HomeMy WebLinkAboutAgenda Report - December 17, 1997 (104)AGENDA TITLE: Acceptance of Improvements Under Fairmont Avenue Street Improvements
(Kettleman Lane to Vine Street) and Lockeford Street Street Improvements (500 Feet
West of Ham Lane to Ham Lane, and California Street to Pleasant Avenue) Contract
MEETING DATE: December 17, 1997
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Fairmont Avenue
Street Improvements (Kettleman Lane to Vine Street) and Lockeford Street
Street Improvements (500 Feet West of Ham Lane to Ham Lane, and
California Street to Pleasant Avenue)" contract and direct the City Engineer
to file a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The project was awarded to Granite Construction Company, of
Stockton, on June 18, 1997, in the amount of $256,378.70. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
The contract completion date was September 25, 1997, and the actual completion date was
October 15, 1997. The final contract price was $271,142.42. The difference between the contract
amount and the final contract price is mainly due to an increase in the contract quantities for concrete
work and pavement repair areas.
FUNDING: As determined at contract award.
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/Im
cc: Purchasing Officer
Street Superintendent
APPROVED:
caoopt.doc
Jac L. Ronsko
Publik Works Director
H. Dixon Flynn -= City Manager
12/05/97