HomeMy WebLinkAboutAgenda Report - February 4, 1998 H-01CITY OF LODI COUNCIL COMMUNICATION
AGENDA TITLE: Hutchins Street Square Conference and Performing Arts Center Project Update
MEETING DATE: February 4, 1998
PREPARED BY: Public Works Director and Community Center Director
RECOMMENDED ACTION: Information only.
BACKGROUND INFORMATION: The City Council, at its November 6, 1996 meeting, awarded the
contract for the Hutchins Street Square Conference and Performing
Arts Center Project to F & H Construction, of Stockton, in the
amount of $8,262,010. At the time of the award, the Council
appropriated funding from the $10 million Certificates of Participation (COP), issued July 22, 1996, and
anticipated construction fund interest earnings, for a total project estimated need of $10,050,000. This
included construction contingency moneys of $948,100, or about 11.5%, and assumed that interest
earnings would be approximately $450,000.
The construction project has gone extremely well. F & H Construction has been an excellent
contractor, and a true "partnering" relationship exists between them and City staff in keeping the project
on schedule and within budget. Thirteen project goals (Exhibit A) were established at the beginning of
the project through a partnering session that was attended by all "stakeholders", including City staff,
contractor and subcontractors, architects, consultants and engineers. Most, if not all, of these goals will
be met or exceeded. A key player for the City is our onsite Construction Manager, Gary Wiman, who
oversees the project full time and deserves much of the credit for keeping us on task. The remodel of
the existing multipurpose and theater buildings, plus the addition of backstage facilities, rotunda, and
connecting galleries, is now almost complete. The contract completion date is March 29, 1998.
Project change orders to date total $136,525. This is offset, however, by a $130,794 deduct identified
through a value -engineering process done at the outset, where the contractor and subcontractors had
an opportunity to suggest more cost-effective ways to accomplish the design intent. The net change
order amount to date is just $5,730. Change orders to the end of the project are expected to cost about
$50,000. The total of all change orders anticipated to project close out is $55,731, only .67% over the
original contract amount. A change order percentage this low (only two-thirds of one percent), especially
on a project of this magnitude, is exceptional and deserves recognition.
The architectural firm of Wenell Mattheis Bowe should be recognized for their quick response, attention
to details, and overall commitment to the project. The addition of the amphitheater, furniture design and
landscaping detail has been added to their project scope.
At the time of the contract award, several portions of the project were deferred or left out to ensure that
adequate moneys were available. Now that the end of the work is in sight, we need to move forward
with those portions as quickly as possible. Our intent is to issue change orders and utilize
APPROVED:
H. Dixon Flynn -- City Manager
Cupdate.doc' 01/27/98
Hutchins Street Square Conference and Performing Arts Center Project Update
February 4, 1998
Page 2
F & H Construction and as many subcontractors currently on the job as possible to accomplish these
project additions. The Old LUHS Site Foundation has committed to raising significant amounts of money
to make many of these needed items happen. The Foundation has raised over $200,000 for theater
seating (fixed and handicapped), has a $120,000 commitment from F & H Construction to build the porte
cochere as a donation, and is actively pursuing gifts from the community to repay the debt service. Other
proposed project additions are: theatrical lighting, drapes, orchestra shell, data/communication wiring,
security systems, site and building signage, landscaping, amphitheater, furniture, staff office/Fine Arts
retrofit, and activity field fencing (for Camp Hutchins). The total estimated dollars needed is
approximately $1 million.
The Finance Director and the City Manager have estimated that the total of both actual and anticipated
interest earnings available by the completion of the project will be approximately $910,000, about
$460,000 more than originally planned. This brings the total available funds to $10,510,000. The original
contract amount of $8,262,000, plus the anticipated change orders to the end of the project at $55,731,
plus the project additions and professional services fees can be accomplished within the funds available.
The Hutchins Street Square Conference and Performing Arts Center, when completed, will be one of the
premier facilities of its type in the area. It is truly a dream about to become reality; a unique partnership
between the City and the Foundation. We can all share in this success.
FUNDING: From the $10 million Certificates of Participation (COP), issued July 22, 1996, and
anticipated construction fund interest earnings, as approved by the Council on
November 6, 1996.
Jack L. Ronsko Charlene Lange
Public Works Director Community Center rector `
Prepared by Dennis J. Callahan, Fleet and Facilities Manager
JLR/DJC/CUlm
Attachment
cc: City Engineer
Finance Director
Fleet and Facilities Manager
Construction Manager
F & H Construction
Wenell Mattheis Bowe - Tim Mattheis
Old LUHS Site Foundation Board
EXHIBIT A
HUTCHINS STREET SQUARE
CONFERENCE AND PERFORMING ARTS CENTER
PROJECT PARTNERING SESSION
NOVEMBER 13, 1996
The project stakeholders were asked to develop a list of project goals in
which all participants can endorse. The results of this work are listed below:
1. No lost -time accidents.
2. Meeting or bettering all stakeholders' budgets through a
commitment to efficiency.
3. Meeting or exceeding the established project schedule.
4. Each project participant will take pride in the work.
5. The project will be completed so as to meet the high public
expectation for this project.
6. Commitment to remain friends and respect each other
throughout the project.
7. Use this job to create future opportunities.
8. Resolve conflict quickly, without litigation.
9. No back charges and no rejected work.
10. Reasonable and fair treatment in change order negotiation,
with a target of 5% to 7% total change orders.
11. All stakeholders agree to attend and participate in the weekly
progress meetings.
12. Payments will be made to the General contractor within
10 days of approved progress payments. Subcontractors will
be paid within 10 days of receipt of the City payment.
13. All stakeholders commit to be proactive in the problem -
solving process.
CUPDATEEXA.DOC