HomeMy WebLinkAboutMinutes - May 29, 2001 SSCITY OF LODI INFORMAL INFORMATIONAL MEETING "SHIRTSLEEVE" SESSION CARNEGIE FORUM, 305 WEST PINE STREET TUESDAY, MAY 29, 2001 An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held Tuesday, May 29, 2001 commencing at 7:03 a.m. A. ROLL CALL Present: Council Members — Hitchcock (arrived at 7:10 a.m.), Howard, Land, Pennino (arrived at 7:05 a.m.) and Mayor Nakanishi Absent: Council Members — None Also Present: City Manager Flynn, City Attorney Hays, and City Clerk Blackston B. CITY COUNCIL CALENDAR UPDATE Reading of the weekly calendar (filed) was waived. C. TOPIC(S) C-1 "Review of Capital Improvement Budget Requests" City Manager Flynn noted that in addition to the packet material, the Council has received a General Fund Capital statement (filed). The long-term, 10 -year financial plan was included in the packet; however, the print is very small and a more legible replacement copy will be distributed to Council at a later date. Deputy City Manager Keeter reported that the packet information includes additions and revisions to projects. The first project is the Public Safety Building and Civic Center Complex designated reserve. She asked that this be added to the overall budget packet and considered as page 1A. The project includes interim measures to the current building, the air conditioning, and boiler. The new police station was designated as a highest priority project in the last fiscal year and it is currently in the design phase. Staff anticipates returning to Council next September or October with the final design presentation. The next phase would be to construct a parking structure just to the east of the fire station and City Hall, which could be done concurrently with the construction of the new police building. The final phase would be the renovation of the old public safety building to house fire administration, Fire Station 1, and possibly the departments of Finance, Public Works, and Community Development. Staff recommends designating $1.5 million under the capital budget. The project cost is currently estimated at $19.2 million. City Manager Flynn clarified that the $1.5 million will be taken out of the capital budget and placed in a separate fund. Referencing page 1A, he noted that construction cost under Phase II of the project begins to occur in 2001-02. The project will not be completed until 2002-03, so the first payment that will occur is in 2003-04. If the money was borrowed this Fall and it took three years to complete construction, payments would begin at the time of completion. He estimated a cost of $800,000 per year. Discussion ensued regarding whether or not to use the $1.5 million to pay for the design work, and loan considerations for the projects. City Manager Flynn stated that staff will come back to Council later this summer with financing recommendations. Ms. Keeter continued her report and referenced page 40 of the packet material. She noted that it includes a revision and asked Council to replace this page in their original budget document. Parks and Recreation Director Baltz has requested an increase of $775,000 for construction costs in year two of the Aquatics Center development. The total cost of this project is currently estimated at $3 million. Continued May 29, 2001 Page 42 relates to the Indoor Sports Center and Ms. Keeter asked Council to replace this page in their original budget document as well. The original cost estimate for this project was $135 per square foot for a 30,000 square foot building. Mr. Baltz now estimates that it will cost $175 per square foot, increasing the cost to $500,000 in year one of the budget and $5.2 million in year two. Mr. Baltz has begun the process of developing a Request for Proposals for a conceptual design of both the Indoor Sports Center and the Aquatics Center. Page 46A was added at the request of Mayor Pro Tempore Pennino for the Lodi Lake central area improvements. This page replaces page 38 of the original budget document. The project has been increased to include improvements to the west 13 acres. The overall cost estimate is $1.2 million. Page 58A is an added page to the budget document, which relates to the Civic Plaza Veterans Monument. A final design presentation will be given to Council at the June 6 regular meeting at which time a request will be made for $450,000 to complete the project. City Manager Flynn reviewed the General Fund Capital handout. Ms. Keeter referenced the 'blue sheet' handout (fled) for a telephone systems upgrade. She explained that the City is at capacity with the current phone system, voice mail component, and ports. The request is being made to upgrade the main PBX to allow increased capacity and the ability to connect to Fire Station 4 when it is completed. The cost of $55,000 is recommended for year one. Ms. Keeter then drew Council's attention to the Vehicle Replacement Requests document provided for informational purposes. She explained that requests go through the Fleet Committee for recommendation to the City Manager. Vehicle replacement is funded from various sources, $425,000 of which comes from the equipment fund, and $738,000 from other funds. The City of Lodi draft Mission Statement was reviewed and considered by Council. Following discussion, Council consensus was to amend the statement as follows: "The City of Lodi's purpose is to enhance the quality of life for Lodi residents, reflecting our high community standards." Mayor Pro Tempore Pennino announced that the Habitat and Open Space Plan won first place from the National Association of Regional Councils. He will be absent at the June 5 Shirtsleeve Session to attend the awards ceremony in Omaha. D. COMMENTS BY THE PUBLIC ON NON -AGENDA ITEMS None. E. ADJOURNMENT No action was taken by the City Council. The meeting was adjourned at approximately 7:40 a.m. ATTEST: Susan J. Blackston City Clerk K Mayor's & Council Member's Weekly Calendar- - WEEK OF MAY 29, 2001 Tuesday, May 29, 2001 7:00 a.m. Shirtsleeve Session 1. Review of Capitol Improvement Budget Requests 5:30 p.m. Special Council Meeting, (NOTE: Meeting will be Cez The Merlot) 1. Review of Downtown Lodi Business Partnership's (OLSP) Signif icant Expenditure Request Wednesday, May 30, 2001 9:30 a.m. Nakanishi. Groundwater Banking Authority Coordinating Committee meeting, Public Works Building — Conference Room A, 5tockton. 5:30 p.m. Special "Town Hall" Meeting 1. Discussion regarding 2001/03 Financial Plan and Budget Thursday, May 31, 2001 6:00 - 8:15 a.m. The Greater Lodi 2001 Leadership Prayer Breakfast, Hutchins Street 5quare -- Kirst Hall. Friday, June 1, 2001 Saturday, June 2, 2001 8:00 - 3:00 p.m. Lodi Energy Fair, Lodi Grape Festival Grounds — Chardonnay and Zinfandel Halls, Sunday, June 3, 2001 Monday, June 4, 2001 Disclaimer: This calendar contains only information that was provided to the City Clerk's office counc i I\misclmcalndr.doc 2001-03 FINANCIAL PLAN & BUDGET CAPITAL BUDGET DETAIL BY ACTIVITY 05/23/01 I2001-02 2002-03 ° Requested City Manager Requested City Manager Cost Recommended Cost R000mmeodod Comments Public Safety Police Department la Public Safety Building Information Systems 1 Personal Computer replacement plan Animal Shelter 2 animal Shelter Expansion 3 3/4 Ton CNG truck Fire Department Emergency Services 4 Tools & Equipment for Quint 5 Rescue trailer & equipment 6 1 1/2 Ton Truck to pull command center Total Public Safety Public Utilities Wastewater Utility Services 7 Purchase Pipe Inspector System 8 Wastewater - White Slough Facility Upgrade 9 White Slough Capital Maintenance Electric Utility Services 10 Upgrade server Electric Utility 12 Electric New Building Electrical Engineering & Operations 13 Personal computers replacement 15 Engineering Analysis & Design software Electric Construction & Maintenance 17 Line Extensions 18 Distribution System Improv 20 Substation Construction 22 Street Light Improvement 23 Overhead Wire Puller 24 flatbed trailer 25 Forklift 26 High Current Test Set 27 Battery Testing equipment 28 Tapchanger Oil Filter Pumps 29 Substation Block Wall Total Public Utilities Transportation Streets and Flood Control Streets Division 30 Tree Planting/Landscape - Hutchins St Total Transportation Leisure, Cultural & Social Services Parks & Recreation Capital 31 Salas Park backstop (50,000) 32 Small projects (20,000) 33 Shade structure (25,000) 34 Maxicorn irrigation Kofu (20,000) 35 Ma -acorn irrigation Salas (25.000) 36 Maeicom irrigation Beckman (20,000) 37 Slung Seal for Nature Trail (10,000) 1,400,000 1,400,000 1,400,000 1,400,000 desigtated set aside 60,000 60,000 other funding ie grants 220.000 220.000 2.250,000 2.250.000 financing 40,000 40,000 otter funding to grants 70,000 70,000 other funding ie grants 34,000 34,000 other funding ie grants 49,000 49,000 other funding ie grants 1,839,000 1,779,000 3,744,000 3,684,000 16,000 16,000 Wastewater 350,000 350,000 Wastewater 312,000 312,000 1,132,000 1,132,000 Wastewater 20.000 20.000 Elec 2,000,000 2,000,000 5,000,000 5,000,000 Elec 21,000 21,000 14,000 14,000 Elec 50,000 50,000 50,000 50,000 Elec 1,094,800 1,094,800 1,036,300 1,036,300 Elec 1,795,200 1,795,200 1,527,200 1,527,200 Elec 1,886,250 1,886,250 419,950 419,950 Flec 1,484,000 1,484,000 1,487,000 1,487,000 Elec 40,000 40,000 Elec 15,000 15,000 Elec 90,000 90,000 Elec 30,000 30,000 Elec 10,000 10,000 Elec 23,000 23,000 Elec 100,000 100,000 Elec 9,278,250 9,278,250 10,725,450 10,725,450 182,000 182,000 182,000 182,000 150,000 150,000 Streets/ elec grant 150,000 150,000 OF capital 2001-03 FINANCIAL PLAN & BUDGET 05/23/01 CAPITAL BUDGET DETAIL BY ACTIVITY 2001-02 2002-03 Requested City Manager Requested City Mamew Cost Recommended Cost Recommended Cammems 38 Lodi Lake Parking lot (100,000) 39 Lodi Lake Pedestrian Trail Phase II 500,000 500,000 undetermined 40 Aquatic Center 225,000 225,000 2,775,000 2,775,000 Financing 41 DeBendetti Park Development 310,000 310.000 5,900,000 5,900,000 Financing 42 Indoor Sports Center 500,000 500,000 5,250,000 5,250,000 Financing 43 Replace duplicator 10,000 10,000 Equip Rep 44 Floor Lift 16,000 OF capital 45 1/2 Ton Pickup Truck 26,000 OF capital 46 Skate park 538,000 538,000 OF capital/ Elec benefits 46 a Lodi Lake Central Area Improvements 1.200,000 1,200,000 Financing Cultural Services Community Center 47 Table & Chairs Replacement for Kirst Hall 43.660 20,000 20,000 OF Equip Library Lib Trost 51 Renovation & ADA compliance 30,000 30,000 30,000 30,000 CDBG 52 Checkout equipment 13,500 13,500 Lib Trust . 53 Upgrade computer system 270,000 270,000 grants 54 Workstations 10,000 10,000 100,000 - Private sector trust for yr 1 Total Leisure, Cultural & Social Services 2,372,160 2,306,500 15,675,000 15,595,000 Community & Economic Development Construction Development Building and Safety 55 Microfiche conversion to CD ROM 15.215 15,215 OF capital 56 Field Inspection Pickup Truck 24,400 24,400 OF capital Engineering 57 Purchase 112 ton Pickup 30,000 30,000 Water[ Ww Total Community & Economic Development 69,615 69,615 - - General Government Non -Department 58 Replace High Speed copier 37,000 37,000 equip replacement 58 a Civic Center Veterans Monument Citv_• Clerk 59 Purtmse Image Scarmer 4,000 - part of Inf Systems rep] Information Systems 64 LCD projectors (6) 27,000 part of Inf Systems rept 65 Replace City Hall Server 16,000 - part of Inf Systems rept 66 Information Systems Replacement 75,000 75,000 75,000 75,000 OF capital 67 JDE consultant services - HR module 100,000 100,000 OF capitaLlElec & w/ww Organizational Support Services 68 Meter Reader Vehicle 22,000 22,000 Elect Public Works Facilities Services 69 Vehicle for Const Proj Manager 22,000 22,000 OF capital 70 HVAC replacement - Library 10,000 10,000 600,000 600,000 electric grant - NCPA 71 Roof Replacement - Fire Station i!3 26,570 26,570 GF capital 72 HVAC replacement - Fire Station 43 39,000 39,000 OF capital/ Public Benefits 73 Roof Replacement - White Slough 22,000 2'-1000 WW 74 Purchase one pickup truck 29,000 29,000 OF capital Total General Government 429,570 382,570 675,000 675,000 - TOTAL CAPITAL BUDGET 14,170yM =-13,997�Ci5 ' 30 819,430: 4�A ' 30rL7l,450 Cunwd Debt Service: 2001-03 FINANCIAL PLAN & BUDGET 0$/23/01 CAPITAL BUDGET DETAIL BY ACTIVITY I2001-02 20O -03 Requested City Mmaw Requested City M—M Cost Recommended Cost Recommended Comments General Fund 1.275,205 1,275,205 1,267.895 1.267.895 Electric Fund 1,391,435 1,391,435 1,391,435 1,391,435 Water Fund 227,975 227,975 227,975 227,975 Wastewater Fund 812,385 812,385 817,465 817,465 TOTAL CAPITAL BUDGET & DEBT SERVICE 17,877,595 17,704,935 34,524,220 34,381,220 FUNDING SOURCES: GENERAL FUND RESERVE 1,400,000 1,400,000 GENERAL FUND - CAPITAL 936,860 225,000 GENERAL FUND -EQUIP REPL 67.000 20,000 LIBRARY- TRUST 23,500 - FINANCING 1,255,000 17,375,000 CDBG GRANT FUND 30.000 30.000 STREET TDA 150,500 - ELECTRIC FUND 393,775 707,000 ELECTRIC FUND -LONG-TERM 8.360,250 9,470,450 WATER FUND 19,025 - WASTEWATER FUND 703,025 1,148,000 UNDETERMINED 500,000 - OTHER GRAFTS 159,000 304,000 TOTAL CAPITAL BUDGET : _„ 13,997,915 ; 30,679yd50,� General Fund Debt Service 1.275.205 1,267,895 Electric Fund Debt Service 1,391,435 1,391,435 Water Fund Debt Service 227,975 227,975 Sewer Fund Debt Service 812,385 817,465 TOTAL CAPITAL BUDGET & DEBT SERVICE 17,701,935 34481,220 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Safety REQUEST TITLE: Public Safety Building & Civic Center Complex— Designated Reserve Project Description The Public Safety Building & Civic Center Complex project consists of three phases: Phase I includes critical improvements to the current Public Safety Building and upgrades to Fire Station 2. Phase 11 includes building a new Police Station Phase III is the addition of a parking structure at Church/Elm. (build concurrent with new Police Building) Phase IV includes the renovation of the current 30+ year-old Public Safety Building for Fire Administration and Station 1 plus other governmental office uses. Council has ranked this project as a "highest priority" during the budget process. Project Objectives The objectives of this project are to: • set aside a special designated reserve toward the funding of the Public Safety Building project. • give a better picture of impact of a financing on the General Fund operating costs • setup a reserve if anticipated revenues do not materialize in a given year Existing Situation After numerous shirtsleeve meetings, the Council has approved moving ahead with design of the new Police Building and a space needs assessment of the old Public Safety Building . When the design stage is completed, staff will bring recommendations to Council for discussion and approval. The next stage will be to discuss funding alternatives. One alternative is to finance the project using General Fund revenues. A cash flow projection was prepared by Public Financial Management to show the feasibility and impact of a Public Safety financing on the General Fund. Council approved the rash flow assumptions on March 30, 2000. Other alternatives include combinations of grants, low interest financing from the State and traditional financing using Certificates of Participation. The alternative scenarios are intended to free general fund revenues for use in meeting other public needs. Setting aside a designated reserve annually would give Council a better picture of the impact of a financing on the operating costs and would demonstrate the city's ability to meet the projected annual debt service prior to any actual financing. These funds would also establish a reserve if anticipated revenues do not materialize in a given year. Schedule and Project Costs Project 1998-99 1999-00 2000-01 2001-02 2002-03 Total Phasing Preliminary Design/Study Acquisition Construction Phase I Phase II Phase 111 Phase IV $327,000 $260,000 $375,000 $390,000 $224,000 $700,000 $900,000 $2,310,000 $50,000 $250,000 $4,612,000 52,302,000 $4,750,000 $1,750,000 $587,000 $765,000 $924,000 $10,124,000 $4,800,000 $2,000,000 Total $327,000 $1,759,000 $3,700,000 $9,362,000 $4,052,000 $19,200,000 Recommended Set Aside $1,500,000 $1,500,000 $1,5000,000 $4,500,000 Ir,— 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Parks and Recreation REQUEST TITLE: Aquatics Center Project Description Aquatics Center development. Strong interest has been expressed to pursue consulting services and a center for the community. The funding and location of such a facility has not been determined. Project Objectives To provide the community with a much needed aquatic facility. Existing Situation Lodi relies heavily upon School District pools to accommodate our aquatics needs. Additional facilities would eliminate the reliance upon the High School pools. Project Work Completed None. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives Maintain status quo Funding sources may include bonds or short term financing or Certificates of Participation. Project Effect on Operating Budget Upon development the facility must be maintained by stats. ``J 0 $ 25,000 $200,000 $2.775.000 S225,000 $2,775,000 $399,000 $225,000 $2,775,000 $225,000 $2,775,000 $3,000,000 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Parks and Recreation REQUEST TITLE: Indoor Sports Center Project Description Indoor Sports and Recreation facility development. Facility will provide gymnasium (3 courts), bathrooms, offices, and meeting room for communityuse. Rough estimate is 30,000 sq. ft. building at $175 per sq. ft. Location and funding for facility have not been determined Project Objectives Local and regional basketball, volleyball, and indoor athletics. Existing Situation Lodi relies heavily upon School District and County facilities to accommodate our needs. Additional facilities would eliminate the reliance upon the School District and County. Youth participation has climbed and this would allow the City to accommodate all who wish to participate. This year we turned away youth wishing to participate due to lack of facilities. Project Work Completed A feasibility study was completed in 1997 Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total $30,000 $30,000 $30,000 $30,000 5500,000 $5,250,000 $500,000 $5,250,000 55,750,000 5500,000 $5,250,000 $500,000 $5,250,000 $5,750,000 Alternatives Maintain status quo. Funding sources may include bonds, short-term financing, Certificates of Participation, formulation of special Recreation services District, or special allocation. Project Effect on Operating Budget Upon development the facility must be maintained by stab. i 2- 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Parks and Recreation Administration REQUEST TITLE: Lodi Lake Central Area Improvements Project Description Improvements to Lodi Lake central area. A site plan of improvements has been produced and approved. Improvements include new irrigation, added turf areas, removal and replacement of asphalt paving, building ramps and walkways, and landscaping. The project also includes construction of a new parking lot from west of entry to the beach house from Turner Road to the Discovery Center. Project Objectives Improvements to the site. Existing Situation The park is in need of these improvements due to its age. Project Work Completed This is part of the ongoing improvements based on our master plan. Staff will design this project in-house and in keeping with work already completed at the entry and beach areas of the park. Schedule and Project Costs Prior Project vudse46 1199-99 1004 01 ZGA 102 2002 W 'fetal Phasing Study completed Design in-house Acquisition Construction $1.200.000 $120000 Total $1,200,000 1,200,000 Recommended Funding Sources Capital Outlay Fund $1,200,000 $1,200,p00 Electric Utility Fund Water Fund Sewer Fund Total $1,200,000 $1,200000 Alternatives Funding to come from grant funds, capital, or other undetermined sources Project Effect on Operating Budget Upon development, the facility must be maintained by staff 2001-03 Financial Plan and Budget Request CAPITAL UAFROVEMENT BUDGET REQUEST ACTIVITY: Administration REQUEST TITLE: Civic Plaza Veterans Monument Project Description The community is very proud of the sacrifices our Veterans have made on behalf of our Country. As a show of respect and gratitude, the proposed project would create an All Veterans Monument located at the south end of the Civic Plaza between the City Hall and Carnegie buildings. Project Objectives The objectives of the project are to: • Establish a concept design for the monument Establish a non-profit foundation to spearhead fund raising activities Construction of a monument Establish an agreement between the City and the foundation whereby the City will be reimbursed for the funds necessary for the construction of the monument as donations are received Existing Situation A Veterans Advisory Committee has been established, with members being appointed by the Mayor, to evaluate construction, marketing, finance and event planning. The Committee meets bi-monthy to ensure this monument becomes a reality. The committee has approved a concept design created by Tim Mattheis, a local architect. The final design concept is scheduled to be submitted to Council at the June 6, 2001 Council meeting. .Project Work Completed As indicated above, the Advisory Committee has been established, the initial design concept has been completed, and fund raising has begun. Schedule and Project Costs Prior Project Budgets 1997-98 1998-99 1999-2000 2000-01 Total Phasing Study Design Acquisition Construction 5450,000 5450,000 Total Recommended Funding Sources Capital Outlay Fund $450,000 $450,000 To be offset by Donations Project Effect on Operating Budget The cost of any on-going maintenance of the monument will be absorbed in the current operating budget. City of Lodi Mission Statement The City of Lodi's purpose is to enhance the quality of life for all Lodi residents through activity serving, pursuing excellence and reflecting our high community standards in providing: Public safety Managed growth Progressive and balanced economic development Cultural opportunities Recreational activities Fiscal accountability City of Lodi Mission Statement The City of Lodi will provide a superior quality of living to its citizens by embracing public/private partnerships and service-oriented practices. The City will uphold high community standards for public safety, managed growth, progressive and balanced economic development, cultural opportunities and recreational activities. The City will operate in a fiscally and environmentally - responsible manner. 01/1.9/200=. 18:41 FAX 415 982 4513 PUBLIC FIN. ;MSGMT. 10001 M— = PFM domenal- C— Public Financial Management Financial and Investment Advisors Memorandum To H. Dixon Flynn, Cly of Lodi Vicky NIcAthie, City oj-Lodi From Ale..: Burnett, Public Financial Management, Inc. Cameron Parks, Public Firannal iVana.gerncnt, Inc. Re General Fund Model Update 5o5 hiorttgomery street Suite am Sar. Francisco. CA 94111.2552 January 19, 2001 Fax: (2179) 333-6807 (209) 333-6795 12 page 415 982-5544 415982.4513 fax In response to your request, we would like to provide the City of Lodi (the "City's with an update to the City's General :Fund Model. This communication is intended to provide you with an update of the model to reflect actual revenue and expenditures to date and to provide you with the opportunity to give feedback upon the methodology used for revenue and expense projections. We have also calculated the financing cost of the Public Safety Complex based on current market rates. In conjunction with City staff, we have updated the previous versions of the model to include the actual data for the fiscal year ending June 30, 2000 ("FY 2000"). The chart on the n"t page shows a comparison of the general fund revenue assumptions contained in the previous versions of the model versus the actual revenues received in FY 2000. The chart shows the dollar difference between projected revenues and actual revenues and also list the projected rates along side the actual rates of change. As you know, the model is meant to be a living document. The model has been crafted such that over time it can be updated for actual values and the projection rates can be revised for changing econotnic conditions. This update to the model, which incorporates actual values for FY 2000, eonf.=s that the projection rates used for FY 2(-.100 were reasonable. Recognizing that revenues will fluctuate from year to year, whereby some projections rates will prove to be high while others are low, we are reassured by the fact that net revenues in FY 2000 were $157,854 higher than projected. In the attached model, on the pages entitled Ee alatim Rates ('o) and Escalation 1Zlees (S), the six year average rates of change for revenues and expenditures from fiscal year 1995 to 2000, luow appear on the leftmost column. We would als:, like to note the recent decline in interest rates might have an impact on the Public Safety Complex financing. Previously, we estimated that average annual net debt service could be approximately $1,390,000. ]lased on current market rates, w -e estimate that average annual net debt service could be $200,000 lower, approximately $1,190,000. However since it is not possible to know where interest rates will be, in the event that the City issues bonds to finance die Public Safety Complex, in order to be conservative in our projections in the General Fund Model, we have maintained the previous estimates for the cost of financing the project. We hope that this update is helpfitl in providing some Perspective on the City's general fund. Please feel free to contact us ,it ( 115) 982-5541 with any comments or concerns. Revenue Assumptions Milo City of od CatcLory Projection (1) Contains Other Sources and Transfers In / Property Tax $4,629,777 $4,931,835 $302,058 2.50% 9.19% Sales and Use Tax $6.871,894 $7,095,460 $223,566 3.75% 7.13% In -Lieu Franchise Tax Electric $4,317,797 $4,367,000 $49,203 1.00% 2.15% Sewer $797,104 $790,000 ($7,104) 1.00% 0.10% Water $568,064 $564,000 $4,064 1.000/0 0.28% Other Taxes Public Safety Sales Tax $186,805 $196,180 $9,375 3.75% 8.96% Transit Lodging Tax $318,650 $318,034 ($615) 4.36% 4.16% Waste Removal Franchise Tax $289,117 $301,088 $11,971 2.76% 7.020/0 Industrial Franchise $34,045 $50,255 $16,210 5.46% 55.68% Gas Franchise $132,705 $137,154 $4,448 3.41446 6.87% Cable TV Franchise $174,478 $173,755 ($724) 6.00°'0 5.56% Electric Franchise $11,656 $12,436 $781 0.99% 7.75% Real Property Transfer Tax $124,958 $116,059 $81899 5.00° 2.48% Intergovernmental Revenues Motor Vehicle License Fce $2,356,446 $3,008,393 $651,947 3.79,/o 32.50"/ Other $450,193 $740,256 $290,063 1.41°x0 66.75% Other Revenues Licenses and Permits $1,342,628 $1,405,935 $63,307 6.004'u 11.00% Charges for Services $1,385,822 $1,411,163 $25,341 6.00° 0 7.940/6 Fines, Forfeits and Penalties $948,505 $714,051 ($234,454) 8.000/'0 (18.704.,) Rental Income $150,835 $240,989 $90,695 6.00% 69.36% Investment Earnings $400,000 $331,250 ($68,750) ' Miscellaneous Revenue $71,301 $161,996 $90,695 Tota! Rwenxerr't $30,463,699 $31,062,301 $598,602 4.62°io 6.68% Tota! Expejuktures $29,544,208 $29,984,956 $440,747 3.02% 4.56% Net Income $919,491 $1,077,345 $157,854 (1) Contains Other Sources and Transfers In m coon '.LK7K 1.103 3T -Mid CTSt Z96 STY TYd Zt;BT TOOZ/6T/T _ s �.'$k=�8�$Ea���a5 A Ref and w.f "j O,4;,FL gL'If Q a:gti 3 �7C4'���Be3�3aC^ 39ai:�t�9sF�: RRSg3• '. 979 TAdZan�u� S -e(793 -w: e.N �sN3 ri i uaa� � —a$ ei & •R$r- to a -r - $'•5A 3:!,!tg VN 3 3�$3as�"-83_I9c 3$,oiSa^ =j If d 4 $ 38". g: agp43'xus as9�a9$k38 a n�d5$" $I&, ola g a - �g Vis,«s��a��a�g3'•g ��d$3a�=k� � ����°,�'� �i��� � o � $ ^ 3 J d �J�i�BB�sQi•'� F"GAN o� 2!R n a RM1 gJs�3RRr^"'OAT g '0 3:Ns hied§3"ak'ss $ 1.45 �Fi RIM, Nh3 6, e 6 •` � RISC- Ng�R3 z,� 3:4 _ °�•ag�6B$a:s� 3_i$3�"R 31&$oe evI3$e o"- iA f S'�3a a7«B:=N, ^ � oe��a .�- a •i 6. ���aARB3d���al� �$=�e�7S�•$ � �R3R•ae eS� C = ; Rei 33ss i7 slag n«$19 1i4?B3a 3i4 saa�R � ■ I]Ali I I F m coon '.LK7K 1.103 3T -Mid CTSt Z96 STY TYd Zt;BT TOOZ/6T/T ni VI rb 2 cr{�Of1,0o1 .;. GmF1�JAl Ft77ryf f17fA19�/il Pion -:- 1.SarwtO - A4u46r1o(lon T-�s,n.nrPn,l��i ■. -.', _' E*O;' iWw66 "Oct" 61 S Sq6. -061�enl l6nd`(.gnakKlN(Out) e.!1�1',R°ale»gno LOVraiibao8tl'6tY:Comol+t „1rlcYw 1,.'.. �' ',+:i• .. 16mAtal Pro S FLtr V- 0.6w 104 INS 140 1642 Im 1964 7000 7001 7007 2067 304 7006 2m 2007 9006 amp 2010 TWI `82.63784 w OWED., TYm14n b 1 0474 of fl w Tro .9- 7.4WAM 7.ed63M 2.666960 2.121.011 3.14.420 1341!,700 7 19rt FtlO ti>d YtbdIM 4444 ffrit 640.000 03UM 9MAM 060575 067.363 952A67 1,00[007 1,m50L 7,44802 7 ewwo21w AM 4 108017 F- 97 F00 6 Ewpnrt Fur `AOM 6 0- 3.021,370 2A 4A41 2.114691 MMAN 1.014.624 391171 0 0 4.491440 4.64,700 4,915627 4,904.174 S.IMA 0 6,1.10.172 6296.643 5.719,166 0.619.676 66.SM,SW 7 TOW OprAO Tfaf h -b 4,661,376 3,771ASI 9.754391 5612210 4.10.112 4213.47 1995.0t1 4.343,170 4,466440 4,662,700 1215,627 4,965174 :1'$620 61363.172 SAMD67 674AM 6611,6.'16 60AMAV 1 TOM Tlrd-l0 4.361363 3.779.991 750391 4519.310 4 19D 024 3,6%.011 420 4L495,440 4.662760 4616621 4,99417A 6156670 3.339.172 SSM013 57/94yA 6,21SAW W 677 -RAOOFITWOIA 't t. OP-tiq T7W- Out ' It C41rY1+9 T-1Of1 Cuf 0 b G"fa F-4 101,113 209.463 210,466 614063 11 a t Fv 636667 -6267 40004 40404 76491,7.4 12 0"" IdM,O6S 1.636.316 rmcw 136,446 661?J3 125 04 564 801 0 669,465 669,466 669.4SS 669.466 0'.9.466 660.466 WAN 661.45 669.46 17.971462 13 T0W op ow 0Tu4I1dv40.1 1"Am 1.63.326 221170 16.2.64 f,730,,m 1270.960 1.17174 ',.4S 40AK 669.465 609.45 669.40'1 (69.465 "A66 SWAM 069.45 6W.446 17.10&279 TnMIN 01110 dpid 6ff64cb FuN 14 610641!}To O 611.114 1,60r.06m 12R.MA 1.312.35 1.3567A 1,479,551 1.31615]9 1}64.457 1,697'714 1.6:0.147 1AM176 1.71S.OM 1.75181 160IL4W 1•547.756 1223.950 2489$971 16 V -d S,tr w 0 4 9&klomW T,%, IW b Ddl Srota 0 0 0 2U.161 1827806 ,.161756 1,145611 I.IMID6 IAWSm 1A06331 961.716 7.932,095 17QW43-dFW C40W 211,025 0 I;Dmaw- 1,611,605 11 TCN 1-4.. Out M C41d91 RRpt4 Fuld 0 611.114 186'7.646 1,17/,264 1.312.329 1.47,295 IA70.361 3.016231 1.3-•64 1616,475 2.66&14 ;657,761 2.567.335 ;6.56906 2656,191 4653,090 2.W&26S 33AVCSI Tf-wus Out lawny 1Wd 4 P.Pp yTaf D 20 Total T -1-Q4 b L*..y Fw10 O 0 0 D D O 0 O 0 0 0 0 0 0 0 0 0 O M T.60 TIO."CL0 15411,005 2614FAW 3 4.40 2606 t30 1142129 A&VaM 2, 3, 104 P,2ZLWM 2,617.260 3,56..9 1527,2,16 3,t;9.621 3,".391 X527,en 3522.675 I•T7,750 ..o 27 TOTAL 7443E R7 016244 163241 46969 1,914,180 1,641 ps, 1706.762 1341.716 667396 Z2FIAM 2.134.620 12119.698 11 926 t.F.5` ,2.0 1,610711 1.""z 31 OW 2.601645 29 457 171fA]WAOE3'61LE! - •' 4 01W 6642094 73 E#WMW 54710 69w06 0 1 :0 ISOM 196767 193.756 203.791 202.730 203,776 206676 2(1.604 1,121263 24 FM RN4 0 :2024 60104 514060 616.151 sm.0 623.50 070.74 SMMO 6t1.46 64,10 la1,iM 26 t14643d E4wd1u14 0 27=0 214000 AQISirit i 0 455911 23 0Q976OOet64 • 6 0 0 0 0 0 0 1.410217 197.770 7D56O9 711,06 719.057 726.216 731610 74054 741251 756.73'7 7Aa3M M cam 11994 26 mat" -9 -On t 0 - 0 24 TOW 0" 0/4 0 0 0 0 0 0 O 0 0 0 0 0 p 0 0 0 O 0 127 TWALONEAWWESILASM 0 0 0 0 0 0 O 1,414.611 607,910 701009 711,939 719W 726810 n%910 74AA48 748,254 15&737 7057]00 4,rwE01r791 429 r 0o -AA, GOrlsdiu,tl 6:4rg60A-544I�j.46 . ,.. _ ne cv l9e{m.... .._ .. .. • :. „t.. _ _ — -,�q fd 11YBlltl . w1.99 e9ot.o9 e1.a•. %19+9 � ItlawO 91o90q Lla9l1R Y � „oea I+PsVd 1tArm '.9991 196u4b 19•mN w eaap 111 C9Dtf rt Vol, 1,011 LT'M WE71 41I'4119 Le", 1(sL9 el 1M uW9 if 12 Ks 9L'Oc logic 61, to 11004-7 W VAG t/ 9CC0 ftt'0 owl$ 06979 Ar09 O6ro 990'" tts79 tt6,[s Ks'/c lCiVis oea199 00!79 00rK e(r'f9 gisT9 0mt9 .Ao1Odu %LM0 %f^.M0 '%DMO %i0W't %=O1 %419011 %Mill %HOrs %OCtr1 %OWCI %9[910 %am0 16CM0 %1090 %60{0 AV91L6l9wm PcrlOAA41o0 K409YO9t mW15 0's ML'TtrdKc alllrlmT 0r9Lrt1CZT O1WC1C'Ut% "WOWSIVIE 110'1W7Wt AWCU'0001 OK•CrlCre Om'[e1'T[rZ OWVU-VCS 001T10'00'c 000VWCWZ OW-131ifOre 000'KL'L[1`9 W ICLUNe LAVJ 6"M it"OP4 Pala lItfM 0001S1c'0c 0079sL,cc 000YM'10 000'91DOTC wyowK 00almte 000VtOlc m07t97C 0007µ'1f o00'buis' OO011o'n 000'00171 OW'O1rf1 OOO'Oel'9l awvw9 0 O AyrlltVp9laavyp90 P�Od P+1+0 PM li %!0'® %N,011%Orn %9*11 %et 11 00119 Y41 go %01 WAIL %root %Acte %Sol %mI %Wt %9c'/ 66+6+1a Wit p0q P% c w AWIP M-0K S0r/OL1 UOreoVy tac'MI't 001tro C1L'Krf Om'oSr'f fK'Ac't SUt'907t 1,49,10re t9Twal 9019'9 00'meY 1"*CWe1 L91119'cr vwlwelt 9rywUMwAl9Wtl cc -act III it ve It VU EEL +me Cl rst't1 •arw mtt r10T1 WiL -it it -099 -von 619'tc t0elot bi utirm "909 0�901TOK 9",Nt%L earow;T, /9/YNc9 011119'01 t9'e'Cte'K W,W12'/4 WS'ON'K 9,1'09191 CO'llt'K CM'-wir 106,00 LC 1K'Ott 910'Ll Ver OCt9rt 2111's9rW tlt'Wrt 09v" tweKo COL'OPW coam VWSK OI170t M•wV Pot P—fp 1T f,=VvAJpQj 111Lla11990ln9L K 9erelt'O9 m"Wirr 06,119•12 11VI11 9N1SSe 9R'OW3 1911/59'9 HYy1rc gitlowt StrWt'L s9t'Krl 9"Wet 0Y5791 19/'SOC mvK 011'909 "Was. 'Cl ~ it 109',11 N071 OWYI ""I W061 W4,zt 410'91 0091 199'91 owe! 96011 Uri 111'9 s017 9107 sm VM VM la0A1D/9►Vre00'S 09 m0'q Oft 'f Oef'1 OYt O on.. 00,'1 Obf't 011". WO 01`1 Wt'! YM YM VM YM Viol Vol YM lame"" 811 MY11 Olo'C No% Ot/'t O/rc Ot9Y OI9t Wirt C. Vc, OIrc 01911 0111 W'd Opt OBIT YM VM VM OWt M" Q 991'U9 MET 9M'I seat 990'6 990'1 06,c "WC W11c Wrt MT SWT t61t SCSI M-T SLOT VM YM Soft 6Mee IU 1011890 Placid 00l'LN79"I'M.a 001"'t 991'11,119 cor9 it 01aewL 9r1'St9'r su*"114 eat'Kt'1 Z1c7tt'1 ell't1Z'1 14'[1.1 9CIVIZ'I iKtetl c9Yc1L tsartet VM VM .1"mromow16awru 9I 0197'll VWCN'L 0lthl9'1 MWO'l oLI'OLc't 11r01rt Kc719't Ou'us's 119'095 (906,tOt) I9of100 Ym VM VM VON VM YM YM IWscom 1e rf1711'll shots OK'Ow =TwoSWM ot9'Lte leff?o 9w"ll etrfK H17w gig" O.ITM 9K'LM 9U'On tW'9/t YM YM VM Beal www K 9trIW7 OK I t1rlel 106'91' Witt f:'fCi1 M9Tr/ 141'113, tzolry L1/7Cf IOL'UZY IK'M Isc'19/ 10'45cf 1C1'13/ *Witt VM VM ¢ol" k 9:111,0111 1PO PH C90t9r1 YM YM VM VM YM YM YM Cts'OL/ 1m'IK'l P1,049 Vm YM YM YM VM VM VM r—pq P1919Pe71ATSa C90i6Y'e YM YM YM VM YM YM VM C19'019 LW'IK't CIYO[9 YM YM YM VM YM YM Vol ION la169 19 YM YM YM YM YM YM VM VM YM YM YM IM V91 Vol VM YM YM VM Not Sim N YM YM YM VM YM Y.0 vm YM VAN YM YM YM VM VM YM VM VM YM WIq+S of Salim Palmation CTA'tl9e 966,!01 996'101 910101 Sea'I01 500'101 506'101 Witt 60/'101 9Wt01 100'09 YM YM YM VM YM VM VM •tiNiWatlt9q.116VB 11 LWOW gww:.*l Nf1011 Ne'101 90'101 sm"01 90'10{ 2r10t WWLOI 2W101 900'OS YM VM VM VM VM YM YM I411claY9c L1 VM Vill V.N VM VM YM YM YM YM YM YM YM Vol VM VM YM YM VM seat "We 11 VM YN VM YM YM VM YM VM YM YM YM YIN YM YM YM WN YM VM Wimp" at 10199167 PW (JOG.) 01-W G%m M/91166119/0 st.in'9t f8170i e11iCT0'1 $9~9 mvW9 99['0919 1AWL1re wroorg 016,0399 Kr9t9'9 CCZVK't OU'U31 Ke7/Yl t1CV9rl ZUTU twUs VM 1llY A06K 6AvliglTr It "WL4'91 19009'1 996,10'1 eN'Y.rl ttr'lW1 11.5'196,1 swc"1 959'Utrl lzn,%,t LrnWl C.2'an YM VM VM YM Will VM YM IM90M it '"'hill t1S7M 0070 6=109 OfC" 93,9'1" M('t11 sets" strt/9 N/'Oc9 9tsT1 M'OK VN'LN 991`051 IWVK YM YM VM M1"" Z1 .to .t90'9 90C'se, 11YtA Ir6'9Lf 9[9,13, r.»'irt 60t'CU1 lµ'/O 3,[0'19! 1WRO 10L'!Lf 1,1[91 190'190 UWRF ICr01T MNitt YM YM SWI ailm IL ' 19'6119 /1b t�W 1 01 4LL10LC YM YM VM YM YM VM YM W11 VM OW'GWZ VM YM VM WO wi t [LI LOOT YM YM RNR1T 01 Tit'101 YM VM VM YM YM VM YM VM YM L71'1 YM YM YM VM 000'101 YM YM IP-OW OWOPW 1 0' 0ICe VM VM YM YM M V VM VM YM YM Kett, YM YM YM YM YM VM VM 916%9 laP69 1 09%'ILI YM VM YM YM VRI VM VM YM YM OSI'Kl YM VM YM YM YM YM YM YAODt1p 9J69MCPYP l 00.00 YM VM YM YM YM YM YM YM YM OWme VM VM YM Ot'10i 0007ol YM YM 191M9p10P97 e DOYOBYr YM YM YM YM nu VM VM VM VM WWI M YM YM VM YM VM YM p.6lellawlq lla96/Mp S loit0'1 VM YAI YM YM YM YM YM VM YM /1rAr1 M YM YM YM YM YM YM Pr•J Y1014U 9r►5119 pep I UfLbOe'iT VM YM YM YM YM YM VM YM VM oOWSWIP VM YM YM 000'11ro [LLMC'/ VM YM P69P-kid C 9009" ML 009 901//166 laalil owl 000'OrrU WN vim VM YM Y^t YM VA, VIN VM 0030019 M VM O>D'eal'0 00009 00' YM VM 160rlolPglA1^17"8 9 WYOWU YM MM Y YM VM Y. VM VM VM VolYM 0o07AW YM Vol YM wwah Ol C090m'9 YM Vol YO-W 6e 1 I=atly laOt MVK cn1 0N19 all-am Pae s71t10rL� _ rylf)9 WL v. am me LMi woe 9009 IOU am am 1009 0909 $1111 Het 1 I19t MOs 1,091 n1A F�WU I1p a p916RN -t�' r', r -+;'+ 1 Dtlptltil�dt �Iis19$709n�1�MlWY1�1Y01q�O9d 9ae�. �'t-.�9MY�1!5ffi �Q.` _ ? :l F " 4041/11��PR+S/1lJeuOd:: 'l' 17:tiSiM(°1j't+gW01wdc17 :•1 •i. i r41ARN1"eF;, Y 'bl=0L� VIiTOIlOAL:1,. .. �y 4i1 Y:OF LDGI '. Sn�hf4. L pBn9ltlr!h r? -, C�neri7Fu►iC Fh7an47f�f, Ptm �llstp3+ tlsu! E?rPmditurei propeNpp it i fax t C�aplt�) li7i FliVilm4aC Fupd :;:8tt!►'ihol Ilon9 WMh Lpid PUb�IC laEel�t,QaMO-FIgMSInO e r 114 t 1 Intxml hale N°n DaM PI°eeed9 : 1Mbrld fa44>1Yr 1970 1095 Tf88 ION 119 1090 1700 2001 !_! 1000 7.304 20°6 1000 1007 7000 2008 2010 T4W 1 n 84014143 SAMPO 5765222 UMAN C 182 12MSAN 2475300 2,81 .330912 7 7SAa 7058166 0702,506 811.3 12 7M,!,!4 7170.211 7,104,229 665791 6.131.456 107 7136 C4PU AM 2 C4pW F1nO Fkirmw 9AMA37 4961.500 11.769$56 26.477.767 19A67,0/e MWAM 0.728.425 lWMA24 0.367A7e ISA23AM 4,2.32.3" 4260,7!9 4.238.173 4313.49 4.120.691 4,163AM 4.197.905 140,920.153 2 T91J CAP" FIB" 4149°94 6.423.857 41181,300 11.79}56 23,077.757 19A "AM AM 0,720.0= IO. -T"4 0.367}76 ISA25,475 4787,144 4359,309 4.60.173 4711AW 4,190= /.103.402 4.167395 146.026,163 4 rOW 5palU BPA,W7 4461,MO 11700 23,47'7757 ISAWAO 1R1629 5726928 10,272121 8.367 a 10A25A75 4282344 4A9,3M 67!817 4213.09 4,190 1103 4197693 14e,920.1S3 Ri m A. It'.. '41. copB1 tb49904■4wb 6 O nwwcMR -m 400'7 2,767.756 MAIM 5J00,9e 5 AD64 Wnlu 71AM 71,070 7 (Ionw3l Fuld F11q,+0aeu191 804AN IA27.933 4,00.6a2 9107.044 1S.W= 2.712,09 Z.".ODD 5.313.125 la,m,000 1,6bO.9W 1/0!6.5/8 1,652.821 1,679.782 1.707,461 1.776,712 1.704,729 72.777,765 0 BDA II09^1• 0 0 744a1GPO PA4116aaw0t0 064790 IA27.963 4.7°9.°x! 6p07A" 75.339337 2.732A9 2x67.755 3088.136 6.313.125 14777A7DD IMp°° 1AM.S48 1.652.1 IA79,7n2 1.707.409 1,776.712 1.764.729 75.3LO 1 T74e44a4 040 Op4r01110 ke1141S1 Out To Coo d&wtes TwAactla. o I a."F1.d 141,=0 141)000 12 8g14pm"a F1 b".lr4 465.4.33 300,°00 400.000 40OA°0 400.000 400.00° 4DDAW 4=,010 400X= 40CAM a6Dp= 40DAW 8.150.443 13 OM 3,000.605 2720_792 120.746 9Rt3_469 11x97:73° ..000 ,.462.44.3 360335 5411m0 400.(00 4=A)00 4°9900 40D.QW 100.=0 400.000 40(1100 40DOW 4W.00D MMA31. 41,100.374 14 loaf Wa4640 OMeYrl ow 6.Uk@ 6 2,420.702 4743248 024449 12.428.171 2.362,443 66CAM knp.d For W O. lff FOW 16 Flu 0 I1 FOO$ ° 17 Pun a g4a4art 6600o SO.WD SOAM W AOD LOAM so,DOD 50.000 360.000 11 09+474747_ C�-O FecGlx ° t0 Sbbttl ►ryaar/'sr roCa"mlF" O 0 0 0 O 0 SOAUO 50.°00 LOAOO 30.400 SOA= 50.4700 30.400 3Tg0°D 16 11"orb Pay Debi S4Mw 49.10° USA" 500203 836.481 1206.371 1702.509 1212,367 1270.7as 1.185379 IAM,476 2.650.4" 2.437,76/ 2.460,91 2AM" 2A9,191 2.453,(60 2.650266 00.310295 M TOW T,M4M9 OW 0274.047 23602= 4,743.410 10,164,118 13.710,344 3,631.754 /X42,007 1,777,795 1}85776 2748,47S 3,308,444 7.307.781 7.310.:JB 3,79114)7 3.300.101 3=.OW 3306.MS 71,428,000 Z T4bl Um 7159 14 4.394153 01 000 20172,200 29°51 a .812 4 592 7740.921 7.98.40 19025475 4.407 I9m300 3063.173 49999 S.OISAM 6038002 S 995 150172,691 22 AOAlla4iy 190W493110r4e"0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 23 Oa�14111p 8911- 6189,Q74 3.783 12 3pd7A9 0,570.162 12X7SA29 2.4737= 2,12,560 4236.912 7.075A64 7.96410.1 a202.5m eAe<kw 7,7.33314 7,474311 7,101324 6.637,91 8,131,406 24 E40maM0 k41 In - C4111Y.p4 311.140 412,428 444,421 448,726 431,701 419.6,17 401.017 96.467 351.764 322,190 3X23.09 25 Fas"*%AytiNl.r1M(ON) !:47.458: (14794) 26 E,,WT 118- MY) dSoara49r4r mw -n us- (tx14.467) 167.147 2.6303°0 03=.477 (BA02.42a) 338,17 1.426,543 2,59.50/ 409,174 (100.OM p76XOD) WSA7=) (7253100) (77SAM (W6.ODO) (075PM (873.47=) P.Z"Alm T g08101s1ur4a 9.217 ' 1317 28 - In eawm 3263722 .6957.306 5,374162 12075AN 2A732m 2.012.660 473$.012 7.075.564 7Xmies $202}9 6,0231112 7.793.514 7A70711 7,104,270 OA87.91 0.134.465 6,501 A3$ a, m., Il ..:.n1 9 +r- a. :nrx. " 333 r 1„77-1 Ga,atl hr,O 6cerW60ASa 'JL" Lo0Z *Lw:)w ISIS 3IlSld mt z88 S[6 IY3 L►:4I Iooz/Bi/Io R B 5i q 3 �n •.}. 4 R s peg :a g 3 s 0i let N « « • a �X? gill 11 s' ^'� C }{ 729_33 sN s , 6r G w S'8 1A a� <� gqq S51 S g n 1A6 {tt111 N] _ jj 4 QI`k'f� fl s Q Y1 y g ej ig « R J� e a Via: asF4 N ;zo� 013 6 2$3 as yy 7 �$ � � �`� �� +• Q_� 4 n LTi a� �v � - It - -N...n o eo?=� �R-plSRii•ii$�i RlOA� ii .iS Lo0Z *Lw:)w ISIS 3IlSld mt z88 S[6 IY3 L►:4I Iooz/Bi/Io 4 Qsues-VoWuoos) Pu1i PioueJ 'J•r.w: Iw.r.•w■q F..N �'�"�. Y.yN V4.•Mti '•.I..�F.i AF[Fti 1•S ri Hyl. ��w r.wJl'F'IIr.1�s. rM1�11rr�wM,yti V�MIh:,�F•\ r OL 1'LZ9bf Obft9d'6C 92L 9Z£'LC LZC BI9 SC 5f9'swa 60L Wer 191 b99'OC t9nsol6Z t9Z'Lid'Zt 9£1$' v Oct Tet $ 0009 Wil flop Go Ivo L AUP MLM fZ LCC W& At'1'19l't WWI Z0f20L'1 MA1911 9£9'299'1 909929'1 0081709'1 000'W'9i SZ1 ot69 000t£7Z scilsSt$ potvdolgt 7Qo1 eA11"—;D 0 litumajinbou loll f7 you triol CL OLI LZ9 0► 6Z6'►9C t ZLLSSL 1. ZO►'LOLL ZNL 6Lg L 9£9259 t 8 089'1 oul 000000'LLL 91 6ZL £t£ OMD f£9 Z 9£t 9CL flu" 4 INW O Purd 11MAID 1140-L ZZ ew'O98'Z{ 821'09C'L ZtL'SCL'l. 7.O►'LOC'l 29L'tLl9'L 9C9'Zs9'I 9?S'9Z0'l 008'001 000'09£ - 0M8'ZD6 Wf1wdlL7#'VMWAWVtrt4qV LZ ?6S't66't 8ZL'6£t'l Ztt'OWL Z07'Z90'l Z8lm,t 9£0'tal ops, l00'I 000'9[6 o00'OSC' ttrBVZ oeQ:jpudul OZ 90£'690 000'529 OOo'SZB 000'929 00µ'S28 0001920 QOd9Z9 000'929 50£'>LB PUN Iri"D 6t $PobJd mcfrJ MftMV tC£m,LZ OOO'LCL'9t SZL'CIM'9 000'f9C'Z 90Z'ZLZ'Z INLCK" 9l 019µuoo Ned CL 9l9Mtp pbvv munoom 91 tuu90y tu9udDIOAG H 9t m 1. 000'001 000'001 000'00Z ZCZ'ZBC 9W91SA$uonrmc l ft 000'09t 000'09 owog 000'09 9punmC.L91dpxm EL 000'05? 000'OSL 000'01t 000'091 mis leNdro b R d ZL 000'002 000'OOZ W1 Wvr4vvudu4 4oeo8 wIol pcl t l SZt't08 SZt't08 PIrAuGterxwo%19d OL WOWS 1700'ZLS uol7'tAslupwy H o d 6 000'SLO'e 000'SLL'9 Won AVIPr.A o odeJOO I 9 raPIPNd wu9axwd Y *Ird U0'09'st o00'Z9C'L 000'Zt9'? 000'ooS't ►LO'69L't uoNenawli 84prn6 L smFoxWnbe "pd oph 9 OOt'►Z on'?2 t9 uoNR9 044lu9w9ovoew foot; 5 0081%2 OOO'ZL 009'91 "Jod/dinboegi-Irl ► s"uewjdu! L>uP" 44rS jpW Qr4m4s BtnVcd LWXMA O e No" XOLW U-"-8 2 u t? BwL1d01e1 �++o:SA$ unomoryl t OH 0: OtOL OOGLAd I91ot OIOZ W= SCOL .0^Z 9002 9002 ?OOZ COOL '9002 t00Z 000L :&10-3—A M -M �.:y1:�rrial�-w�wiw� ::1'y^" _ �•1w�`••�•�i�-:•`1r•rr^ p .: ,:': e.•.... � �N i _ - �<'L-w •�M wa � �N.i=r�y"^4....M "t .r.� w.Y: �IRIw..'ri� Y�.� mow. •I w.�n.srw'r\�w.,•."'y' L ¢¢�� �T (��j �P_. yam. y�7�►�:i _ _� - - _ - _ _ _ _ _ 'o•�w7T.::.�r"•-" ^010:.`.::::;:;:=: - Z, d I crrr of 1.t? . ''Glnaral r1U1d FBssnGlalP,An ;Squlpmant&Aeplacement:Fund ew 111W.a. 2 Charges fn arNw a MMMt W Pres V -e I t M i Ldf u- wvr.u. 6 Toll N...1u. Trsdry a Oprlaq T,rvl.nn let 7 CdYlF WT re..1. a T"7 -6-I. lel i a t.1n 1Amrld f0 T.NFw.dap6wrr GAIN P01a1,606TW 12 Orval G vnm l I 12C41M PgaM ;% fat /4 T.Ul C.aaya qua.m1.11 1.5 i /q.tYn W to OprakV 1w, sr al la aanMl hldC IrvenT 17 Twrprixt."" Pablo11111 16 T.N Trrrrrs Out i 20 Aeslla•11I1 P1alb.e R- zz Fg1llWe hAlarria EX*W I b PY10.A11quly rm11Pr Intaal I 2e Elo11WLLAC16400asaws"Wldf*nUu* s! 26 j1lsOla1111at n E.Av IwLfw >� Gerald km ticmoloASn&Z 'k I i i Revenue Assumptions Prop" Ta: $4,629,777 $4 931,8 My of Lodi Wes and Usc'I'2: $6,871,894 $7,095,4 rrat I 35 Diffeiem:v 1 302, 8 i'micccion 2- a Acttiall I . . 1 60 $223,566 3.75% 7.13% In-Ijcu Fr2nclusc T1 x. Fleeter 'e $4,317,797 $4,367,000 $49,203 1.W". 2.15% Sewer $797,104 $790,000 ($7,104) 1.001/. 0.101/a Water $S68,064 $S64,000 ($4,0(A) 1.00% 0.28% Other faxes Public Safety Sales Tax $186,805 $196,180 $9,375 3.75°/s 8.96%. Transit Lodging Tax $318,650 $318,034 ($615) 4.36% 4.16%. Waste Remov2l Franchise Tar $289,117 $301,088 $11,971 276% 7.021/6 Industrial Franchise 534,045 $50,255 $16,210 5.46% 55.68% Gas Franchise $133705 $137,154 $4,448 3.41% 6.87% C2bIcTV Franellise $174,478 $173,755 (5724) 6.00% 5.56%. Electric Franchue $11,656 $12,436 $781 0.99% 7.75% Real ProTransfcrT2a 1124,958 $116,059 8,89 5.00°/.248°/ Entetgovemtne11121 Revenues Motor Vehicle License Fee $2,356,446 $3,008,393 $651,947 3,791/o 3250% Othet $450,193 $740,256 $290,063 1.41% 66.75% Other Revenues Litmus and Permits $1,342,628 11,405,935 $63,307 6.00146 11.00%1 Chuges for Services $1,385,822 $1,411,163 $25,341 6.001/. 7.94% Fines, Forfeits and Pendtics 1948,505 $714,051 ($234,454) 8,0011 (18.70%) Rental income $150,835 $240,989 $90,695 6.001/1 69.36%. Investment 112mings $400,000 $331,250 (168,750) Miscellaneous Revenue j71,301 1 $161,996 $90,695 Total Rspeaxu $30,463,699 $31,062,301 $598,602 4.62%6.68% Tetra! EJOtIrSAM $29,544,208 $2-9M 956 $440,747 3.02%L 4.56%. Net Income $919491 $1,077,MS $157854 rrat ti 0 crrra�coa 7;o2�r,!k .�s.•Yw9nr�..., - a-WdFundF7n-ndW,PLn . Algrtlofforigs - - ElperMftilts loh6ua4tO:S0lc '-AWSkW R6Igsr,('r<)' �: ...:'.. `9W OrO1r1I9►N MISh,LMIP11609 S2ftNy tYmpyjf.11nal(JIW� - ..• ', - - - . L 1%.-117141 A..117.6.udbig, 14462000 11144 1944 144 14441 IM 3000 7001 2002 3009 1904 2006 7006 2007 2006 70011 2010 T7/6Y ( 64pnro wv -2476116 9omr 740.4(2r 2 .1177.. (a0611) (17.1131) 35x1 0am 116% 325% 6.1 250% 250% a -W% 2WIL 260% 250% 2.504 259:11 2W% 2.50% 3 Stlr1U14TY 1,296 (010%) 1040% 12575 4.26% 474% 7.13% 175% 1.75% 176% 1.75% 1.75% 175% 3.7071 375% 17511 174 4 Pkbk Will, SYr T..(prcp ltq 12171 61.69% Sam 041% 16.57% all% 696% 175% 175% 17S% 175% 375% 175% 379% 375% 1.75% 175% 6i.�lllaynp-r 4.33% 0172% 1tJ21 11010%) 1136% 990% 4.1 4:11% 4]1% 431% 433% 4144 439% 433% 411% 4.1375 4.17% t 1FrM1Y%7 F7-,1Y.TY 146% 1.90% 1414%) 625'6 SM 196% 7@1 146% 146% 146% 340% 14@15 3496 146% 3.40► 3..0% 1 7 b A*W Fnrt74r 1264% I1a64%7 4.01% 1012% 12.10% 1330% u 60016 60"4 390% 600% 400% SWR 6.00% 6.00% 6.00% 1 1 OY Finatr IS11% 1140% (061%l34611) 1as6% s63% 611 44 1% 10 6% 3 q% 11 11% 94 35 116'% 1 90% 190% L a% I t cWtowF7mY4r 666% i36ev 1.W% 641% last% 1061% $ 400% SM 600% COON aW1 1,01% 600% Cm% 600% e 10 B%XF I -VO 205% (2136%) 1S0% 2231 4.10%- (,33%) 7.75 266% 244% IN!, 2.18% 2.08% 206 4 101% 206% 2130% 2% 01 11 hiJwfmrir-Bt4vt 2925% an% 21314 SAC% 1a4m4 2.16 1001 1.00% 1.11% 1.% 00 1.110% IAo7. Lwh 1.m1 1.00% twit 12 644FtYF74 N%.-54... 1277% 61.14% 1343% 413% (4.71x) 14.56% 0.1 1.00% I.pp% 1.017% 1.00% 1.0014 I.Wt: 1.00% 1.00% 10"5 IWIL 13 IwY Ft7r -1F4/t1 U 146414 12616%) 295% 1114414 4.09% Ia30%) 02 IAM IA 1.00% 1.00% 100% 1.00% 1.00% 1.07% IAO% 100% 14 R./ pmy" 1..11.407- 99_ OYsI 1064% (1742%) 1790% 51071 17 4%) SVC% SW* 6.00% LOD% 6ao14 611".&60% 500%600%5W% Is 749 T4.44 3� 1777% 6.42% 065% +.43% 4.11% SN% 10 004171.1 V10 On.NY 16x6% 26.16% 3246% 21120% 1611% 7.105 11.001 5100% 600% 8.0171, aw% 6.00% CW7. 600% 9DD% 600% owl 44a007�m76'ael 7441844 17 row Vat"l lira% Fr sl 732% 691% 9.0% (4.2a4 2.27% 3260'% L00% LOOK SAM a0o% 500'4 sCO14 L00% 60"5 6.00% 6.00% to 01 10.1 7&t2% 4690% IC6.67% 13064%) (12.86V _M 70% Uos Con 5-004 fiam SD" 51)0% 6005 SOD% 600% 600% It Talliryr+ImtrYfn:Yuo 11.4"6 19.11% (605%) 24-21% 0.4414 (11214 31400. 20 4]%qr 10.41444-41 13 (3622%) 12711% 6.13% 2a44% 431% 7.141, son 600% 1100% aODIS 600% 6O 6.00% t00% 600% 1100% !1 Fiat 6760. 441.0.". tat (039%) 3.74% 7A4% 4610% 70.7,% (11.701( 000% %1105 a-00% 4.00% 6.00% 61301: 4.00% 1479% L00% 100% 22 741111 it- 11.16% 151"%1 14171% (6106%) 117/1% 6177% 611 1100% am 600% 4110% 600'% 6DD74 11006 6.00% 6011% 11 23 2.O71141.44..7112�.ip 014% 1240% 16 M%) (4047%) 41.13% 10472% (340114 26740% 1126074 00974 COWL O00% 000. 0100% 1100% 1100% a 24 6%ola:per.147V t0 42.7%6 (790%) rA1O%) "Am (3615%) 12710% 000% 000% O.W% oom OoO6 0001, 00014 000% cam n t6 Cow 94457.. oom060% at11% 600% 000% 000% 0001 OW% (106774 I.W% I.W% 1.00% IAO% 1110% IAO% t.Wloftp Z T.anitwh (2.16%1 (17.1314 (am) 31160% 3.11% 16 t7%) (466%)& ra. 350%310% 160% 330% 350% 360% 3.50% 3601 27 Suet4.7/111 41 I,t)% 57071 1511'% 497% 3111 066% 040% 1.06-1 3q% 346% 361% 3HY. 367% 360% 362% 3tS 177% [151112 Of "as 110" t F '484 327% 1.50% 1511% 160% 150% 35"4 ISO% 350% 33014 3. Cw M G.-"po+.n d 4.011% (1.5611 4171t -234% 20174 2.42% 7.4 29 F\41kp b.N. 224-, (17-11 600% 1201%) 370% 131 6.71% 3AM 36014 160% 1604 3.13:: 150% 3401 1.509 1.4 30 PAt.+tw 296 (7.1011 1926% 1601% 1I On) 137% (1.11%1 1077%,) 3.50% 360% 350% SW% 3504 350% 360% 3.60% 1 31 lLr7 1 0.46% (O2JN 610% (4.5011 661% 160% 7J4% 3Sa% 350% 3W% 1'W% 360% 3W% 3.W% 1505 1. 32 0.74. tr1014146.900 2 (0.1614) 14.19M 622% (60014 244% 16711 Os71 3.50% 350% 3.30% 36014 250,. 1605 3sO% 110% 3-W* IS C -U.. 0 OCO% OOOL am% cam 90074 nO7s OW% 0001 coax 000% 0.00% 1100% 000% 0.00% 000% 0 7117+7411 C64 ' 14 RN.6-:47 C40e4.. F17wO 0 000% COWL GOD% 0.110% a@% aws OIW% 10196% (647.x7%) 17577% 0,7% Om% (O Ota) 7Ulm a13% 0 56 C3N. 91M ]4906 62"% (goom I//e% 07657%1 1113% 44 411 311 ti!% 61% (1B ALJ �?26) _ 1322% 004% 4003% toO?y Col% 0071 0.07, _)1107%)..0 (21474 N% poet/ (Qx') (014%) ons CIC% 31 T wTr.e.Y474'14 9A 30J0% 52A01 (39SON 1872% (1657%) 467% 11 A0rd47C .914.1 41 176% 6710 624% 2.61% on% 460% ).OR 1.40% 4Jft 6293. ].154 117% 110% 3.19% 3.16% :: '. ... �: .�... :-'.:�r:•. .,; .... -- .:: �::. 1716'111 5144 F4' i.. 1911 ..._ -... .. .. ., ... ;y. . . �.... .. .- .. .:. - .: .. 6114.. Vivo lab C 00 F47744906'. OA,64F%$.1% ..;CYI,YOFLOd . • ;-.•:-,,sasl6da swwrorllyl=.l. ... - ,. ..,06i>.ral'i+77Xlf•316nt3t6/P/en_ •�. ,;� 'A99scIB4ilsat •. .faPDndla+n9Pral.a.drra6ox :: - - , : ElGietloRAstat (i) Br•q . elu Wtll4r1 Moto ed6(7C4 MOWX FIfAwlcb0 , " A MMa11a4 P5p- Fu.dV-Endes 1M610" 1101 taxa 140 t999 low am 1001 7901 2054 7001 405 7101 300 am am 2110 T4141 1 "Qt41M16 sd4 J9OUPCUl*F%XbS Blinn TIw4 2 PI 'T. PAIS MOM '40.308 1.030 141.606 142.3" 414.900 0 0 0 0 D 0 0 0 0 0 3 A.U. Tu 04" IS,124 546AW 18721 254AR 418,626 47t.w 0 0 0 D 0 0 D 0 O 0 M1 4 he464yt Tr map 171) 19,47 60996 4159 am 15.319 20 14127 0 0 0 0 0 0 0 0 0 0 6 i14.M( djL-V 1. 1428 1.711 211,360 aM.12) 7,766 27506 IZ701 0 0 0 0 0 0 0 D 0 0 0 Wow P -A F...dm4 Tu It. I 11 4.810 (167660 14,902 20,006 6,]77 79,7]9 0 0 0 D 0 0 0 0 0 0 7 OMbW Furs*. 41412 (;60111 096 2.2m 3'm 3" 17.914 0 0 0 O O 0 0 0 0 D 4 a -F -d- 1,772 490 (9642 Pim) 17.363 GA" 4411 0 0 0 0 0 0 0 0 0 0 9 Cat. TV F.4.dw 11,14► (4444 404 7,n0 20,615 ISAI6 9.153 a 0 0 0 0 0 0 0 0 D 10 t)1d •.mcrn1r 799 8721 2m 246 537 (1661 an 0 0 0 0 0 0 0 0 0 0 11 1/140 F-.O..•EWoft 41,48 94'%a 1118 (09,000) :0)426 111•@0) 11."3 0 0 0 0 0 0 0 O 0 0 11 hI FRn76 S.- 3a9m 7]4.00'1 6IAM 26.Ow (00.3001 100,492 7" D a O 0 D 0 0 0 6 0 19 ON74u F fa9. 9h14r 8.920 Qf x600) 14700 MR 01 22.102 (2,127) I,9a0 0 0 O ' 0 O 0 a O 0 0 14 8441 t wwrio 963 on ).tF p.6m1 11.147 41.642 (LN8 0 0 e '0 0 0 0 0 0 0 16 YrAw7- 721.077 110.185 644,165 10967 n1. 0 )47,130 I.0ata66 16 Ita4M'tm Demo 179,"1 127,471 XK314 IM123 170.112 "00 '69.X6 0 0 0 0 0 0 0 0 0 0 Y Lk1 V14n4&L1 m,F 17 144v 6141'14 Lb4n14 Fw 224SA3 '740141 1243141 126,910 4111,0653 41166 i0,9A0 0 0 D 0 0 0 0 o D la "t 66216 7141095 1341.a1p 401.11 724,1 aV ry0/.7lq 714723 0 0 0 a a 0 0 0 0 0 M Mw Mn9lMnmf1161nwMp5 199,911 453,85 ,221 .i470 CaAA P6AN) LO3k2n a 0 0 0 0 0 0 0 0 0 20 ch.., b44rhs4 164AM (717701 01.141 1,11 214.013 64AM 104161 0 0 O o 0 0 0 0 0 0 31 Mm imt44 Ord pwWm 61977 (191q 14ta6 31.734 2D11.D" 216.410 1161154 0 0 0 0 0 0 0 D 0 0 22 RMW 6>me0 2a,"1 IMAM oa7 1@.176) 4471 "914 94007 0 0 0 0 0 0 0 D 0 0 23 E4U1t0 lnwe.•w4 C.Mw 3.621 SLI97 116,196) V07.610) 40.926 260106 flnum) D 0 0 D 0 0 0 0 0 0 6h04Mtiou n7-v4w 14,"6 79,142 (IQ3" 142,246) 34.11 NI,{L9 IgB5 0 0 0 0 0 0 0 0 0 0 25 C 1 6w4014 0 0 0 O 0 O 0 a 0 0 0 0 0 0 0 0 D 28 T.1.6- 41111" (79"78) �.1n .--.6001 78919 144,100 N114i31 1760 0 0 0 0 0 0 0 o a o 21 W/i6WAPOngs 1109942 Y14p8 I 611 1•{109111 16)4134 "1532 /42152 i✓V� 042 221,216 0 0 0 0 0 0 0 0 a 28 479.275 M262) 3KX2 654.711 Macau 176"2 636,"6 28 kbkpOervan MUD 531,90 (t]7252) 11931/ P640 361104 156412 11.4161 0 0 0 0 0 0 0 0 0 30 pJ.941VF4 61.60 (21,796 680174 "o -%O ("3.654) 61,x37 04.901) p431/) 0 0 0 D 0 0 0 0 0 31 1�761Y 76,4641 N,Qtl QZQ) 541722 (14600) ".00 mAM 625161 D 0 D D 0 0 0 0 0 32 P66801d lk704391 KOO 0.174 (101387) 114,765 (1)8.734) 66666 4.30.0]0 97.973 0 0 0 0 0 0 0 0 a 33 M. U- 0 0 0 0 0 0 9 0 0 0 0 0 0 0 0 0 0 Tr6d-041 34 ►130 tw"unps V-1hv 0 0 0 O 0 0 0 54670:1 u, / 0 O 0 0 0 D 0 0 0 36 Of- IM lib 401,3U 1 156,96]3) 437199 (60116:) 116@01.0m A 0 C 0 0 0 0 0 0 D 38 talc T4uryn 304 164,676 801,766 121",98.1 071,119 431,209 (601,1") 110,0(0 I,m inmag 0 0 0 0 0 D 0 0 a 31 AA"d 190.617 64937 1121712 723.673 20AM 13M 90 I10,]I/ �_ _^. ----• _531061" .,---. k,#V&VM #t Po 116 A p '. :: +. .._. 6666... .,._ . •; . :6666 ,. ;. 3.- Gw d 1114 GOreld Fwd (6c471a QhSola)'10 EZILAS.VyD-qcwPUN P—l`D Fm PAm* v." . •; r M .... .. ... , ... .. .... •.: '" 1014 iO 71T0P11w1 J1l AI ,...,. UQ l 1100'1 x001 x101 %001 MAOI UOI 1006Kris) %000 0 %010 x000 WOO Moo Mile Ima '0 0 91(Id 16"101t1O1 tt '0 %000 Moo 16010D MO0 MCO MAO %OOo Two %000 0 MAO Moo %MO x000 xme D 9011 w%Ip PPLK LMA Moo %oto %u9 woo V=0 %aoo MAO %WO %mo o +Imo Moo %Doo taco %000 0 1-MVIw se -10I+w0O K %00'1 •411 x003 1001 %00"1 xmt %O0'I V.W. Iw90W %010 %mO %010 xWO %000 MOD MOO %100 --"w%to99 %999 x4I1 %9C'Ol %11'11 Y46 it 146L1 M.V. l:td9 us 9t[ x0119 1611 xKi Itv1 %Ov 99E 41wC'1 V x111 i1t4NW111101 a %S&Q 1110) Inalsol tvivo 01 %/00 x100 %0001 %MCI x39/C %44K cV Willi Will %m %0141 %0611 %IVLI 1`09.P l"L K %WO%m'O %010 %WQ %m'o %000 %000 %WO %000 %AOD 0 x000 %010 %000 Milo 11000 %000 "^40+9.91101 M 9"001 PPl Ot %000 140'0 x000 9000 %000 1000 %010 x40 %W %W WO %Wo %000 %009 %ODD 11400 MAO Al 4-0-d t: P•M 41 "01010 S -mol %910 1%110) MOO) (x01 0) %0 01 x090 %"K %19'91 (tYr0.) %0IDl HO %It'll %Mf %310%1t'!01 11000 %mv P.1 W.PY too&0 a PO 9.00O1Roll 11 Mcl0 1000 16WO Swo %O0o MO %010 %mV N DOWO %ma 1MoODO %010 MCI* %mv MOO •1000 (wool) I, (%W 1) 9%941) t%9O►1 t%1vrJ (%" t92d %Ll tft %wo %000 %000 O MOO %010 410 09 00 %0 %000 000 %0 9a,lw5 op.4,%.wl'4+•p" 91 M00 %000 %01 0 %v O0 %000 %ADO %000 1101 -0 10 00 %000 x010 Moo %000 UP .4m %01 0 ��9N.�w9�1 I S9 1605'L %096z 11O1L %092 %094 105? 1091 %DSL M46 %9cc %949 %400 %K,10l %010 %OE9 •11 A-OvI p 91w/ n••1 -Y 1.:1 7 a1 To ""-"a %000 -mo "Wo %WO %WD MOO x000 %WO %mv 1%90&) Moo (%01 KJ LEEK Nvv[L) 41.11[ 1M7D) (x1-11 PO O4-1 640 -WO PPI LI Moo %00 it %m'o %000 %000 Moo %000 Moo %wo 1%.00.0 %Ogv00 1x1951) Ixlivo (%Ord %.711 Kpol t-op1 +40 01 %0001%1120) %WO 1009 %000 %WO %mv (1121) ga1+l lOwwa9 It %m v 119t %010 %oa0 %0:10, %000 %000 W 12 0v^/ 111." 01 %000 Moo Imo MAO %000 41000 %010 MAO wOP911wIDP"do 1 1110 9.w1t M9199O Mfg ItM c %OS'C -.091 74ST %oS t Las c MISS %"I %71.9 Ras) %261 %61't %09 Ptll," 1'21) ("al h 9w190 L PP/ 1 tact %OS9 %MT %Ot't %00f %mc %Ot9 1091 %491 %aI Mal) 1%291) %4vt %NOZ (%iiol [41'311 WAV 71 MO4•MO14o0vmd0RPL 2 x09 t VAS t %O'. c VA t %01 c tai t Us f %aS c Use %00'0 MOpml) 1%K Its (%LDvI fftt'OD9l 111.104) [211LI 1%000111 M0O 0 %oro MAV %010 %WD 1000 x000 limo Mal; P-d,u drba 5 %000MAO %W 0 %WO %WO %001 %mD %mv ..A P.O19 t %000 %700 1010 %mV %000 %011 1100V %00o O -imp d0 6 %p0 %tl21100 166"411sL %000 %lost xP0 %.wu Mow P•900101 n4Osy POB L %531 %vl it 1010 Mitt %WD MOV Moo MCOl PW -i t 4 -P-L&7w•dO • M tY1i1NYY IML Otai No oom W" /Om soot IOD[ aK La" ON 0101 1011 Not 251 IN& SII& 6t &IM S19PIR WA NS U Ot9+9(0L �0 R Po Y .. ..: _ 6uf1D0y01 KYldI1g71M�oRIDd 11111'1 YIMJNWW,1�4ldI'fl . -11RQ�u1 �1[J$Yj;(WfIj�1�U90:: . ' . xDs•e tR wld.lda �&IwR++3 �1�9 �hrAr nrti+►urj paw r.�1,ea �. 1 i ItiMAAIMSL 1 1 DliaPuS '� .IOOT�OA.IID O t+ 2001-03 FINANCIAL PLAN AND BUDGET Vehicle Replacement Requests CITY OF LODI CALIFORNIA 2001-03 FINANCIAL PLAN & BUDGET CAPITAL BUDGET DETAIL BY MISSION - Replacement Vehicle Requests ss r '" .zt �s OWN-" F X7001-02 "007r03;� , w .. ueated;, � . cr�w i ,Zr lents " ..✓-COSI _ Public Safety Police Protection Police Investigations 1 undercover units l 30,000 05-020 2 under cover units 2 60,000 05-078;05-080 Police Operations 3 patrol sedans 5 155,925 5 163,350 5 motorcycles l 19,000 1 20,000 e Animal Shelter 6 314 ton CNG truck l 40,000 Fire Department Emergency Services 7 Command vehicle 1 44,000 06-007 8 Sedan l 33,000 06-004 Total Public Safety 8 248,925 10 316,350 Public Utilities Water Utility Services Water 9 2 114 Ton Truck 1 52,310 share cost 50!50 with wtiv Wastewater Utility Services 10 Replace generator l 46,000 04-2665 I I Replace generator l 46,000 04-266 12 3/4 Ton Pickup 1 25,000 04-139 Electric Utility Services Electric Construction & Maintenance l3 Bucket Truck 1 220,000 09-002. 14 Line Truck/Digger 1 215,000 09-009, 15 Line Truck/Digger 1 215,000 09-010 Total Public Utilities 2 313,310 4 506,000 Transportation Streets and Flood Control Street Maintenance 16 Air Compressor 1 11,800 04-053 17 Nine Wheel Rubber Tire Roller 1 66,000 04-107 18 One -yard Front End Loader 1 58,300 04-023 19 Twelve -yard Dump Truck l 90,100 04-084 Total Transportation 4 226,200 - 2001-03 FINANCIAL PLAN & BUDGET CAPITAL BUDGET DETAIL BY MISSION - Replacement Vehicle Requests Leisure, Cultural & Social Services Parks and Recreation Parks Division Equipment Maintenance 20 Fiat bed Truck 21 Forklift 22 Dump Truck 23 One -ton Pickup Truck 24 Turf vehicles 25 Turfvehicles 26 112 Ton Pickup Truck 27 Mini Van 28 Mini Van 29 Mini Van 30 Mini Van 31 Boat 32 Tractor/Loader 33 Trim Mower 34 Turf vehicles Total Leisure, Cultural & Social Services Community & Economic Development Community Improvement 35 Mini Van Construction Development Building and Safety 36 Field Inspection Pickup Trucks Total Community & Economic Development General Government Organizational Support Services Field Services 37 Mini van/ sedan Total General Government TOTAL OPERATING BUDGET FUNDING LEVELS: EQUIPMENT FUND ELECTRIC FUND WATER FUND WASTEWATER FUND 1 29,680 7069 1 24,500 1 38,000 7018 1 28,000 7073 3 56,250 , .• 6,8,&10 3 60,000 17,18 & 19 1 21,500 7006 1 24,000 7035 1 24,000 7005 1 25,000 7004 1 24,000 7014 l 19,700 1 1 60,000 7048 1 25,000 325 3 60,000 Ml, M2 & TV 21 16 374,630 5 145,000 1 25,000 75 2 48,800 79 & 89 3 73,800 - 1 22,000 2088 1 22,000 0 - .-1.258,865 i - - - 967,350 i 425,000 215,000 52,310 46,000 738,310 425,000 435,000 71,000 931,000 The above is a listing of replacement vehicle requests. Per the budget and fleet policies, a funding level has been set and approved by Council. The funding level may not allow for all the requests to be filled. The fleet committee will recommend to the City Manager all vehicles to be replaced during the year based on criteria stated in the fleet policy and the available funding levels. PUBLIC SAFETY POLICE FIRE GRAFFITI ABATEMENT 2001-2003 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services / Police Department REQUEST TITLE: Police Under -Cover Vehicle Replacement Project Description Purchase one "under -cover" vehicle in 2001-2002 as a replacement for a vehicle that has met the retirement schedule; and obtainlinstall emergency and police equipment as needed to make the vehicle ready for the full range of investigative and surveillance duties. Project Objectives r,.,. Provide the Police Investigations Bureau with safe, properly equipped vehicles that will not malfunction during critical incidents. Since these vehicles are sometimes used under emergency conditions, advances in safety features that become available through regular replacement are desirable. In addition, such regular replacement helps to prevent visual familiarity with the vehicles among the local criminal element, which renders them less effective for surveillance. Existing Situation The listed vehicle (05-020) has reached mileage and age levels that are in excess of the Fleet Policy and Procedures guidelines for Class 1-B (police undercover) vehicles. The vehicle is a 1994 Chrysler Concord with 65,000 miles. This vehicle was budgeted for replacement in the FY 2000-2001 budget, but was not funded due to higher priorities depleting the available funds. Project Costs It is estimated that the vehicle will cost approximately $30,000, including purchase of the vehicle itself and the purchase and/or installation of police emergency and surveillance equipment. Wherever possible, existing equipment will be salvaged from retiring vehicles and installed in new ones. The recommended funding source is the equipment replacement fund. Schedule Budget Year: 2001/2002 2002-2003 Project Tota! Acquisition: $30.000 Total $30,000 $30,000 -3 l2�0 1 feet anager Da e -1- 2001-2003 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services 1 Police Department REQUEST TITLE: Police Under -Cover Vehicle Replacement Project Description Purchase two "under -cover' vehicles in 2002-2003 as replacements for vehicles that will meet their retirement schedule during the second year of the pending two-year budget period; and obtainlinstall emergency and police equipment as needed to make the vehicles ready for the full range of investigative and surveillance duties. Project Objectives Provide the Police Investigations Bureau with safe, properly equipped vehicles that will not malfunction during critical incidents. Since these vehicles are sometimes used under emergency conditions, advances in safety features that become available through regular replacement are . desirable. In addition, such regular replacement helps to prevent visual familiarity with the vehicles among the local criminal element, which renders them less effective for surveillance. Existing Situation It is projected that two existing vehicles will have reached mileage and age levels that will be in excess of the Fleet Policy and Procedures guidelines for Class 1-B (police undercover) vehicles, by the time replacement vehicles are purchased and equipped in the 2002-2003 budget year. The two vehicles are 05-078, a 1998 Pontiac sedan with 43,000 miles and 05-080, a 1997 Ford sedan with 45,000 miles. Project Costs It is estimated that each vehicle will cost approximately $30,000, including purchase of the vehicle itself and the purchase and/or installation of police emergency and surveillance equipment. Wherever possible, existing equipment will be salvaged from retiring vehicles and installed in new ones. The recommended funding source is the equipment replacement fund. Schedule Budget Year: 2001/2002 2002-2003 Project Total Acquisition: $0 $30,000 X 2 Total $0 $60,000 $60,000 r "�q -z' 1 -1 of meet Mana t r Date - 2 - 2001-2003 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services/Police Department REQUEST TITLE: Purchase of Police Patrol Sedans Project Description Purchase five police patrol sedans in 2001/2002, and five more in 2002/2003, as replacement vehicles for cars that will meet their retirement schedule during the next two years; and obtain emergency equipment and accessories to fully equip these police patrol sedans for duty. Project Objectives 1. Ensure that the Police Department is provided with safe, modern, and effective pursuit/patrol vehicles for its daily support needs. 2. Ensure that quantities of pursuit/patrol vehicles are adequate for staffing levels, providing for out -of - service and emergency replacement situations. Existing Situation The current fleet of police patrol sedans includes twenty-two vehicles. Five are needed in the 2001/2002 fiscal year, and five in the 2002/2003 fiscal year, to meet the current replacement schedule. The replacement patrol car is the Ford Crown Victoria four -door sedan at a current cost of $25,700 per car. Our hope is that the design of the car will not change significantly so the emergency equipment in the current vehicles can be reused. Planning on this limits the cost of emergency equipment and accessories to installation expenses only, approximately $2,000 per car. If this equipment cannot be reused, there will be additional costs to modify and equip the vehicles for service; i.e., back seat, protective screen, shotgun rack, radio rack, push bumper, etc. New emergency equipment, purchased and installed, is $4,000 per car. Because the current patrol cars will reach their designated retirement mileage by the time these Crown Victorias can be ordered, received, and readied for service, and because the availability of police patrol vehicles is limited to a very short order period, these sedans must be approved in 2000/2001. Project Work Completed Several years ago, the Police Department and the Public Works Equipment Maintenance Division formed the Police Vehicle Committee, comprised of representatives from both departments, to evaluate vehicles available to replace the Dodge Diplomat, which was no longer being manufactured. The group's recommendation was to standardize the police patrol fleet with Ford Crown Victorias. chedule and Proiect Costs Prior Project Budgets 2001/02 2002/03 Total Phasing Study Design Acquisition $155,925 $163,350 $319,275 Construction Total $155,925 $163,350 $319,275 Recommended Funding Sources Equipment Replacement Fund $155,925 S163,350 $319,275 Total $155,925 $163,350 $319,275 - 3 - 1999-2001 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services REQUEST TITLE: Purchase of Police Patrol Sedans Cost Detail 2000/2001 2002/2003 REPLACEMENT CARS: (1) Crown Victoria sedan $ 25,700 $ 25,700 Emergency equipment 4.000 4.000 Each car (including tax) $ 29,700 $ 29,700 r x 5 x 5 TOTAL $ 148,500 $ 148,500 Plus 5% cost increase $ 7,425 Plus 10% cost increase $ 14.850 GRAND TOTAL $ 155.925 $ 163.350 Alternatives 1. Do not replace police patrol sedans on the current schedule. This alternative would only delay the replacement of patrol vehicles, and consequently compound the amount of purchase dollars needed. Additionally, it would require the Police Department to use older, higher mileage vehicles that could be suspect of their ability to perform under emergency conditions. Because of being older, they would also be technically further behind, and possibly not as safe. Savings in purchase costs would be partly offset by greater mechanical repair and maintenance costs, and increased fuel use would be likely. 2. Require the Police Department to use alternative modes of transportation or downsize its patrol staff who require full-size patrol sedans. Downsizing patrol staff to require less officers would be directly opposed to the community -oriented policing program the City of Lodi has adopted. 3. Change police patrol sedan selection to a less-expensive model. This alternative has been considered. The Crown Victoria (full-size) patrol car is the car favored by the Lodi Police Department and the Public Works Fleet Services Division because of the number of units presently in service. Performance, size, safety features, familiarity, and serviceability are proven; choosing a different make and model now, with the multiple benefits to be realized by the "standardization" of the patrol fleet, would be ill advised. Project Effect on Operating Budget The current police patrol fleet consists of twenty-two cars. Maintaining these units requires that funds for fuel, car wash, maintenance and repairs be budgeted annually. et M nager 6at6 -4- 2001- 2003 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services/Police Department REQUEST TITLE: Police Motorcycle Replacement Project Description This project is to address the City of Lodi's commitment to the ongoing replacement of the Traffic Bureau's motorcycles on a three year rotational basis (pursuant to Council resolution 96-06.) The Traffic Bureau continues to be an invaluable asset in responding to the many requests for traffic enforcement and specialized operations, such as DUI Checkpoints. The Traffic Bureau also responds to major traffic accidents and utilizes extensive training in the investigation and reconstruction of such incidents. The assigned officers use police motorcycles as their primary mode of transport during emergency response and enforcement activities. Project Objective The objective is to maintain the Police Department's current level of traffic enforcement and safety by providing reliable motorcycles for our Traffic Bureau. Existing Situation Under the current motorcycle replacement plan, one motorcycle per year will be replaced. This continues to give the City reliable motorcycles and takes advantage of the Harley Davidson "buy- back" program. The Traffic Bureau has found the Harley Davidson FLHP-1 Motorcycle to be well suited to its operations. Project Costs It is estimated that each motorcycle will cost approximately $18,000, and that removal/reinstallation of existing emergency and enforcement equipment will cost approximately $1000. A 5% inflation factor has been added in the second year of the project. The recommended funding source is the equipment replacement fund. Schedule Budget Year 2001-2002 2002-2003 Project Tota! Acquisition: $19,00Q $20.000 Total' $19,000 $20,000 $39,000 ` Please note that the total cost does not reflect the buy-back of the used Harley Davidson motorcycle. After the buy-back, costs should be decreased significantly. Estimated trade-in value is between $9,000 and $11,000 per unit. -7 61 ee ana r Dat - 5 - 2001-2003 Financial Plan and Budget CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Fleet Services/Police Department REQUEST TITLE: Animal Services Truck Project Description Purchase (in FY 2002-2003) of a 3/. ton CNG truck with attached specialized body and associated equipment (two-way radio, etc.) for Animal Services Officer as a replacement for an existing vehicle. The existing vehicle will be nearing scheduled retirement during the second year of the upcoming two-year budget, and substantial grant funding is available during that time to defray the purchase. Project Objectives 1) Provide the Animal Services unit of the Lodi Police Department with an adequate number of appropriate vehicles to allow for efficient and effective performance of daily operations, especially in light of recent increases in staffing. 2) Continue to upgrade the fleet of Animal Services trucks to a safer, more humane, and more efficient style of vehicle. Newer trucks that are in service in this field are equipped with air conditioning for the animal transport box, ramps for leading large animals into the vehicle, and other features designed for safe handling and transport of animals. 3) Place in service for primary use an alternative fuel vehicle (specifically CNG), which is a city fleet planning objective. A CNG vehicle would also improve humane conditions for the animals, in that exhaust fumes would not be a factor during transport. Similarly, employees working around the box while the vehicle is idling (a likely situation during the summer when the A/C is running) would not be exposed to such fumes. Existing Situation The existing vehicle is a 1991 Dodge D250 cab and chassis with an animal transport body. The vehicle currently has 68,000 miles on it. It is estimated that based on current rates of usage, the vehicle will reach 80,000 miles and will be 12 years old in the second year of the two year budget. The Fleet Policy and Procedures guideline for the retirement of such vehicles (Class 4-A) is 10 years and 85,000 miles; as a result, the vehicle will have not met the mileage guidelines. However, preliminary approval has been received for approximately $8700 in federal grant funding that would substantially defray the cost of the project, and it is believed that such funding would be less available in future years. Given this factor, and that the City's goal of introducing low -emissions vehicles to the fleet would be furthered, it is recommended that the replacement of this vehicle be budgeted. Schedule and Project Costs Prior Project Budgets 2001/02 2002/03 Total Acquisition $40,000 $40,000 0 Total 0 $40,000 $40,000 Recommended Funding Sources Capital Equipment Fund $40,000 $40,000 Total $40,000 $40,000 It is estimated that the project will cost approximately $40,000, including the purchase of the vehicle itself, and adding the specialized body, equipment and two-way radio needed to perform required operations. The CNG upgrade will be paid for with separate grant funding from the $8700 mentioned above. �1 Mana er Date t3E 2001-02 Financial Plan and Budget CAPITAL EQUIPMENT BUDGET REQUEST ACTIVITY: Emergency Services - Fire REQUEST TITLE: Fire Command Vehicle (Replacement) Project Description: Purchase a Sports Utility Vehicle for Shift Battalion Chiefs Project Objectives: Replace 16-yearold vehicle and place Battalion Chiefs in a single vehicle with the resources to command emergency scenes. Existing Situation: The current vehicle is a 19S6 full-size Chevrolet Van (06-007). The vehicle currently has 94,000 miles on the odometer and will be 16 years old during the budget cycle. This vehicle exceeds established guidelines of seven years for replacement as stated in the City of Lodi Fleet Policy Manual. After evaluating the department fleet, it was determined no vehicle presently meets the requirements for a command vehicle. The 1936 Chevrolet Van was originally designed -for utilization as a command vehicle. It has never met the expectations for this utilization. The reassignment of the Battalion Chiefs to a shift schedule calls for sharing a single vehicle creates the need for an operational command vehicle. The vehicle will be used as the command post for most emergency events. - COST Sports Utility Vehicle 33,000 Incident Command Cabinet 2,000 Code 3 package 3,500 Radio equipment 5.500 TOTAL 544,000 Schedule and Project Costs: 2000-01 2001-02 2002-03 Total Phasinc, Study Acquisition 44,000.00 44,000.00 Construction Total 44,000.00 44,000.00 Recommended Funding Source General Fleet Fund Total S44,000.00 S44,000.00__ Alternatives: 1. Utilize sedan. 2. Defer replacement to a subsequent budget year. -7- 2002-03 Financial Plan and Budget CAPITAL EQUIPMENT BUDGET REQUEST ACTIVITY: Emergency Services - Fire REQUEST TITLE: Staff Vehicle Replacement Project Description: Purchase a replacement vehicle for staff. Project Objectives: Provide a safe, reliable vehicle for staff personnel. These vehicles are used for emergency services and must maintain a high degree of reliability and dependability. This vehicle will meet the alternate fuel vehicle requirements of the city. We plan to suggest to the fleet committee to search for outside grant funding, if available. Y,.,.•.' Existing Situation: The vehicle to be replaced is a 1990 Plymouth Voyager (06-004). The vehicle currently has 81,000 miles on the odometerand will be 13 years old during the 2002-03 bud;et cycle. This vehicle exceeds the established guideline of seven years for rcplacement as stated in the City of Lodi Fleet Policy Manual. COST Mid-size sedan 28,000 Code 3 package 1,500 Radio equipment 3.500 TOTAL 33,000 Schedule and Project Costs: 2000-01 2001-02 2002-03 Total Phasing Study Acquisition 33,000.00 33,000.00 Construction Total 33,000.00 33,000.00 Recommended Funding Source General Fleet Fund Total 33 000.00 33 000.00 ALTERNATIVES 1. Continue to utilize the existing vehicle. 2. Defer replacement to a subsequent budget year. - 8 - PUBLIC UTILITIES ryr.. ELECTRIC WATER WASTEWATER 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST . ACTIVITY: Public Works — Water/Wastewater Division REQUEST TITLE: 2 -1/4 -Ton Truck (#04-125) with Utility Bed with Three -Yard Dump Bed and Bumper Crane Project Description Purchase a new 2 U4 -ton Cab and Chassis with utility bed with a three -yard hydraulic dump bed with a bumper crane to be installed on the new WatcdlWastcwater 2-1/4 ton service truck, No. 04.125. r v., Project Objectives 1. Replace a 1989 Dodge D350 I -Ton Utility Body, with a new larger 2'/. -ton truck with utility body. 2. Dispose of the existing unit by trade-in or at auction and transfer 2 -way radio to new vehicle. Existing Situation Unit No. 04-125 currently has an odometer reading of 30,407 miles. This unit was purchased for 515,800 in 1989 and has accumulaied`S9,438 in repairs and 571 1 in maintenance costs. It is used on a daily basis by the Water/Wastewater Division's maintenance crew and is indispensable to the Water and Wastewater Utilities. This vehicle is used daily in upgrading water/wastewater services and in emergency situations to repair broken water mains or service connections. This vehicle will also be equipped with a bumper crane to lift heavy tools and parts onto the truck (cement saws and pumps) and to lift fire hydrrnts. The existing utility body is too small to use on the new WatedWastewater service truck No. 0-1.125. This new utility body would be stocked with all the tools to make any type of repair and carry a parts inventory for daily use and for handling emergencies. The dump bed will be utilized to haul dirt and debris or trench patch material to and from job sites. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-2002 2002-03 Total Phasing Study Dh sigrr Acquisition/Vehicle Replacement Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund (5011.) Wastewater Fund (50"/0) Total 552,310 552,310 552,310 S52,310 526,155 S26,155 526.153 $26.155 _ $52,310 552,310• •Note: Trade-in value is not included so that adequate funds are bud¢eted for purchase orvehicle. Alternatives Postpone replacement and continue with escalating repair costs. Endure more frequent breakdowns which will have a negative impact on our customers. Project Effect on Operating Budget Eliminate any further expenses for this aging vehicle. Approved: Fleet & Facilities Manager - 9 - Date 2001.-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Noris — Water/Wastewater Division REQUEST TITLE: Generator for N11olcelumne River Sanitary Sewer Lift Station Project Description Replace existing natural gas standby generator, No. 04-2665 for 4lokelumne River Sanitary Sewn Lift Station, Project Objectives 1. Replace a 1951 Smith & Loveless Model 81-0296 generator with a new comparable model_ 2. Dispose of existing unit by trade-in or at auction. Existing Situation Unit No. 04-265 currently has a meter hour reading of 254 hours. This unit was purchase for approximately S 1.0,000 in 1931 and has accumulated 5.1,557 in repairs and maintenance costs. This generator is used as standby power for hlokelumne River Sanitary Sewer Lift Station to continue sewage flow during power outages. Because of this unit's age, it is difficult to find parts and maintenance costs %ill continue to escalate. Project Work Completed Schedule and Proiect Costs Phasing Study Design AcquisitionNehiele Replacement Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Wastewater Fund Total Alternatives Prior Project Budgets 1999-00 2000-01 2001-2002 2002-03 Total S46,000 S-16,000 Continue to budget the following lift stations in 2003104 and 536,000 546,000 2004105: Northeast Lift, Park West Lift, Woodlake Lift. 5.16.000 546.000 546,000 546,000 Postpone replacement. Continue with escalating repair costs, rely on aging equipment to continue performing during power outages, and run the risk of total failure which would allow raw sewage to now into streets and the Mokclumne River. Project Effect on Operating Budget Eliminate any further expenses for this aging generator, reduce the threw: to public health and possible risk of sc%%agc discharges to the'Ntokelumne River. Approved: Fleet & Facilities Manager Date -10- 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works —Water/Nastew2ter Division REQUEST TITLE: Generator for Rivergate Sanitary Seaver Lift Station Project Description Replace existing natural gas standby generator, No. 04.266, for Riveroate Sanitary Sewer Lift Station. Project Objectives 1. Replace a 1979 Smith & Loveless Model 81-0228-C generator with a new comparable model. 2. Dispose of existing unit by trade-in or at auction. Existing Situation Unit No. 04-266 currently has a meter hour reading of 520 hours. This unit % as purchase for approximately S 10,000 in 1979 and has accumulated S3,077 in repairs and maintenance costs. This generator is used as standby power for Rivergatc Sanitary Lift Station to continue scv age flow during power outages. Because of this unit's age, it is difficult to find parts and maintenance costs will continue to escalate. Project Work Completed Schedule and Proiect Costs Phasing Study Design Acquisition/Vehicle Replacement Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Waste,iwter Fund Total Alternatives Prior Project Bud.Rets 1999-00 2000-01 2001-2002 2002-03 Total 546,000 546,000 S46,000 546,000 S-16.000 546.000 546,000 54,000 Postpone replacement. Continue with escalating repair costs, rely on aging equipment to continue performing during power outages, and run the risk of total failure which would allow raw sewage to flow into streets and the blokelumne River. Project Effect on Operating Budget Eliminate any further expenses for this aging generator, reduce the threat to public health and possible risk of se«-agc discharges to the Mokelumne River. Approved: Fleet & Facilities Manager Date 2001-2003 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works Wastewater Utility REQUEST TITLE: Purchase New'/, Ton Pickup (Unit No. 04-139) Project Description Replace 1988 Dodge Pickup, Unit No. 04-139, with a new'/, ton pickup for the White Slough Water Pollution Control Facility. Project Objectives 1. Increase vehicle reliability. 2. Eliminate down time. 3. Eliminate continued repair costs. Existing Situation Unit No. 04-139 was purchased for use by the White Slough staff in 1988. This vehicle has accumulated 80,915 miles on the odometer, repair costs of more than S 10,785, and corresponding down time to make repairs. The White Slough staff uses this vehicle on a daily basis. They perform a variety of essential tasks which includes transporting supplies needed for Facility maintenance, delivering equipment for repair to local shop, and performing various inspections and repairs around Plant facilities. Project Work Completed Schedule and Project Costs Prior Project Budvets 2001-2002 2002-03 2003-04 2004-05 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Wastewater Capital Reserve Total $25,000 $25,000 525,000 525,000 $25,000 525,000 Alternatives Continue using the existing Unit No. 04-139 and accumulate additional repair costs and endure continued down time. Project Effect on Operating Budget Approve Flee Facilit ts Manager Date - 12 - 2001-2003 Financial Plan and Budget CAPITAL BUDGET REQUEST ACTIVITY: Electric Construction and Maintenance REQUEST TITLE: Bucket Truck (Replacement) PROJECT DESCRIPTION Replace existing Bucket Truck #09002. PROJECT OBJECTIVES To provide a dependable bucket truck with sufficient rating for hauling materials and equipment for today's needs. EXISTING SITUATION Bucket Truck #09002 is a 1991 International 4900. This truck was delivered on 04/24/91. It is approximately 10 years old with an odometer reading of 30,591. The engine has significant idle time over and above the measured road mileage due to bucket operation, installing transformers and keeping the battery charged for radio transmission during the workday. The original cost of the vehicle was $115,683. The cost of maintenance and repairs to -date is $24,623. This truck does not have the Gross Vehicle Weight (GVW) carrying capacity needed when fully loaded with tools and equipment necessary to perform all tasks assigned in today's environment of prompt service to customers at the lowest possible cost. It is essential to be prepared to perform all tasks on arrival at a job site. The minimum replacement criterion of the 'Fleet Policies and Procedure" as outlined under "Guidelines for Utilization/Replacement" Section 4.5 is 10 years. This vehicle (#09002) Bucket Truck meets the criteria. SCHEDULE AND PROJECT COSTS Prior 8udaet 2002-2003 Total Project Phasing Study Design Acquisition Construction 220,000 $220,000 Total 220,000 $220,000 Recommended Funding Source Capital Outlay Fund ALTERNATIVES Keep Truck #09002 (not recommended) which could result in significant downtime and cost for major repairs. FINANCE 2001-2003 IMPLEMENTATION Upon approval, purchase new truck, transferring radio equipment and sell vehicle at auction in 2002/2003 fiscal year. - 13 - 2001-2003 Financial Plan and Budget CAPITAL BUDGET REQUEST ACTIVITY: Electric Construction and Maintenance REQUEST TITLE: Line Truck/Digger (Replacement) PROJECT DESCRIPTION Replace existing Line Truck/Digger #09009. PROJECT OBJECTIVES To provide a dependable line truck with sufficient rating for hauling materials and equipment for today's needs. EXISTING SITUATION Line Truck/Digger #09009 is a 1989 Ford F800 with a derrick/digger unit. This truck was delivered on 7/14/89. It is approximately 12 years old with an odometer reading of 37,472. The engine has significant idle time over and above the measured road mileage due to digging pole holes, setting poles,, installing transformers and keeping the battery.charged for radio transmission during the work day. The original cost of the vehicle was $136,355. The cost of maintenance and repairs to date is $23,677. This truck does not have the Gross Vehicle Weight (GVW) carrying capacity needed when fully loaded with tools and equipment necessary to perform all tasks assigned in today's environment of prompt service to customers at the lowest possible cost. It is essential to be prepared to perform all tasks on arrival at a job site. The minimum replacement criterion of the "Fleet Policies and Procedure" as outlined under "Guidelines for Utilization/Replacement" Section 4.5 is 10 years. This vehicle (#09009) Line Truck/Digger meets the criteria. SCHEDULE AND PROJECT COSTS Prior Budget 2001-2002 Total Project Phasing Study Design Acquisition 215,000 $215,000 Construction Total 215,000 $215,000 Recommended Funding Source Capital Outlay Fund ALTERNATIVES Keep Truck #09009 (not recommended) which could result in significant downtime and cost for major repairs. FINANCE 2001-2003 IMPLEMENTATION Upon approval, purchase new truck, transferring radio equipment and sell vehicle at auction in 2001/2002 fiscal year. - 14 - 2001-2003 Financial Plan and Budget CAPITAL BUDGET REQUEST ACTIVITY: Electric Construction and Maintenance REQUEST TITLE: Line Truck/Digger (Replacement) PROJECT DESCRIPTION Replace existing Line Truck/Digger #09010. PROJECT OBJECTIVES To provide a dependable line truck with sufficient rating for hauling materials and equipment for today's needs. EXISTING SITUATION ;�.• Line Truck/Digger #09010 is a 1989 Ford F800 with a derrick/digger unit. This truck was delivered on 7/18189. It is approximately 12 years old with an odometer reading of 30,200. The engine has significant idle timelover and above the measured road mileage due to digging pole holes, setting poles, installing transformers and keeping the battery charged for radio transmission during the work day. The original cost of the vehicle was $135,690. The cost of maintenance and repairs to date is $16,669. This truck does not have the Gross Vehicle Weight (GVW) carrying capacity needed when fully loaded with tools and equipment necessary to perform all tasks assigned in today's environment of prompt service to customers at the lowest possible cost. It is essential to be prepared to perform all tasks on arrival at a job site. The minimum replacement criterion of the "Fleet Policies and Procedure" as outlined under "Guidelines for Utilization/Replacement" Section 4.5 is 10 years. This vehicle (#09010) Line Truck/Digger meets the criteria. SCHEDULE AND PROJECT COSTS Prior Budget 2002-2003 Total Project Phasing Study Design Acquisition 1 215,0001 $215,000 Construction Total 1 215,0001 $215,000 Recommended Funding Source Capital Outlay Fund ALTERNATIVES Keep Truck #09010 (not recommended) which could result in significant downtime and cost for major repairs. FINANCE 2001-2003 IMPLEMENTATION Upon approval, purchase new truck, transferring radio equipment and sell vehicle at auction in 2002/2003 fiscal year. - 15 - TRANSPORTATION STREETS STORMDRAINS TRANSIT 2001-2003 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works - Street Division REQUEST TITLE: Air Compressor (904-053) Project Description Replace 185 CFM Air Compressor. Project Objectives 1. Replace a 1979 Sullair au compressor (Unit No. 04-053) with anew like -type unit. 2. Dispose of the existing unit by trade-in or at auction. Existing Situation Unit No. 04-053 has an hour meter reading of 624 hours. This unit's minimum replacement criteria was met in 1989. This unit was purchased for 511,607 in 1979 and has accumulated 518,222 in repairs and 5590 in maintenance costs. This unit has an air filter and attachment for a fresh air breathing hood utilized when sand blasting. This unit is used by Street Division crews for maintenance. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 20092-03 Total Phasing Study Design AcquisitionNehicle Replacernent Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Wastewater Fund Total Alternatives S11,800 S11,800 511,800 S11,800 511,800 S11,800 S11,800 511,800 Continue to use current equipment and accumulate higher than normal maintenance expenses. Project Effect on Operating Budget None. APPROVAL: Fleet and Fac ities Manager Date - 16 - 2001-2003 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works - Street Division REQUEST TITLE: Nine Wheel Rubber Tire Roller (#04-107) Project Description Replace a nine -Wheel rubber tire roller (Unite No. 04-107) tiNith a new 27,000 Lbs. ArticulatingNine-Wheel Rubber Tire Roller. Project Objectives 1. Replace a 1972 9-%vheel rubber tire roller (No. 04-107). 2. Dispose of the existing unit by trade-in or at auction. Existing Situation Unit 04-107 has an hour -meter reading of 3,140 hours. The minimum replacement criteria for this type of vehicle is 15 years. This unit was purchased for $9,010 in 1939 and has accumulated S30,975 in repairs and S750 in maintenance costs. This unit is 29 years old and its dependability is questionable. This type of equipment is not available in alternative fuel engines. This unit is used on a daily basis during the paving season by Street Division crews for maintenance. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design AcquisitionNehicle Replacement 566,000 566.000 Construction Total 566,000 566,000 Recommended Funding Sources Capital Outlay Fund $66,000 566,000 Electric Utility Fund Water Fund Waste%,ater Fund Total 566,000 566,000 Alternatives Continue to use current equipment and accumulate higher than normal maintenance expenses. Project Effect on Operating Budget N1, one. APPROVAL: Fleet and Fac ities Manager Date 17- 2001-2003 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works - Street Division REQUEST TITLE: One -Yard Front -End Loader with Two -Wheel Drive (104-023) Project Description Replace a one -yard front-end loader with two -wheel drive tractor. Project Objectives 1. Replace a 1986 one -yard front-end loader with two -wheel drive tractor (Unit No. 04-023) with a new like -type unit. 2. Dispose of the existing unit by trade-in or at auction. Existing Situation Unit No. 04-023 has an hour meter reading of 3,159 hours. This unit's minimum replacement criteria was met in 1993. This unit was purchased for $21,282 in 1986 and has accumulated 531,120 in repairs and S2,424 in maintenance costs. This request was originally submitted two years ago. Since that time, it has been necessary to spend an additional S9,000 in repairs. This unit is used on a daily basis by Street Division crews for maintenance. Schedule and Proiect Costs Alternatives Continue to use current equipment and acquire higher than normal maintenance expenses. Project Effect on Operating Budget None. APPROVAL: ��_ 3 e z o f Fleet and Fac ities Manager Date - 18 - Prior Budgets 1999-00 2000-01 2001-02 Project 20002-03 Total Phasing Study Design Acquisition/Vehicle Replacement 558,300 558,300 Construction Total 558,300 558,300 Recommended Funding Sources Capital Outlay Fund S58,30o 558,300 Electric Utility Fund Water Fund Wasteoater Fund Total 558,300 558,300 Alternatives Continue to use current equipment and acquire higher than normal maintenance expenses. Project Effect on Operating Budget None. APPROVAL: ��_ 3 e z o f Fleet and Fac ities Manager Date - 18 - 2001-2003 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Public Works - Street Division REQUEST TITLE: Twelve -Yard Dump Truck #_L04-084) Project Description Replace a six-yard dump truck. Project Objectives 1. Replace a 1985 6 -yard dump truck with a new 12 -yard dump truck. 2. Dispose of the existing unit by trade-in or at auction. Existing Situation Unit 04-034 has an odometer reading of 93,276 miles. The minimum replacement criteria for this type of vehicle is 15years or 55,000 miles. This unit was purchased for 544,603 in 1985 and has accumulated 337,130 in repairs and S 1,910 in maintenance costs. This unit has a very sick engine and its dependability is questionable. The upgrade request is to provide the Street Division with greater hauling capabilities at a reduced labor cost. This size truck is available in alternative fuel CNG engines. It is staffs intention to write specifications around a CNG product line. This request was originally submitted two years ago. Since that time, it has been necessary to spend an additional 52,000 in repairs. This unit is used on a daily basis by Street Division crews for maintenance. Schedule and Proiect Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition/Vehicle Replacement 590,100 S90,100 Construction Total $90,100 590,100 Recommended Funding Sources Capital Outlay Fund $90,100 590,100 Electric Utility Fund Water Fund Wastewater Fund Total $90.100 590.100 Alternatives Continue to use current equipment and accumulate higher than normal maintenance expenses. Project Effect on Operating Budget None. APPROVAL: Fleel-and Faci 'ties Manager Date -19- LEISURE, CULTURAL & SOCIAL SERVICES PARKS RECREATION LIBRARY COMMUNITY CENTER 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Equipment Maintenance REQUEST TITLE: Flat bed truck Project Description Purchase (1) flat bed one -ton truck to replace a one -ton flat bed truck (Vehicle No. 7069) Project Objectives This truck is used daily to haul materials such as brush, broken concrete, garbage, etc. Existing Situation This vehicle was budgeted for in the 1999/2000 budget, but has yet to be replaced. Project Work Completed This vehicle has 80,000 miles and meets the criteria set forth in the City of Lodi's Fleet Policies and Procedures. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $29,680 $29,680 Construction Total $29,680 $29,680 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives 529,680 $29,680 $29,680 $29,680 Continue to operate this vehicle in a manner that continually disrupts work schedules due to downtime and repairs. Project Effect on Operating Budget None - 20- 2001-03 Financial Plan and Budget Request CAPITAL ]IMPROVEMENT BUDGET REQUEST ACTIVITY: Equipment Maintenance REQUEST TITLE: Forklift Project Description Purchase of one (1) Forklift to replace a 1961 forklift Project Objectives To facilitate the loading and unloading of materials. Existing Situation Currently the forklift we have is a 1961 -year model. It was a Pubic Works forklift that was to be disposed of. It was given to our department to replace a 1965 forklift that was totally inoperative. This vehicle has major mechanical problems and is very difficult to find parts for. Project Work Completed Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $24,500 $24,000 Construction Total $24,500 $24,500 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives $24,500 $24,500 $24,500 $24,500 Continue to operate this vehicle in a manner that continually disrupts work schedules due to downtime and repairs. Project Effect on Operating Budget None - 21 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ,CTIVTl"it: Equipment Maintenance REQUEST TITLE: Dump Truck Project Description Purchase (1) one ton dump truck. This is to replace a 1978 International 1600 dump truck (Vehicle No. 7018) Project Objectives To haul brush, dirt, etc. Existing Situation This vehicle is 23 years old and is time to be replaced. It is very large and we feel we can make better use out of a smaller dump truck. A smaller dump truck would allow use more diversity in its usage. A smaller dump truck will cost substantially less. Project Work Completed This vehicle meets the City of Lodi's Fleet Policies and Procedures criteria for replacement. schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $38,000 $38,000 Construction Total $38,000 $38,000 Recommended Funding Sources Capital Outlay Fund $38,000 $38,000 Electric Utility Fund Nater Fund Sewer Fund Total $38,000 $38,000 Alternatives Continue to operate this vehicle with higher maintenance costs and not as efficient as we can be. Project Effect on Operating Budget None -22- 2001-03 Financial Plan and Budget Request CAPITAL IlVIPROVEMENT BUDGET REQUEST CTIVITY: Equipment Maintenance REQUEST TITLE: 1 Ton Pickup Truck Project Description Purchase (1) one ton pickup truck. To replace a 3/ ton pickup truck (Vehicle No. 7073) Project Objectives To tow the Parks Divisions 6600 LB mower from park to park. E,dsting Situation This vehicle has close to 100,000 miles. We feel that increasing the size to (1) one ton will aid in the life of the vehicle. Project Work Completed This vehicle meets the City of Lodi's Fleet Policies and Procedures criteria for replacement. schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $28,000 $28,000 Construction Total $28,000 $28,000 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total $28,000 $28,000 Alternatives Continue to operate this vehicle with higher maintenance costs and disruption transportation needs. Project Effect on Operating Budget None - 23 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST .CTINM: Equipment Maintenance REQUEST TITLE: Turf Vehicles Project Description Purchase (3) turf vehicles to replace Cushman 6, 8, and 10 Project Objectives To provide Park Division employees with safe and reliable equipment to perform there job duties in a proficie'zt manner. Existing Situation These vehicles are used to prepare our ball diamonds and maintenance of parks. This was budgeted in the 2000-01 budget, but has yet to be replaced. Project Work Completed These vehicles satisfy the criteria of the City of Lodi's Fleet Policies and Procedures. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives Continue to operate vehicles with increasingly higher repair costs and downtime. Project Effect on Operating Budget None - 24 - $56,250 $56,250 $56,250 $56,250 $56,250 $56,250 $56,250 $56,250 2001-03 Financial Plan and Budget Request CAPITAL ]IMPROVEMENT BUDGET REQUEST CTIVTTY: Equipment Maintenance REQUEST TITLE: Turf Vehicles Project Description Purchase (3) turf vehicles to replace Cushman 17, 18, and 19. Project Objectives To provide Parks Division employees with safe and reliable equipment to perform there job duties in a profic4ne'utanner. Existing Situation These vehicles are used to prepare our athletic fields and maintenance of our parks. Project Work Completed These vehicles are currently on a replacement schedule of 10 years and meet the criteria of the Fleet Policies and Procedures. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $60,000 $60,000 Construction Total $60,000 $60,000 Recommended Funding Sources Capital Outlay Fund 560,000 $60,000 Electric Utility Fund Water Fund Sewer Fund Total $60,000 $60,000 Alternatives Continue to operate vehicles with increasingly higher repair costs and downtimes Project Effect on Operating Budget Jone - 25 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST kCTIVITY: Equipment Maintenance REQUEST TITLE: Full Size 'A ton Pickup Truck Project Description Purchase one (1) '/a ton pickup truck (Vehicle No. 7006) Project Objectives To provide park employees with a safe reliable vehicle to perform there job duties. Existing Situation This vehicle has close to 100,000 miles and qualifies for replacement in the City of Lodi's Fleet Policies and Procedures. This vehicle was budgeted for in the 1999/2000 budget, but has not yet been replaced. Project Work Completed This vehicle meets the City of Lodi's Fleet Policies and Procedures criteria for replacement. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $21,500 $21,500 Construction Total $21,500 $21,500 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives $21,500 $21,500 $21,500 $21,500 Keep operation this vehicle, disrupting schedules and increasing costs due to breakdowns. Project Effect on Operating budget one - 26 - 2001-03 Financial Plan and Budget Request CAPITAL MPROVEMENT BUDGET REQUEST %CTIVrrY: Equipment Maintenance AEOUEST TITLE: Mini -Van Project Description Purchase (1) mini -van to replace a 1989 Dodge Caravan (Vehicle No. 7035) Project Objectives Provide safe and reliable transportation for the after school program and coordinator. Existing Situation Currently a motor pool car is being used, whereas the 1989 Dodge is in the shop with major engine problems. It is not going to be repaired due to the cost. Project Work Completed This vehicle has 49,065 miles and was not anticipating replacing. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $24,000 $24,000 Construction Total $24,000 $24,000 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total $24,000 $24,000 524000 $24,000 Alternatives Continue to use the motor pool car. This vehicle is in inferior condition and I foresee problems with it in the future. Project Effect on Operating Budget None - 27- 2001-03 Financial flan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST .CTIVITY: Equipment Maintenance REQUEST TYME: Mini -Van ' Project Description Purchase (1) mini -van to replace a 1989 Dodge Caravan (Vehicle No. 7005) Project Objectives Provide safe and reliable transportation for our Recreation Supervisor - Existing Situation This vehicle is used to transport our Recreation Supervisor to sport activities and transport equipment to these grounds. This vehicle was put into the 1999/2000 budget, but has yet to be replaced. Project Work Completed This vehicle has 100,000 miles. It satisfies the criteria of the City of Lodi's Fleet Policies and Procedures. schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $24,000 $24,000 Construction Total $24,000 $24,000 Recommended Funding Sources Capital Outlay Fund $24,000 $24,000 Electric Utility Fund Water Fund Sewer Fund Total $24,000 $24,000 Alternatives Continue to operate this vehicle, disrupting work schedules due to breakdowns and downtime. Project Effect on Operating Budget None -P8_ 2001-03 Financial Plan and Budget Request CAPITAL ENAPROVEMENT BUDGET REQUEST ACTIVITY: Equipment Maintenance REQUEST T1TLE: Mini -Van Project Description Purchase (1) min -van to replace a 1987 Dodge Caravan (Vehicle No. 7004) Project Objectives To provide transportation for the Park Superintendent to travel to job sites and attends meetings. Existing Situation This vehicle has close to 90,000 miles and is constantly having mechanical failures. It was budgeted for replacement in the 1999/00 budget, but has not yet been replaced. Project Work Completed This vehicle meets the City of Lodi's Fleet Policies and Procedures criteria for replacement. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $25,000 $25,000 Construction Total $25,000 $25,000 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives $25,000 $25,000 $25,000 $25,000 Continue to operate this vehicle with higher maintenance costs and disruption transportation needs. Project Effect on Operating Budget None - 29 - 2001-03 Financial Plan and Budget Request CAPITAL MPROVEM ENT BUDGET REQUEST 1CTIVITY: Equipment Maintenance REQUEST TTPLE: Mini -Van Project Description Purchase (1) mini -van to replace a 1989 Dodge Caravan (Vehicle No. 7014) Project Objectives To provide safe and reliable transportation for Recreation Supervisor. Existing Situation This vehicle is used by our Recreation Supervisor to go to sporting activities and to transport equipment to these grounds. This vehicle was budgeted in the 2000/2001 budget, but has yet to be replaced. Project Work Completed This vehicle satisfies the criteria of the City of Lodi's Fleet Policies and Procedures. Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $24,000 $24,000 Construction Total $24,000 $24,000 Recommended Funding Sources Capital Outlay Fund $24,000 $24,000 Electric Utility Fund Water Fund Sewer Fund Total $24,000 $24,000 Alternatives Continue to operate this vehicle, disrupting work schedules due to breakdowns and downtime. -oject Effect on Operating Budget None - 30 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST kCTIVITY: Equipment Maintenance BEQUEST TITLE: Boat Replacement Project Description Purchase (1) boat to replace a boat at Lodi Lake. (Boat No. 1) Project Objectives rel To move docks, watch over and rescue the people that rent the aquatic equipment at Lodi Lake. Existing Situation This boat is over 17 years old. It is in very poor shape. The sides have to be chained to one another to keep them up. It is fiberglass construction and leaks water. The bottom of the boat fills with water every year. This is also the boat that the Police Department used in the recent boating accident on the river. Project Work Completed This boat doesn't meet with the City of Lodi's Fleet Policies and Procedures criteria for replacement. It falls short by 3 years. It is felt the need is definitely here, on the standpoint of mechanic and safety. Schedule and Project Costs R;g "* Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives Continue to operate this boat with being unreliable and compromising safety. Project Effect on Operating Budget Vone - 31 - 19,700 _ 19.700 19,700 19,700 19,700 19,700. 19,700 19,700 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST \CTrVM: Equipment Maintenance REQUEST TTTLE: Tractor Project Description Purchase (1) Tractor/Loader to replace a 1994 John Deere Tractor (Unit No. 7048) Project Objectives To provide the Parks Department with efficient and reliable equipment to perform there duties, Existing Situation Currently the Parks Division is using a John Deere tractor designed for farm use. It is big and cumbersome. This unit is very limited due to its size. It also has had mechanical problems plaguing it throughout the period we have had it. Project Work Completed This tractor will meet the criteria of the Fleet Policies and Procedures. - Schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $60,000 $60,000 Construction Total $60,000 $60,000 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives $60,000 $60,000 110NEW7, 11M Continue to operate under existing conditions and experience the awkwardness and ineffectiveness of the tractor. Increasingty higher repair costs and downtime, \'roject Effect on Operating Budget None - 32 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST CTIMITY: Equipment Maintenance REQUEST TITLE: Trim Mower Project Description Purchase (1) trim mower to replace trim mower (Mower No. 325) Project Objectives To provide the Parks Department with a safe and reliable mower to keep the parks looking well groomed. Existing Situation This mower is used to trim the outer acreage of all the parks. Project Work Completed This mower will meet the criteria of the Fleet Policies and Procedures. ,chedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing - Study Design Acquisition $25,000 $25,000 Construction Total $25,000 $25,000 Recommended Funding Sources Capital Outlay Fund $25,000 $25,000 Electric Utility Fund Water Fund Sewer Fund Total $25,000 $25,000 Alternatives Continue to operate mower with increasingly higher repair costs and downtime. Project Effect on Operating Budget None - 33 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST .CTIVrl[Y: Equipment Maintenance REQUEST TITLE: Turf Vehicles Project Description . Purchase (3) turf vehicles to replace three turf units. Turf vehicles M1, M2 and TV -21 Project Objectives To provided Parks Division employees with safe and reliable equipment to perform there job duties in a proficient manner. Existing Situation These vehicles are used to prepare our athletic fields and maintenance of our parks. Project Work Completed These vehicles are currently on a replacement schedule of 10 years and meet the criteria of the Fleet Policies and Procedures. schedule and Project Costs Prior Project Budgets 1999-00 2000-01 2001-02 2002-03 Total Phasing Study Design Acquisition $60,000 $60,000 Construction Total $60,000 $60,000 Recommended Funding Sources Capital Outlay Fund Electric Utility Fund Water Fund Sewer Fund Total Alternatives Continue to operate vehicles with increasingly higher repair cost and downtimes. Project Effect on Operating Budget None - 34 - $60,000 $60,000 $60,000 $60,000 COMMUNITY & ECONOMIC DEVELOPMENT BUILDING PLANNING CODE ENFORCEMENT ENGINEERING ECONOMIC DEVELOPMENT 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: COMMUNITY IMPROVEMENT REQUEST TITLE: PURCHASE ONE MINI -VAN FOR COMMUNITY IMPROVEMENT OFFICER Project Description: Purchase and equip one mini -van to be used for code enforcement related field investigations and inspections by the Community Improvement Officer. Project Objectives: Provide a safe and reliable vehicle for the Community Improvement Officer. A mini -van would allow for stora;e and better access to the necessary tools, equipment and materials necessary in conducting field inspections for the Community Improvement Division. Existing Situation: This van will replace car #75, which was a police vehicle prior to being utilized by the Community Improvement Division. Car 475 is a 1992 Ford Crown Victoria sedan with 106,201 miles. Project Work Completed: The vehicle is overdue for replacement. Schedule and Project Costs Prior Project Budsets 2001-02 2002-03 2003-04 2004-05 Total Phasing Study Design Acquisition 525,000 Construction Total $25,000 Recommended Funding Sources $26,000 General Fleet Fund Projected Effect on Operating Budget - 35 - 2001-03 Financial Plan and Budget Request CAPITAL IMPROVEMENT BUDGET REQUEST ACTIVITY: Building & Safety REQUEST TITLE: Purchase Two Field Inspection Pickup Trucks Project Description: Purchase two t/2 ton pickup trucks with king cabs and 8 -foot boxes. Vehicles to be used for residential and commercial field inspection. Project Objectives: Provide safe and reliable vehicles for the field inspectors. Existing Situation: Truck 79 and 89, 1992 Chevrolet S -10's, have been in service for a full 10 years. They were due for replacement 3 years ado. Truck 79 has 53,170 miles and 89 has 76,324 miles. Both trucks arc overdue for replacement. Project Work Completed: N/A Schedule and Projects Costs Prior Budgets 2001-02 2002-03 2003-04 2004-05 Phasing Stud Design Acquisition $48,800 Construction Total 548,800 Recommended Funding Sources Capital OutlaFund Enterprise Funds General Fleet Fund $48,800 Project Effect on Operating Budget - 36 - GENERAL GOVERNMENT LEGISLATION ryl,. ADMINISTRATION CITY CLERK SUPPORT SERVICES NON - DEPARTMENTAL 2001-03 Financial Plan and Budget Request CAPITAL UVIPROVEMENT BUDGET REQUEST ACTIVITY: Finance Field Services REQUEST TITLE: 'Vehicle Replacement Project Description Purchase one (1) replacement vehicle for Field Services use. A Meter Reader uses this vehicle daily. r Project Objectives Provide a safe, reliable vehicle for the Field Services employees. The majority of their duties are in the field, performing scheduled work that must be completed within a certain timetable, usually that day. Existing Situation Vehicle #02088 is a 1990 Plymouth hatchback and has 74,047 miles on the odometer. A Meter Reader uses this vehicle daily to carry equipment used for job duties that include reading electric and water meters and for installation of angle meters. Total repair and maintenance costs are $12,837.62. This vehicle exceeds the recommended replacement guideline of 7 years old/60,000 miles. Project Work Completed The Fleet Committee will approve and make recommendations to locate a vehicle for purchase. Schedule and Project Costs Prior Project Budgets 2001-02 2002-03 2003-04 2004-05 Total Phasing Study Design Acquisition Construction Total Recommended Funding Sources Capital Outlay Fund Enterprise Funds Alternative $22,000 $22,000 The alternative is to continue using the existing vehicle. However, when this vehicle is in the shop for repairs, a motor -pool loaner vehicle is used, which is unable to hold all of the equipment that the employee uses to perform their duties. -37 -