan to remove the tracks on Lodi Avenue.
Charlie Swimley, Senior Civil Engineer, provided a recap of the project goals:
• Improve rail safety in Lodi by removing the tracks on Lodi Avenue, removing 15
crossings, and installing a pedestrian crossing at Calaveras Street to funnel school
children to Lawrence School.
• Improve the pavement surface on Lodi Avenue. Staff plans to pave over the existing
tracks and in the future do a complete street reconstruction.
• Encourage redevelopment of the Lodi Avenue corridor.
• Secure reliable railroad service to Lodi.
• Improve Lockeford Street.
The project proposes the reconstruction of the north wye, (Kentucky House Branch
railroad), which is in need of repair. To create a clearance, it is necessary to move tracks
and construct an interchange yard, consisting of four tracks. The plan also calls for the
construction of a pedestrian barrier and crossing at Central Avenue and Calaveras Street
for children to cross safely, with new signal crossings at the north wye and at Stockton
Street and upgrades at Washington Street, Cherokee Lane, Guild Avenue, and Cluff
Avenue. Rail and ballast/base replacements and upgrades will be made at the Kentucky
House Branch, and additionally the tracks will be realigned to accommodate areas for
future road widening. A new curve will be created to connect the Kentucky House Branch
to the existing Central California Traction (CCT) lines, running north and south through
town. Initially the plan calls for the tracks on Lodi Avenue to be paved over, the
reconstruction of the new switching facilities east of Highway 99 on Lodi Avenue, and the
abandonment of the Beckman Road crossing, which would allow for a new driveway
entrance into the K -Mart shopping center.
Continued July 16, 2002
In response to Council Member Howard, Mr. Swimley stated that the pedestrian crossing
will be on a smaller and simpler scale and will include lights.
Mayor Pro Tempore Hitchcock questioned why the Lockeford Street widening, included
on the original Shirtsleeve enclosure, was removed from the plan.
Public Works Director Prima replied that an old City plan shows four lanes on Lockeford
Street; however, this plan is based on old projections that need to be updated. The scope
would not allow for the full widening, and staff felt that bringing this into the plan now
would be unnecessary and would complicate the environmental review process — it would
be best decided at a later time. Mr. Prima assured that the Lockeford Street widening has
not been dropped from the City's master plan.
Mr. Swimley reminded Council that in December 2001, the City Council authorized a
consultant to proceed with Phases 1 and 2 of the project. Phase 1 included the
preliminary engineering, mapping, and cost estimate for the preparation of the
Memorandum of Understanding (MOU) with the railroads. Phase 2 was for the
preparation of the MOU. Both phases are nearing completion. Staff has had three
meetings with the railroad on this project, and the news is very encouraging. The
railroads have also participated in the preliminary design and have committed to assisting
the City by 1) providing right-of-way for road purposes, and by 2) requiring tenants to
relocate existing utilities for the switchyard north of Lockeford Street, which could result in
a savings to the City of $2 million.
The City Council previously authorized $240,000 for Phases 1 and 2 of the railroad
improvements (preliminary design work). The final design estimate is $500,000, which
includes completion of the engineering details and assembling a biddable project to
secure prices. The construction work is estimated at $7.3 million. The Lodi Avenue
reconstruction project estimate of $3 million is subject to change, as a decision will need
to be made on the streetscape and whether the City paves over the tracks or rebuilds.
This estimate is similar to a typical downtown street reconstruction project.
In answer to Mayor Pro Tempore Hitchcock, Mr. Prima stated that the original background
material was amended to include the $3 million estimate in order to provide a budget that
would allow for whatever enhancements might be desired. The City could do a rebuild for
a cost of two-thirds less. Mr. Prima believed that the original submittal to the San Joaquin
Council of Governments (SJCOG), which enabled the City to secure funding for the
project, included the reconstruction of Lodi Avenue. However, the Lockeford Street
widening was described as a future phase to the project, and not having this included in
the project should not jeopardize the City's funding.
Mayor Pennino indicated that prior to any decisions by the Council regarding Lodi Avenue
reconstruction, the City would conduct public hearings to obtain citizen, staff, and Council
input.
Public Works Director Prima confirmed that immediately after receiving approval from the
railroad, staff will cover up the tracks with a thin layer of asphalt, similar to the Main Street
tracks, which is not a long-term solution.
Mayor Pennino reiterated that the first priority is the safety issue of getting the tracks
covered; whereas, the Lodi Avenue reconstruction project will take time and public input.
This will not be a simple project in regard to the street closures as many businesses along
Lodi Avenue will be affected.
NOTE: Mayor Pro Tempore Hitchcock left the meeting at 7:26 a.m.
Mr. Swimley stated that Measure K grant funds cover $6.7 million of the project ($2.8
million from the Congestion Relief fund; and $3.9 million from the Railroad Crossing
Safety fund). Funding of $4.4 million is still to be determined. Staff will attempt to secure
additional funds from SJCOG, and some may come from the street funds.
2
Continued July 16, 2002
The first goal for the project is to finalize the MOU with the railroads. Staff believes that
one more meeting with the railroads is necessary to agree on the right-of-way transfer
and on when Lodi Avenue can be paved over. Next, the consultant will be authorized to
proceed with the final design and begin the bidding process. Subsequently, the Lodi
Avenue tracks will be paved over as a temporary improvement, with the total street
reconstruction plan to be decided in the future.
Staff will then continue to work on securing the additional $4.4 million for the project and
complete the final railroad design. The railroad design will then be turned over to CCT to
bid the project and oversee the rail construction. CCT will bid the project with railroad
contractors, which will save the City money.
Future phases include establishing design theme and reconstruction for Lodi Avenue, the
K -Mart shopping center entrance (which may be completed sooner in the project), and
improvements to the Lockeford Street corridor.
Mr. Swimley presented photographs of the existing conditions on Lodi Avenue, which
demonstrate the uneven and rippling pavement, and on Stockton and Lockeford Streets,
showing the uneven grade. Diagrams were also displayed showing the subject right-of-
way, which the City is attempting to obtain from Union Pacific (UP), the switching facilities,
railroad tracks proposed for construction, and connecting curves.
Public Works Director Prima stated that the elimination of the Beckman Road crossing
was an option in previous discussions, and staff felt this was worthwhile to do because it
eliminates a safety hazard. Regardless, this crossing needs to be improved. The
interchange on Lockeford Street is a new element and does involve UP. He hopes to
negotiate some cost savings on this by getting UP to agree that the City only pay what it
would cost to have a contractor do the work versus UP's labor overhead rates. In addition
fiber optic cabling and fuel pipelines need to be relocated at the tenants' expense. The
railroads intend to create an "island operation" and abandon the track between Stockton
and Lodi one mile east of Highway 99; although, due to one customer on the east side of
99, the railroads cannot abandon the trestle across Highway 99. Creating an island
operation solidifies the provision of rail service in Lodi in that the City will have a direct
connection to the main line and will not be dependent on CCT to maintain the line in the
future. Mr. Prima added that years ago there was talk about CCT being disbanded, but
with the industrial growth on the east side, CCT is very interested that the operation in
Lodi stays viable.
In reply to Council Member Nakanishi, Mr. Prima stated that a majority of the railroad -
related deaths have occurred on the main UP line in the downtown area and a few by
Turner Road. These areas would not be affected by this project. Further, Mr. Prima
responded that there would be an increase in railroad traffic on the Kentucky House
Branch and a slight increase in the downtown area. The Kentucky House Branch is not
being used now; therefore, this project would create new traffic. CCT's operation is
servicing customers and taking cars to the main line. In regard to delays, this project will
not affect the Lodi Avenue and main line tracks.
In reply to Council Member Land, Mr. Prima stated that there will be longer delays on
Lockeford Street, due to trains on the main line that are using the switchyard, which will
be slowing down and crossing. Mr. Prima confirmed that no additional property will be
acquired; however, every square inch of existing property will be used and a retaining wall
will be built on the east side. The track connection on the Turner Road underpass cannot
accommodate a longer pass, and changing this in the plan substantially increased the
cost estimate. Steps are being taken to minimize delays by installing a power switch to
electronically activate the switch, rather than the engineers having to stop and get out.
The switchyard will go almost to Turner Road. Mr. Prima stated that the switchyard in the
downtown area will most likely not be abandoned.
Mayor Pennino suggested that staff pursue funding to abandon and relocate the existing
public switchyard south of Elm to Lockeford Street.
Continued July 16, 2002
Council Member Howard stated that she was glad that CCT will continue to provide
service because of the need and viability in the industrial area.
Mayor Pennino commended staff on a great job and urged that it continue to keep the
pressure on.
D. COMMENTS BY THE PUBLIC ON NON -AGENDA ITEMS
None.
E. ADJOURNMENT
No action was taken by the City Council. The meeting was adjourned at 7:45 a.m.
ATTEST:
Jennifer M. Perrin
Deputy City Clerk
4
Lodi Central City Railroad Safety
Improvement Project
July 16, 2002
Lodi Central City Railroad Safety Improvement Project
LODI CENTRAL CITY RAILROAD SAFETY IMPROVEMENT PROJECT
U.O -1s. JLC Plee D' LEGEND
sofas Construct qxxx
— — Existing tracks o
E a — — Existing tracks proposed p.R Interchange and 9 P P -a
,Y o to be abandoned O
switching facilities o (—
Railroad wants o 1 stadium Proposed new track O U
to retain north N 1 a. connection o I U
Existingtrack to be 'a
segment of wye O ZMpo New Pedestrian reused "
1- 1 P°rtp i-l.a Crossing with ai1® Improved crossing surface Track
gates and barriF—
UP i IF D gO RR preempt reefmptsignal with abandoned
�+ Festival GroundsL i
WOODBRIDGE � ST. esr S. p R. R. east of C(
BRANCH
To General
}}II Mills
I r�
Sid
ely Milli.moa
city Hmr
EJ o0
❑❑
E I d
T
®❑ I
"WL ",I r.AFHedestrion
r 3 UP KENTUCKY HOUSE BRANCH
e ei reactivate — currently not in use
e e PWU L� barrier, frontagefill ED 3
improvements along
❑ Railroad Ave. @ RR R/W PINE ST
�❑°000
�
�Lisir.
❑\
,Fa�e,n , New driveway to
C�
K—Mart Center
SeheW
Previously
Abandoned
�.
Newq 51.
fl<a"oed 51. Ra.
� s
G � � • 5� 3 C,' — �
m
%%-M M
Pedestrian barrier• frontage improvements
along RR R/W & N. side of Hwy 12.
2
IA:,TP/,FFI(: LCt:rOiLdv:, 12 1;1 :11 .<. .
Project Background
• December 2001, Council Authorized
Consultant To Proceed
— Phase 1 -Preliminary Engineering, Mapping
and Cost Estimating
— Phase 2 -Prepare Memorandum of
Understanding (MOU) with Railroads
• Both Phases are nearly complete
Lodi Central City Railroad Safety Improvement Project 3
Project Background (Cont.)
• Three Meetings with the Railroads Since
January
• Railroads Participated in Preliminary
Design
• Railroads have committed to assist by:
— Providing Right -of-Way for Road Purposes
— Require Tenants to relocate exist utilities if
needed
Lodi Central City Railroad Safety Improvement Project 4
Project Funding
• Total Estimated Project Costs (Rail Only)
- $8.1 Million
Funding Sources
— Measure K Grant Funds
• $2.8 Million - Congestion Relief
• $3.9 Million - Railroad Crossing Safety Funds
• $6.7 Million - Total Grant Funds Reserved
— Measure K Maintenance & Local Street Fees
• $1.4 Million
Lodi Central City Railroad Safety Improvement Project 6
What's Next?
• Finalize / Execute MOU
— One more meeting required with Railroads
— Agree on Right -of -Way Transfer
— Agree on when Lodi Avenue Can be Paved
Over
• Authorize Consultant to Proceed with Final
Design
— Final Design Cost: $500,000
— Design Schedule: 6 Months
Lodi Central City Railroad Safety Improvement Project 7
What's Next? (Cont.)
• Pave Over Lodi Avenue
— Temporary Improvement
— Total Street Reconstruction in Future
• Secure Additional Measure K Funds
— Approximately $1.4 Million
Lodi Central City Railroad Safety Improvement Project 8
OP
cn
n
0 0
Cid
^4
I�
F2
Future Phases
• Establish a Design Theme for Lodi Avenue
• Reconstruct Lodi Avenue
— Add Driveway Into K -Mart Shopping Center
• Widen Lockeford Street
— 4 Lanes
— Construct Pedestrian Barriers
— Pedestrian Crossing at Calaveras Street
Lodi Central City Railroad Safety Improvement Project 10
Recap of Project Goals
• Improve Rail Safety in Lodi
• Improve Pavement Surface on Lodi Avenue
— Initially Pave Over Existing Tracks
— Future Street Reconstruction for Lodi Avenue
• Encourage Redevelopment of Lodi Avenue
Corridor
• Secure Reliable Railroad Service to Lodi
Industry
• Widen Lockeford Street
Lodi Central City Railroad Safety Improvement Project 11
Questions &Answers
Lodi Central City Railroad Safety Improvement Project 12