HomeMy WebLinkAboutAgenda Report - November 5, 1997 (63)CITY OF LODI COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Well 4R Water Storage Tank and Pump
Station, 1215 Thurman Street, Contract
MEETING DATE: November 5, 1997
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Well 4R Water
Storage Tank and Pump Station, 1215 Thurman Street" contract, and
direct the Public Works Director to file a Notice of Completion with the
County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Conco West, Inc., of Manteca on
April 23, 1996 in the amount of $1,222,300.00. The contract has
been completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was May 22, 1997, and the actual completion date was October 24, 1997.
The difference in the completion dates is due to delays in delivery of City -furnished equipment that was
integral to the completion of the project as a whole. The final contract price was $1,372,571.13. The
difference between the contract amount and the final contract price is outlined in the attached change
order summary.
The bulk of the cost of this project is funded by a low-interest loan through the Department of Water
Resources. Fifty percent of the actual costs of this project will be reimbursed through the DBCP
settlement.
FUNDING: Water Fund
Prepared by Mark Lindseth, Associate Civil Engineer
JLR/MUpmf
Attachment
cc: Purchasing Officer
Water/Wastewater Superintendent
. Ronsko
Works Director
APPROVED:
H. Di on Flynn -- Ci Manager
Cacceptdoc 10/28/97 go
CITY OF LODI
CHANGE ORDER LOG
PROJECT: WELL NO. 4R WATER STORAGE TANK AND PUMP STATION
CONTRACTOR: CONCO WEST Inc.
CONSULTANT: MONTGOMERY WATSON AMERICAS, INC.
DATE PRINTED: 1011197
CO
NUMBER
DESCRIPTION
OF
CHANGE
NEG
COST
1
RFI 2001 Add electrical grounding grid to site
35,587.39
2
jRFI 7 Delete PVC rigid conduit requirement CREDIT
-2,600.00
3
RFI 2002 Delete water softener at pump building CREDIT
-7,754.00
4
RFI 18 Add thrust blocks at underground piping
1,092.15
5
RFI 2003 Building structural changes required by Building Dept.
7,410.21
6
Added work at existing manholes and piping due to unknown conditions
833.84
7
16" Storm drain pipe conflict with 8"backwash pipe line
648.94
8
Add plumbing waste line trap rimers
1,354.27
9
Chlorine Generation System
61,144.79
10
Epoxy Coating System at Steel Water Tank
7,323.06
11
OVER EXCAVATION OF TANK AND BUILDING FOOTINGS
12,796.05
12
STEEL ROOF TRUSS CHANGE
1,474.50
13
CAULK AT WATER TANK ROOF LAP JOINTS
3,409.82
14
ADD IRRIGATION SHUTOFF VALVE
235.91
15
ADD 2 V CONDUITS TO MCC PANEL
820.00
16
ADD FUEL TANK LEAK DETECTER
1,170.65
17
RELOCATE ELECTRIC METER PER EUD REQUEST
867.47
18
OVEREXCAVATION OF FOOTING AGREEMENT
2,613.00
19
MOVE FAN SWITCH, ADD PHONE AND INJECTOR VALVE
1,566.00
20
Add altitude valve, Booster pump and Hi -pressure cut off
18,338.08
21 Add Cla-val 3/8" pump control valves to pilot system 1.939.00
Change Order Total To Date
150,271.13
Original Contract
1,222,300.00
Total Contract To Date
1,372,571.13
CHANGE ORDER PERCENT OF ORIGINAL CONTRACT
12.29%